Title Page
-
Site conducted
-
Office
-
Engineer
-
Customer
-
Location
-
FLM
-
Contract No
-
Auditor
-
Select date
-
Conducted on
Revision Information
-
This form is the equivalent to Q2233 issue 0 and Q2234 issue 1 combined. This form is electronic issue 1 - 15/08/2016
ALL SYSTEMS DESIGN CONSIDERATIONS
-
The Auditor must be conversant with BS5839, BS6266, BS7671, LPS1014 and Company Procedures.
-
Where Variations have been listed and agreed, deviation points are not added.
-
Have consultations taken place with the interested parties and where applicable have Variations agreed?
-
Please provide details / reasons
-
Where a standard has been stated as a requirement has the equipment been chosen to comply?
-
Please provide details / reasons
-
Has the Cause and Effect been documented?
-
Please provide details / reasons
ALL SYSTEMS WITH DETECTION INSTALLED
-
Is the detection fitted so that there is no point further than 7.5M from a smoke detector or 5.3M from a heat detector?
-
Please provide details / reasons
-
In pitched roofs are the detectors fitted no more than 600mm or 150mm for smoke and heat, from the apex?
-
Please provide details / reasons
-
Are the point detectors fitted on solid not mesh ceilings?
-
Please provide details / reasons
-
Are the ceiling heights below 10.5M for smoke detectors or 9.0M for Grade 1 heat detector? (Except rapid attendance)
-
Please provide details / reasons
BS5839 P1
-
Is BS5839 P1 applicable to the system being audited?
-
Is detection fitted throughout the building, including any ceiling voids greater than 800mm, the top of all voids and shafts, on the landing of all enclosed stairwells?
-
Please provide details / reasons
-
Is there detection fitted within 1.5M of all vertical shafts that penetrate the floors or ceilings?
-
Please provide details / reasons
-
Is there any detection in any "Lantern Lights" or other ceiling vents/penetrations greater than 800mm deep?
-
Please provide details / reasons
-
Where sounders are fitted are these sufficient to give sound levels as for life protection?
-
Please provide details / reasons
BS5839 P2
-
Is BS5839 P2 applicable to the system being audited
-
Is there clear and unambiguous description of the area of detection coverage?
-
Please provide details / reasons
-
If manual call points are not fitted is this clearly stated?
-
Please provide details / reasons
BS5839 L1
-
Is BS5839 L1 applicable to the system being audited?
-
Check all the points for "P1" plus is there a minimum of two sounder circuits installed throughout the building? (An external sounder is not required)
-
Please provide details / reasons
BS5839 L2
-
Is BS5839 L2 applicable to the system being audited?
-
Check all the points for "L3" plus is/are the additional detection areas(s) clearly specified?
-
Please provide details / reasons
BS5839 L3
-
Is BS5839 L3 applicable to the system being audited?
-
Are all circulation and escape routes including rooms opening onto escape routes fitted with detection?
-
Please provide details / reasons
BS5839 L4
-
Is BS5839 L4 applicable to the system being audited?
-
Are all circulation and escape routes fitted with detection?
-
Please provide details / reasons
BS5839 L5
-
Is BS5839 L5 applicable to the system being audited?
-
Are all areas within the assessed fire risk fitted with detection or have the device locations been specified by the customer?
-
Please provide details / reasons
BS5839M
-
Are all call points fitted to all exits to the open air, not in an approach, and at a maximum search distance of 45M?
-
Please provide details / reasons
-
Are call points fitted at 1.4M (+/- 200mm)?
-
Please provide details / reasons
MAINS POWER TO ALL EQUIPMENT
-
Is continuity of supply satisfactory?
-
Please provide details / reasons
-
Is the circuit dedicated?
-
Please provide details / reasons
-
Is it correctly labelled?
-
Please provide details / reasons
-
Is there not RCD fitted?
-
Please provide details / reasons
-
Is the wiring standard/enhanced category?
-
Please provide details / reasons
DETECTORS
-
Are the types of detector suitable for sitings?
-
Please provide details / reasons
-
Are sensitivities set to approved values?
-
Please provide details / reasons
-
Do the clear 2x the depth of ceiling obstructions?
-
Please provide details / reasons
-
Are detectors greater than 500mm from walls?
-
Please provide details / reasons
-
Is compliance with the relevant BS/EN claimed and are they marked to show this?
-
Please provide details / reasons
MANUAL CALL POINTS
-
Is compliance with EN54-11 claimed?
-
Please provide details / reasons
-
Are call points marked to show compliance?
-
Please provide details / reasons
ZONING
-
Are the areas per zone within the limits specified in the installation rules (2000M Square)?
-
Please provide details / reasons
-
Is the search distance less than 60M?
-
Please provide details / reasons
-
Are remote indicators supplied as needed?
-
Please provide details / reasons
-
Are the fire boundaries/compartments appropriate?
-
Please provide details / reasons
CONTROLS AND INDICATING EQUIPMENT
-
Please show control equipment
-
Is compliance with EN54-2 claimed?
-
Please provide details / reasons
-
Are all panels marked to indicate compliance?
-
Please provide details / reasons
-
Is the siting appropriate and protected?
-
Please provide details / reasons
-
Is there suitable security over access to controls?
-
Please provide details / reasons
-
Are Zone Plans displayed as required?
-
Please provide details / reasons
-
Is internal workmanship satisfactory?
