Title Page

  • Conducted on

  • Prepared by

  • Location

Section 1 - Site Setup and storage

  • 1.1 - Are materials and equipment stacked/stored in a safe manner? No risk of falling materials.

  • 1.2 - Have suitable welfare facilities been provided on site for the current and foreseen workforce.

  • 1.3 - Have transient folders been issued?

  • 1.4 - Are walkways and pedestrian routes maintained in a safe condition?

  • 1.5 - Is access and egress and signage appropriate?

  • 1.6 - Are all significant risks and impacts identified and controlled?

  • 1.7 - Is fencing appropriate for site size and location and is it well maintained?

  • 1.8 - Have adequate storage facilities been provided and are they racked out and/or well organised and secure?

  • 1.9 - Are welfare facilities maintained to a suitable standard?

  • 1.10 - Is all signage professionally manufactured?

  • 1.11 - Has site security been considered and control measures implemented?

  • 1.12 - Has the site compound and/or set up been properly organised?

  • 1.13 - Are all minor risks and impacts controlled?

Section 2 - Public Protection and Community Relations

  • 2.1 - Are the public protected from falling objects?

  • 2.2 - Are all significant hazards in areas where the public have access controlled?

  • 2.3 - Are excavations in public areas adequately guarded and signage in place?

  • 2.4 - Are all significant risks and impacts identified and controlled?

  • 2.5 - Is temporary floor protection adequately managed?

  • 2.6 - Is adequate warning signage provided for the public?

  • 2.7 - Where existing lighting is obscured/disconnected/removed have alternatives been provided?

  • 2.8 - Is segregation of public carried out using proper pedestrian barriers where applicable?

  • 2.9 - Are emissions from processes adequately controlled (noise / dust / fumes)?

  • 2.10 - Are other minor risks and impacts to the public controlled?

Section 3 - Administration and Management (Health and Safety)

  • 3.1 - Is the Construction Phase SHE Plan available and regularly reviewed and updated if required?

  • 3.2 - Are all works in progress covered by a suitable and sufficient Risk Assessment and Method Statement and evidence that these have been briefed to the workforce?

  • 3.3 - Does the site have suitable First Aid cover and complete first aid supplies relevant to works on site with the contents in date?

  • 3.4 - Is there an Accident book available if there is no intranet access?

  • 3.5 - Is statutory information displayed on the project board (F10, HSE poster, insurance, policies, nearest hospital and eye clinic)?

  • 3.6 - Have all previous Corrective Actions been closed out from from previous visits? (GO Visits, Health Checks)

  • 3.7 - All significant admin/management issues controlled?

  • 3.8 - Have permits to work been used correctly where required and are they filed?

  • 3.9 - Have statutory inspections been carried out as required and are they filed? (Scaffold, Excavations, Equipment, Van Inspection and SHE Inspections)

  • 3.10 - Is there a process for signing in/out?

  • 3.11 - Is there evidence that all people have been inducted on site using the Induction PowerPoint Presentation and site specific project board?

  • 3.12 - Is the First Aid box suitable and sufficient for the workforce in the office?

  • 3.13 - Is the First Aid box suitable and sufficient for the workforce in the van?

  • 3.14 - Have any visits by regulatory agencies been recorded and communicated to the SHE Team?

  • 3.15 - Have bulletins been displayed and associated TBT’s briefed where applicable?

  • 3.16 - Are records of all competences being maintained? E.g. CSCS, Gas Safe, NICEIC

  • 3.17 - Are site wide risk assessments completed and and required risk assessments in place?

  • 3.18 - Have all completed forms been removed from the accident book and communicated to the SHE Team and are near misses being reported?

  • 3.19 - Are all minor risks and impacts controlled?

  • 3.20 - Is there evidence of regular toolbox talks being briefed out?

  • 3.21 - Does the Site Manager(s) have the necessary competences for operations being undertaken on site?

  • 3.22 - Is risk register assessment & method statement register being maintained?

  • 3.23 - Is the following displayed? (Fire Marshal Poster, First Aider Poster, Fire Plan)<br>

  • 3.24 - Is there a site specific aspects & impacts assessment available?

  • 3.25 - Are copies of appropriate licences held on site? E.g. water, waste, ecological, heritage.

  • 3.26 - Are records of incidents and complaints maintained? Visits by regulatory agencies recorded and communicated to the SHE Team?

