Information
-
Precast Quality Spot Check Audit Report
-
Location
- Alnwick
- Byley
- Cadeby
- Drakelow
- Ellistown
- Grantham
- Knockloughrim
- Lisnaskea
- Littleport
- Lydney
- Telford
- Weston Underwood
-
Date:
-
Spot Check By:
Concrete Sampling and Testing
-
Person responsible:
EQUIPMENT AND TOOLS
-
Cubes moulds cleaned, oiled and in tolerance
-
Sampling equipment available and clean
-
Cube crushing machine in service and clean
-
Vibrator table / cube making equipment clean and in working order
CONCRETE SAMPLING
-
Concrete for cube making sampled at correct time & loaction
-
Lifting cubes made correctly covered and placed with product
-
7 & 28 day cubes made and stored at correct temperature before demoulding
CUBE CRUSHING FOR BED RELEASE
-
Cube crushed before bed released
-
Results of cube crushing entered onto record sheet
-
Results of cube crush values passed back to QC
-
Other Areas of Concern / Needing Action:
Areas
-
Select areas to be spot checked
- CASTING AREA 1 [ insert name ]
- CASTING AREA 2 [ insert name]
- CASTING AREA 3 [insert name]
- CASTING AREA 4 [insert name]
-
AREA 1 -
-
Person Responsible:
INSPECTION DOCUMENTATION
-
Drawings checked to ensure correct revision is used
-
Any issues highlighted on drawing addressed and confirmation to cast agreed by management
-
Pre / Post pour check sheet filled in & signed off as ok to pour
-
QC checks completed and documentation filled in and signed off
MOULD CONDITION
-
Mould surfaces clean & oiled with no defects
-
Shuttering in good condition, all chamfers in place and in good condition
-
Cast in inserts secured and cover checked
-
Reinforcement/mesh in place with spacers attached and cover checked
PRODUCTION
-
Concrete sampled for consistance
-
Mould cast ensuring no movement of cast in inserts or reinforcement
-
Mould floated off and any required inserts placed in concrete checked to ensure inserts can not sink or move out of position
POST PRODUCTION
-
Post cast checks completed and documentation signed off
-
Any remedial required is identified and recorded
-
Other Areas of Concern / Needing Action:
-
AREA 2 -
-
Person Responsible:
INSPECTION DOCUMENTATION
-
Drawings checked to ensure correct revision is used
-
Any issues highlighted on drawing addressed and confirmation to cast agreed by management
-
Pre / Post pour check sheet filled in & signed off as ok to pour
-
QC checks completed and documentation filled in and signed off
MOULD CONDITION
-
Mould surfaces clean & oiled with no defects
-
Shuttering in good condition, all chamfers in place and in good condition
-
Cast in inserts secured and cover checked
-
Reinforcement/mesh in place with spacers attached and cover checked
PRODUCTION
-
Concrete sampled for consistance
-
Mould cast ensuring no movement of cast in inserts or reinforcement
-
Mould floated off and any required inserts placed in concrete ensuring inserts can not sink or move out of position
POST PRODUCTION
-
Post cast checks completed and documentation signed off
-
Any remedial required is identified and recorded
-
Other Areas of Concern / Needing Action:
-
AREA 3 -
-
Person Responsible:
INSPECTION DOCUMENTATION
-
Drawings checked to ensure correct revision is used
-
Any issues highlighted on drawing addressed and confirmation to cast agreed by management
-
Pre / Post pour check sheet filled in & signed off as ok to pour
-
QC checks completed and documentation filled in and signed off
MOULD CONDITION
-
Mould surfaces clean & oiled with no defects
-
Shuttering in good condition, all chamfers in place and in good condition
-
Cast in inserts secured and cover checked
-
Reinforcement/mesh in place with spacers attached and cover checked
PRODUCTION
-
Concrete sampled for consistance
-
Mould cast ensuring no movement of cast in inserts or reinforcement
-
Mould floated off and any required inserts placed in concrete ensuring inserts can not sink or move out of position
POST PRODUCTION
-
Post cast checks completed and documentation signed off
-
Any remedial required is identified and recorded
-
Other Areas of Concern / Needing Action:
-
AREA 4 -
-
Person Responsible:
INSPECTION DOCUMENTATION
-
Drawings checked to ensure correct revision is used
-
Any issues highlighted on drawing addressed and confirmation to cast agreed by management
-
Pre / Post pour check sheet filled in & signed off as ok to pour
-
QC checks completed and documentation filled in and signed off
MOULD CONDITION
-
Mould surfaces clean & oiled with no defects
-
Shuttering in good condition, all chamfers in place and in good condition
-
Cast in inserts secured and cover checked
-
Reinforcement/mesh in place with spacers attached and cover checked
PRODUCTION
-
Concrete sampled for consistance
-
Mould cast ensuring no movement of cast in inserts or reinforcement
-
Mould floated off and any required inserts placed in concrete ensuring inserts can not sink or move out of position
POST PRODUCTION
-
Post cast checks completed and documentation signed off
-
Any remedial required is identified and recorded
-
Other Areas of Concern / Needing Action:
Yard - Stack and Load
-
Person Responsible:
INSPECTION OF LOADS
-
Product supported on the trailer correctly with label/markings visible
-
No loading or handling damage visible <br><br>
-
Any remedial work completed on units is of acceptable standard
-
Delivery ticket checked and signed off
REMEDIAL WORK -YARD
-
All remedial work carried out of an acceptable standard
-
QC checks completed also covering any repairs and signed off
YARD STORAGE OF PRODUCT
-
Units placed in correct location and supported correctly ensuring no damage/ distortion can occur during curing
-
QC checks completed and documentation completed and signed off
-
Unit identification legible
FINAL DELIVERY INSPECTION
-
All documentation for loads seen completed and signed off
-
Units on loads inspected were stacked correctly with no visible damage
-
All units marked as good to go
-
Other Areas of Concern / Needing Action