-
Please provide details / reasons
DOCUMENTATION
-
Has a document box been installed containing relevant documents?
-
Please provide details / reasons
-
Are all required commissioning records complete?
-
Please provide details / reasons
-
Is there a log book?
-
Please provide details / reasons
-
Is there a certificate against the installation rules?
-
Please provide details / reasons
-
Are there satisfactory as fitted drawings?
-
Please provide details / reasons
-
Are there satisfactory O&M Manuals?
-
Please provide details / reasons
SYSTEM POWER AND STANDBY SUPPIES
-
Please show power supplies
-
Is the PSU suitable for the systems type?
-
Please provide details / reasons
-
Are batteries of a suitable type and dated?
-
Please provide details / reasons
-
Is any interconnecting wiring suitable?
-
Please provide details / reasons
-
Are battery calcs accurate, available and verified?
-
Please provide details / reasons
-
Is the standby supply to any VDU provided to satisfy installation rules satisfactory?
-
Please provide details / reasons
-
Are Spurs double pole unswitched, dedicated and labelled?
-
Please provide details / reasons
-
Are all batteries properly secured?
-
Please provide details / reasons
-
Is battery Ah less than charger o/p - load x 24 or tho contract?
-
Please provide details / reasons
-
Is load x24 + alarm x 0.5 less than the battery Ah or the site requirements (unoccupied + 24hrs)?
-
Please provide details / reasons
-
Is charger rating sufficient for full alarm load?
-
Please provide details / reasons
-
Is any interconnecting wiring suitable?
-
Please provide details / reasons
REMOTE TRANSMISSION OF ALARMS
-
If LPC installation, is it approved?
-
Please provide details / reasons
-
Is the wiring mechanically/fire protected?
-
Please provide details / reasons
-
Is fault signalled?
-
Please provide details / reasons
ANCILLARY SERVICES
-
Is the interface satisfactory?
-
Please provide details / reasons
-
Is no load taken from the fire system in the quiescent state?
-
Please provide details / reasons
-
Are they separately fused?
-
Please provide details / reasons
SERVICING AND SPARES
-
Are spares held on site without maintenance contract?
-
Please provide details / reasons
CABLES
-
Does the area per loop satisfy installation rules?
-
Please provide details / reasons
-
Does the number of zones per loop meet LPC rules (LPC installations only)?
-
Please provide details / reasons
-
Is there adequate short circuit isolation?
-
Please provide details / reasons
-
Are the location of line isolators appropriate?
-
Please provide details / reasons
-
Does the removal of detection isolate call points?
-
Please provide details / reasons
-
Are there no spurs on conventional sounder circuits?
-
Please provide details / reasons
-
Are cables of a suitable type?
-
Please provide details / reasons
-
Are cables suitably mechanically and fire protected?
-
Please provide details / reasons
-
Are joints suitably terminated?
-
Please provide details / reasons
-
Are all joint boxes labelled and on drawings?
-
Please provide details / reasons
-
Is there segregation where needed between cables?
-
Please provide details / reasons
-
Is there evidence to show that cable parameters meet manufacturers requirements?
-
Please provide details / reasons
-
Are insulation test results logged and satisfactory?
-
Please provide details / reasons
-
Are cables fixed supported to meet the requirements of BS5839-1 26.2.4 (F)?
-
Please provide details / reasons
-
Are all penetrations fire stopped?
-
Please provide details / reasons
VISUAL AND AUDIBLE ALARMS
-
Are there at least 2x sounder circuits?
-
Please provide details / reasons
-
Are the units sited to give needed sounder levels?
-
Please provide details / reasons
-
Is there logged sounder db readings?
-
Please provide details / reasons
-
Can Fire Brigade be called with alarms sounding?
-
Please provide details / reasons
-
Does the sounder pattern and frequency comply with the installation rules?
-
Please provide details / reasons
-
Are visual indicators adequate?
-
Please provide details / reasons
Workmanship
-
Grade the overall workmanship 0 to 5 where 0 is Good and 5 is Poor
- 0
- 1
- 2
- 3
- 4
- 5
Product Audit Score
-
Please select audit score
-
Please ensure a copy of this audit is sent to your QEHS Specialist for review
-
Please ensure a copy of this audit is sent to your QEHS Specialist for review
-
Please ensure a copy of this audit is sent to your QEHS Specialist for review
Environmental, Heath & Safety Summary
-
In the opinion of the auditor does the engineer work and act in a safe manner?
-
Please provide details / reasons
-
Does the engineer require any EHS refresher training? (if yes, please state requirement)
-
Please provide details / reasons
-
Does the engineer dispose of waste as per company requirements?
-
Please provide details / reasons
-
Is the engineer trained in all aspects of work related Health & Safety?
-
Please provide details / reasons
-
Has the engineer, subcontractor been issued with up to date risk assessments?
-
Please provide details / reasons
-
Did the engineer spot any near miss, unsafe acts or conditions during the audit?
-
Please provide details of the near miss or unsafe acts and if they have been correctly reported
-
Training requirements (if any)
-
Please provide details / reasons
Sign Off
-
Engineer Signature:
-
Auditors Signature:
Post audit
-
The following items are for post audit use should they be required
-
Any Notes & Observations
-
Preventative Actions (i.e. Training):
-
Proposed Preventative Action Close Out Date:
-
Corrective Actions:
-
I confirm that the corrective action has been completed
-
Add signature
-
I confirm that the preventative action has been completed
-
Add signature