  • 3.27 - Is there evidence of Near Misses being reported on site?

  • 3.28 - Is there evidence of CM audits being undertaken and communicated to site teams?

Section 4 - Workplace and Housekeeping

  • 4.1 - Is the potential of falls from height controlled?

  • 4.2 - Are falling objects adequately controlled?

  • 4.3 - Are work areas and walkways free from major hazards?

  • 4.4 - Are other significant risks controlled?

  • 4.5 - Is housekeeping to an adequate standard? Is site free from litter, mud etc.

  • 4.6 - Is the interface between different trades managed so as to prevent exposure to risks from others?

  • 4.7 - Is fencing appropriate for site size and location and is it well maintained?

  • 4.8 - Is the level of lighting adequate for the operation being undertaken inc. Task lighting?

  • 4.9 - Have suitable work benches been provided for use of power tools?

  • 4.10 - Is site drainage kept free from blockage?

  • 4.11 - Is cable management adequate?

  • 4.12 - Are all minor risks and impacts controlled?

Section 5 - Scaffolding

  • 5.1 - Is the scaffold free from significant defects? (including ties, tubes and fittings, foundations and boards)?

  • 5.2 - Are incomplete sections of scaffold signed?

  • 5.3 - Is any area where there is a risk from falling objects closed off?

  • 5.4 - Are the design drawings and calculations available for 'design' scaffolds?

  • 5.5 - Have scaffolds been erected in accordance with TG20:13 or the design?

  • 5.6 - Are scaffolders working to SG4:15? E.g. advanced guardrail and correct fall arrest.

  • 5.7 - Is the scaffold handover certificate available, are details correct and is scaffold being used in line with the handover certificate?

  • 5.8 - Are test results available for drilled in fixings and calibration certificates available?

  • 5.9 - Have inspections been carried out as required?

  • 5.10 - Are other significant risks and impacts controlled?

  • 5.11 - Is housekeeping during scaffold erection and dismantling managed?

  • 5.12 - Are all tubes, fittings and boards in a useable condition?

  • 5.13 - Are caps fitted to cut tubes and/or sharp edges removed?

  • 5.14 - Has the competency of scaffolders been checked? - copies of CISRS cards must be on site. E.g. design scaffolds supervised by advanced scaffolders.

  • 5.15 - If a gin wheel is in use are LOLER certificates available?

  • 5.16 - Are all ladders fixed in position and of correct orientation?

  • 5.17 - Are brick guards fixed where required?

  • 5.18 - Is debris netting and/or monaflex in place where required, and fixed correctly?

  • 5.19 - Are all minor risks and impacts controlled?

  • 5.20 - Is there evidence that scaffolds are made safe at the end of each working day?

Section 6 - Mobile Towers and Other Access Equipment

  • 6.1 - Has the most appropriate form of access equipment been chosen?

  • 6.2 - Have overhead obstructions been considered?

  • 6.3 - Is all equipment in good order?

  • 6.4 - Are scaffold towers erected in accordance with manufacturer’s instructions and guardrails, toe board in place, wheels locked?

  • 6.5 - Is the scaffold tower or other equipment sat on a level and stable foundation?

  • 6.6 - Are ladders of the correct type / grade and is the use of ladders adequately controlled?

  • 6.7 - Are incomplete scaffold towers marked as incomplete?

  • 6.8 - Are other significant risks controlled?

  • 6.9 - Is equipment being stored correctly when not in use?

  • 6.10 - Are those erecting and/or responsible for mobile towers competent ENGIE or PASMA trained?

  • 6.11 - Are all podium steps and mobile towers tagged?

  • 6.12 - Are copies of weekly inspections available for scaffold towers above 2 metres?

  • 6.13 - Are all minor risks and impacts controlled?

Section 7 - Temporary Works

  • 7.1 - Are detailed designs and drawings available for any temporary works?

  • 7.2 - Has a competent person checked the temporary works after construction/erection?

  • 7.3 - Has the temporary works been modified/amended since erection without being rechecked?

  • 7.4 - Are the works in good order? e.g. Not showing signs of distress and/or excessive deflection.

  • 7.5 - Are other significant risks controlled?

  • 7.6 - Has a competent person been nominated as the 'temporary works co-ordinator'?

  • 7.7 - Is there evidence of regular checks on the temporary works?

  • 7.8 - Is a design check appraisal available?

