Title Page
Introduction
-
This Project Checklist is to be completed in accordance with the audit procedure outlined in SOP02.
-
To begin a project audit, review the audit sections and questions.
Once you are familiar with these audit sections you can begin collecting evidence.
You need evidence in order to answer the questions.
You collect your evidence by reading documents, checking records, examining data, observing activities.
As you collect your evidence, you answer each audit question and record your observation in the relevant column. Three responses are possible: Pass, Fail and N/A. -
• A Pass response means that the document is in compliance with the quality management system (QMS).
• A Fail response means that the document is not in compliance with the QMS, for any reason.
• An N/A response means that the query is not applicable to the current situation -
Once the audit checklist is completed, list all your Fail responses and summarise your evidence.
Non-conforming responses are raised as a Corrective and Preventive Action (CAPA) in the Crest SharePoint Tasks list.
Project Information
-
Project Sale Type
-
Other
-
Project Code
-
Project Description
Audit Information
-
Conducted on
-
Auditor:
-
Audit Approved By:
Sales Lifecycle
General
-
Is Job on CRM with SharePoint Folder?
-
Are Videos/Images stored appropriately on File-store?
-
Are Samples recorded in CRM and stored in the correct Location?
-
Has the Lab Evaluation Report been made available in SharePoint?
-
Is the M2 checklist available for inspection?
-
Does the M3 Move Folder have the final version of the Quote, URS, Costings & PO?
-
Has the signed/agreed URS/SOW been uploaded onto the system?
Costings
-
Is the Master costings available on SharePoint?"
-
Does the costing match the TP1 items on system?"
-
Has the Approved Crest template been used?
Quote
-
Is the read only quote available on SharePoint?
-
Does the master word copy match the read only copy on SharePoint?
-
Has the Approved Crest template been used?
PO (Purchase Order) Information
-
Does PO Value match the Quote?
-
Does all PO details meet the expected requirements?
-
Is the PO verification checklist available for inspection?
M3 Activities
-
Is the M3 checklist available for inspection?
-
Was all necessary information required for handover captured in the M3 Checklist?
Project Lifecycle
M4 Activities
-
Is M4 checklist made available for inspection?
-
Has the project schedule been uploaded to the system and clearly identifies key resources and delivery timelines?
-
Has the BOM available and uploaded to the system?
-
Are the Serial Numbers of the hardware recorded on the system?
-
Is the Project Schedule available, up to date and uploaded to the system?
-
Is the FDS Drafted and uploaded to the system?
-
If applicable, is the VP Reviewed and Approved and uploaded to the system?
-
If applicable, is the BOM up to date and uploaded to the system?
-
Has the OC number been entered on the system?
-
Are the Serial Numbers of the hardware recorded on the system?
M5 Activities
-
Is the M5 checklist made available in the Sign off folder?
-
Have the Electrical and Mechancial drawings been uploaded to the system?
-
Have the design documents been reviewed and approved and uploaded to the system?
-
Have the validation documents been reviewed and approved and uploaded to the system?
-
Are the project documents inline with the approved naming convention according to SOP05?
-
Are inspection files (jobfiles, visionPro, PLC) inline with the approved naming convention?
-
Is the CE Cert available for inspection (only if electrical panels have been supplied)?
-
Are AV Electrical Drawings/Mechanical Drawings uploaded to the system?
Vision Only
-
Have the inspection files been uploaded to system?
-
Is Master copy available in VSO?
-
Is it clearly identifiable that change control has been applied to drawings post FAT activities?
-
It is clearly identifiable that version control has been applied to Drawings post FAT activities?
-
It is clearly identifiable that version control has been applied to Inspection files post FAT activities?
M6 Activities
-
Is the M6 checklist made available in the Sign off folder?
-
Have the executed copies of the validation docs been uploaded to the system?
-
Has the validation report been signed by customer?
-
Is the Issues log available for inspection on the system?
-
Have the system backup files (for FAT and SAT/IQOQ) been uploaded to the correct location on the system?
-
Is the Line Configuration Files available for Inspection?
-
Has the project closeout meeting taken place and minutes available?
-
Have the lessons learned been documented and logged?