Title Page
-
Conducted on
-
Prepared by
-
Location
-
Project Number & Name
-
PC Date
1. Initiation – Sales & Estimation
-
1.1 Was the job quoted realistically?
-
1.2 Did sales get any help from engineering from others for the design?
-
1.3 Did we get enough time to price it?
-
1.4 Was the process correctly followed?
2. Project Planning
-
2.1 Did the job get opened and contract admin completed in a timely manner?
-
2.2 Did we have sufficient time to plan and what planning was done?
-
2.3 Was there a sales handover meeting with sales, projects & engineering? If no, why?
-
2.4 Did the designs get engineering checked?
-
2.5 Were resources already tentatively booked for the project?
-
2.6 Did we review the equip procurement process including when we could get paid for equip?
-
2.7 Were procurement periods reviewed to determine if late goods needed to be substituted?
-
2.8 Were there any other issues related to planning?
-
2.9 Was there any equipment quoted with known problems in the job? If yes, what?
3. Project Execution
-
3.1 Was there sufficient information available at project commencement on site?
-
3.2 Did we have enough plant and tools to start the job?
-
3.3 Were the designs sufficiently developed to build a working system?
-
3.4 Was there enough information on the drawings?
-
3.5 Were there factors that delayed the project execution and if so what were they?
-
3.6 Did equipment get delivered in time for installation and was any of it incorrect?
-
3.7 Did we have enough labour resources?
-
3.8 Review job cost report to determine efficiency or estimating irregularities.
-
3.9 Was the job delivered within budget? If over budget, why?
-
3.10 Was the job delivered on time?
-
3.11 How were any variations managed, if any?
-
3.12 Were there any other issues related to project execution?
4. Project Closing
-
4.1 Was commissioning sufficiently planned?
-
4.2 Did site staff have cabling tested and equipment power up tests done before TRG arrived?
-
4.3 Was installation complete before the Field Engineer and Programmers attended site?
-
4.4 Was there sufficient time to fully commission before handover and training?
-
4.5 Was there any stage of commissioning that required extra time due to equipment complications and/or installation issues?
-
4.6 Was there any stage of programming that required extra time due to equipment complications and/or installation issues?
-
4.7 Were the manuals submitted on time?
-
4.8 Has the job handover been completed and sent to service, CA, projects admin & stores?
-
4.9 Were there any other issues related to execution?
-
4.10 Are there any ongoing defects that need to be addressed?
-
4.11 Do you think the client would recommend or use our services again?
5. Project Outcomes
-
5.1 What were the key factors that influenced project outcome?
-
5.2 What processes need to be reviewed or improved to ensure successful future projects?
6. Comments
-
6.1 Would you like to provide any additional feedback about the project?