  • 7.9 - Have copies of operator’s training/competence been copied into the site file?

  • 7.10 - Are all minor risks and impacts controlled?

Section 8 - Mobile Plant

  • 8.1 - Does the operator hold a CPCS Card or equivalent and is it of the correct type?

  • 8.2 - Is the plant in good order and suitable for the purpose for which it is provided or used?

  • 8.3 - Is the plant maintained so that it remains mechanically sound and are there records available?

  • 8.4 - Is the plant stable in use? Is there a safe way to get into and out of the cab and any other parts of the vehicle that need regular access?

  • 8.5 - Is plant being operated in a safe manner? i.e. is the area segregated, hazard light on and banked if required by RA.

  • 8.6 - Are vehicle lights, reversing lights, a horn and other warning devices such as rotating beacons or reversing alarms fitted?

  • 8.7 - Are reversing aids fitted and in good condition?

  • 8.8 - Is the plant fitted with Roll Over Protection System (ROPS) where necessary?

  • 8.9 - Are dangerous vehicle parts, such as power take –off, chain drives, exposed hot exhaust pipes appropriately guarded?

  • 8.10 - Is the vehicle suitable for any loads carried?

  • 8.11 - Is there a Manufacturers Operation Manual available to the Mobile Plant Operator?

  • 8.12 - Has security been considered and is the unauthorised use of plant prevented?

  • 8.13 - Are other significant hazards controlled?

  • 8.14 - Are seat belts fitted and used correctly?

  • 8.15 - Are mirrors and or closed circuit TV (CCTV) systems fitted and fit for purpose?

  • 8.16 - If used on the road is the vehicle registered etc and operator has a current UK Driving Licence?

  • 8.17 - Is equipment tagged?

  • 8.18 - Is any towing/quick hitch in good order and spares available? – correct pin?

  • 8.19 - Are daily and weekly checks being carried out and recorded?

  • 8.20 - Is equipment that may be used for lifting marked with a SWL?

  • 8.21 - Is equipment that may be used for lifting thoroughly examined/tested and in date?

  • 8.22 - Are all minor risks and impacts controlled?

Section 9 - General Work Equipment

  • 9.1 - Are all safety devices in place and operational?

  • 9.2 - Is the equipment being used for the purpose that it was designed?

  • 9.3 - Are there specific assessments for noise, dust and vibration with adequate controls in place?

  • 9.4 - Are operatives competent to use the equipment?

  • 9.5 - Are tools and equipment in good condition?

  • 9.6 - Is there evidence that defective equipment is removed from use?

  • 9.7 - Are other significant risks controlled?

  • 9.8 - Are whip checks fitted to airlines?

  • 9.9 - Are test certificates available for specialist equipment?

  • 9.10 - If there is a requirement for an exclusion zone has this been established?

  • 9.11 - Are maintenance / inspection records available for the equipment?

  • 9.12 - Are all minor risks and impacts controlled?

  • 9.13 - Are copies of the training records available in the site file?

  • 9.14 - Are there suitable storage facilities for equipment and consumables?

Section 10 - COSHH

  • 10.1 - Have all substances which may be hazardous to health been identified, assessed, and use controlled and MSDS available?

  • 10.2 - Are other significant risks controlled?

  • 10.3 - Are hazardous materials being stored in accordance with MSDSs and COSHH assessments?

  • 10.4 - Has COSHH information been briefed out to those affected? - Record required.

  • 10.5 - Are control measures identified in COSHH assessment being operated?

  • 10.6 - Are the necessary first aid measures in place?

  • 10.7 - Are all minor risks and impacts controlled?

  • 10.8 - Where substances have WEL/STEL in place is adequate control and surveillance in place?

  • 10.9 - Have harmful products be substituted for less harmful products where possibly?

Section 11 - PPE

  • 11.1 - Is all PPE identified by Risk and COSHH assessments etc. being provided?

  • 11.2 - Is PPE/RPE provided of the correct type/grade?

  • 11.3 - Is proper RPE being utilised? - No 'comfort' masks.

  • 11.4 - Where RPE is in use for significant risk works, (Silica/ Carcinogenic etc.) have face fit test certificates been provided?

  • 11.5 - Are other significant risks controlled?

  • 11.6 - Is PPE/RPE being used in good order?

  • 11.7 - Is PPE/RPE being worn correctly or not at all (multiple failures)?

  • 11.8 - Where necessary have operatives been given instruction/training on use of PPE? - Evidence required.

