Site conducted
-
Project Name
-
Project Manager
-
Conducted on
-
Prepared by
Audit Questions - Project Management
-
Has a formal project handover been completed from Estimator to Project Manager?
-
Is there a current Project File available?
-
Has administration been notified of successful tender?
-
Has a Project Risk Assessment been completed for this project?
-
Has JDN-Form-200 Work Checklist - Project been completed?
-
Has JDN-Form-201 Work Checklist - Principal Contractor been completed?
-
Has JDN-Form-202 Work Checklist - Site been completed?
-
Has JDN-Form-203 Work Checklist - Estimator been completed?
-
Is there a Blue Site Folder for this project?
-
Is there a SWMS developed for this project?
-
Has an ITP, PMP, PQP been developed?
-
Has a EMP been developed?
-
Has a Compaction Test Schedule/s been developed?
-
Has Dial B 4 U Dig been undertaken?
-
Has site service location been undertaken?
-
Are suppliers / sub-contractors selected from the Preferred Suppliers list?
-
Have files been nominated in the APE Upload folder by the Project Manager?
-
Have the Operations Manager and Site Supervisor been briefed?
-
Variation advice/s generated?
-
Have monthly claims been forwarded to accounts administration?
Audit Questions - Administration
-
Has a job folder been established on the shared drive under Current Projects?
-
Has the Project List been updated and new project entered into Buildsmart and APE?
-
Has administration been notified by the Project Manager regarding APE uploads?
-
Has administration uploaded required files onto APE?
-
Has administration forwarded claims to client?
-
Have claims been approved by client?
-
Have claims been paid by client within agreed time frame?