Title Page
-
Conducted on
-
Prepared by
-
Location
Doors & Finishing Lines
Doors Requirements
-
Correct door installed in specified location
-
Door installed plumb and level
-
Fire door has correct spacing from trim to frame opening for fire sealant
-
Fire door has correct floor gap as per manufacturer specifications
-
Fire door smoke seals installed
-
Any additional photos, comments and observations
-
Subcontractor QA received, attached and approved
Finishing Lines
-
All finishing lines are correct as per architects specification
-
Finishing lines installed correctly with specified glue and sufficient fixings
-
All finishing lines install complete
-
Subcontractor QA received, attached and approved
Second Fix Services
Electrical
-
Subcontractor QA received, attached and approved
-
Second fix completed
Plumbing
-
Subcontractor QA received, attached and approved
-
Second fix completed
Mechanical
-
Subcontractor QA received, attached and approved
-
Second fix completed
Fire Alarms
-
Subcontractor QA received, attached and approved
-
Second fix completed
Fire Sprinklers
-
Subcontractor QA received, attached and approved
-
Second fix completed
Security
-
Subcontractor QA received, attached and approved
-
Second fix completed
Data / Comm’s
-
Subcontractor QA received, attached and approved
-
Second fix completed
Painting
Painting Requirements
-
Paint specifications and colour correct to specification
-
Seal coat complete
-
Light inspection complete
-
Additional paint application complete
-
Final coat application complete
-
Subcontractor QA received, attached and approved
Finishes
Flooring Requirements
-
Floor preparation to concrete slab complete
-
Correct flooring is installed as per manufacturer specifications
-
All flooring is adhering to the specified glue compound and complete
-
All transition bars are installed in correct locations with sufficient fixings
-
Flooring protection is installed
-
Subcontractor QA received, attached and approved
Cabinetry
-
All cabinetry is installed in correct location
-
Cabinetry is installed plumb and level
-
All cabinetry components and hardware are installed as per specification
-
All sealant, kickboards, screw caps and miscellanies are complete
-
Subcontractor QA received, attached and approved
Hardware
-
All hardware is installed correctly as per manufacturer specifications
-
All hardware is installed in the correct location
-
All hardware components are installed
-
Subcontractor QA received, attached and approved
Miscellaneous
-
Subcontractor QA received, attached and approved
QA Complete
-
Finishes inspection confirms all items are complete to the checklist requirements