  • 11.9 - Does the site have a sufficient supply of replacement PPE?

  • 11.10 - Are all minor risks and impacts controlled?

  • 11.11 - Are face fit tests carried out for all those wearing RPE?

  • 11.12 - Have hoods been issued to Operatives that cannot be face fit tested?

Section 12 - Manual Handling

  • 12.1 - Have all manual handling operations been identified, assessed and managed and control measures briefed out?

  • 12.2 - Is any specialist equipment required as a control measure been provided?

  • 12.3 - Has manual handling training been provided where required?

  • 12.4 - Are weight of items known?

  • 12.5 - Are all minor risks and impacts controlled?

Section 13 - Noise and Vibration

  • 13.1 - Have areas where noise is likely to exceed the Lower Exposure Action Level 80 dB (A) been identified?

  • 13.2 - Have hearing protection zones been established for areas where noise exceeds 80 dB (A)?

  • 13.3 - Where required has a S61 consent been obtained and is there evidence of monitoring and compliance in accordance with it?

  • 13.4 - Have work practices where hand-arm vibration is likely to exceed the daily exposure limit value [5 m/s² A (8)] been identified?

  • 13.5 - Have work practices where whole-body vibration is likely to exceed the daily exposure limit value [1.15 m/s² A (8)] been identified?

  • 13.6 - Are other significant risks controlled?

  • 13.7 - Has noise above 80 dB (A) been controlled at source where possible?

  • 13.8 - Have others who may be affected by the noise been considered and consulted?

  • 13.9 - Does the site or task have working hour restrictions and are these complied with?

  • 13.10 - Is there adequate signage for hearing protection zones 85dB (A) and above?

  • 13.11 - Has information on hearing protection zones been briefed out? - Evidence required.

  • 13.12 - Has hearing protection been assessed to ensure compliance with other PPE?

  • 13.13 - Has a risk assessment been carried out for vibrating equipment?

  • 13.14 - Have all employees and site operatives been made aware of the risks and control measures in place for Noise and Vibration?

  • 13.15 - Are all minor risks and impacts controlled?

Section 14 - Fire Prevention

  • 14.1 - Are all potential sources of ignition, including waste and fuel identified, stored and controlled adequately??

  • 14.2 - Is the site operating a 'Hot Works' permit system and are the controls detailed within the permit being complied with?

  • 14.3 - Has the site developed a written and drawn fire plan and associated risk assessment for all work areas and is it sufficient for the work place?

  • 14.4 - Are other significant risks controlled?

  • 14.5 - Is there suitable means of escape and are they kept clear?

  • 14.6 - Are fire extinguishers suitable for the types of fire likely to be encountered?

  • 14.7 - Is there suitable means of warning and an interlinked fire alarm where required?

  • 14.8 - Are fire points established and maintained?

  • 14.9 - Is there evidence that the fire plan is briefed out and/or included in the induction?

  • 14.10 - Are fire extinguishers serviceable and maintenance records available?

  • 14.11 - Are all minor risks and impacts controlled?

  • 14.13 - Are maintenance records available for fire extinguishers?

  • 14.14 - Is there a nominated and trained Fire Marshal(s)?

  • 14.15 - Are fire extinguishers available in the vans?

Section 15 - Excavations

  • 15.1 - Have areas been CAT scanned at 500mm (depth) intervals prior to works commencing / during works?

  • 15.2 - Is there a permit to dig system in place?

  • 15.3 - Are excavations properly supported?

  • 15.4 - Is the excavation guarded to prevent people, material and plant falling in?

  • 15.5 - Have stop blocks been provided for plant?

  • 15.6 - Are other significant risks controlled?

  • 15.7 - Has a safe means of access/egress been provided for the excavation?

  • 15.8 - Is there an emergency procedure in place for excavations?

  • 15.9 - Is spoil stored at a safe distance from the sides of the excavation?

  • 15.10 - Has undermining of nearby structures been considered?

  • 15.11 - If other services have been exposed are they adequately protected and supported?

  • 15.12 - Record of inspections for the excavation available on site?

  • 15.13 - Are all minor risks and impacts controlled?

Section 16 - Asbestos Management

  • 16.1 - Is there asbestos information available and adequate for the works undertaken?

  • 16.2 - Are works in progress covered by a risk assessment and/or plan of work and is the work correctly described and categorised?

