Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
General Information
-
Person Conducting Audit
-
Section
-
Shift
-
Date
Activity
-
Does the shift planning meeting start on or before 5:30 ( am or pm)?
-
Are all who are requiered to attend present and on time?
-
Is the handover conducted in an organised manner, free from distraction and interruptions?
-
Has the meeting agenda been followed?
-
Has the Section Leader attend at some point during the meeting and look at the shift plan?
-
Plan Quality: Does the plan include all activities?
-
Does the planned work meet the shift budget?
-
Are copies of the shift plan distributed to all concerned?
-
Do the locations and targets issued to the operators on theirline out match the shift plan?
-
Is the line out discussed with the Operators?
-
Is Control provided with the hourly targets for the key machines in their section? ( via the plan or other wise)
-
Is firs bucket at 6:30 (am or pm)?