  • 16.3 - Is non-licensable 'minor' work being undertaken by competent and trained personnel with the required insurances and approved by Regional SHEQ Manager?

  • 16.4 - Are licensable asbestos works being undertaken by a licensed company?

  • 16.5 - Has the HSE been notified using the ASB5 Notification form?

  • 16.6 - Is the potential for accidental release of asbestos fibres identified and controlled?

  • 16.7 - Are there any other significant risks identified?

  • 16.8 - Have all people on site received adequate training with regard to asbestos?

  • 16.9 - Has all asbestos information been communicated to relevant personnel?

  • 16.10 - Is there evidence that face fit testing has been carried out for the RPE being used with asbestos?

  • 16.11 - Are all minor risks with regards to asbestos controlled?

  • 16.12 - Has a general briefing / toolbox talk on asbestos been carried out?

  • 16.13 - Has the Site Manager got access to the Emergency Release asbestos procedure and is it understood?

  • 16.14 - Relevant flow charts extracted from the asbestos standards are displayed on the site notice boards?

Section 17 - Gas Safety

  • 17.1 - Have gas appliances and flues been surveyed, identified, tested and documented? (smoke testing)

  • 17.2 - Is the information on gas appliances and flues recorded in a format that can be easily accessed?

  • 17.3 - Have works that impact on gas appliances and flues been identified? (e.g. changes to ventilation during window replacement and working within 1m of a live flue.)

  • 17.4 - Are all ‘gas works’ undertaken by Gas Safe registered persons? (excludes bayonet fittings)

  • 17.5 - Is there a gas flue ‘Permit to Work’ system in use for all works that impact on live gas flues, and is the system correctly implemented?

  • 17.6 - Are other significant risks posed by gas identified?

  • 17.7 - Is information on GAS SAFE registered persons used on site recorded and easily accessible?

  • 17.8 - Has the Site Manager undertaken the ENGIE Gas Safety training?

  • 17.9 - Are specific RAMS available for works which impact on appliances/flues and works in accordance

  • 17.10 - Is Stars and Stripes TBT delivered to all personnel?

  • 17.11 - Is commissioning paperwork available for all new live appliances?

  • 17.12 - Have those disconnecting/reconnecting bayonet fittings been trained and records kept and do they have access to leak detection spray?

  • 17.13 - Are other risks associated with gas controlled?

  • 17.14 - Are flue tags in use?

Section 18 - Electrical Safety

  • 18.1 - Is the need for 'live' working eliminated?

  • 18.2 - Are works in the vicinity of live circuits adequately controlled? (e.g. safe isolation).

  • 18.3 - Has the risk from overhead services or live conductors been identified, and are suitable control measures in place?

  • 18.4 - Are all conductors properly insulated where required or 'permit to work' in place?

  • 18.5 - Is the use of 240v (and above) work equipment eliminated?

  • 18.6 - Are statutory undertaker’s plans available on site (where relevant)?

  • 18.7 - Are other significant risks controlled?

  • 18.8 - Are test certificates for temporary supplies available?

  • 18.9 - Are the majority of electrical appliances (including extension cables) PAT tested and in date?

  • 18.10 - Are all site supplies certified with no visual defects?

  • 18.11 - Are all minor risks and impacts controlled?

Section 19 - Water Resource Management

  • 19.1 - Have water discharge points been identified and appropriate license in place?

  • 19.2 - Is bulk storage of fuel in accordance with oil storage regs?

  • 19.3 - Are all significant impacts controlled?

  • 19.4 - Have sensitive receptors been identified?

  • 19.5 - Is Oil / fuel drums maintained in bunded areas?

  • 19.6 - Are spill kits available in vans?

  • 19.7 - Are COSHH materials stored away from watercourse?

  • 19.8 - Is drainage from the office / canteen facilities to mains sewer or septic tank?

  • 19.9 - Is monitoring in place for water discharge licences?

  • 19.10 - Is concrete wash-out collected in appropriate container (no discharge to ground)?

  • 19.11 - Is there a drainage plan on site (where appropriate)?

  • 19.12 - Are all minor impacts controlled?

  • 19.13 - Are spills cleaned up and materials disposed of appropriately?

  • 19.14 - Is the drainage system maintained and free from blockages?

  • 19.15 - Are all minor risks and impacts controlled?

Section 20 - Waste Management & Carbon

  • 20.1 - Is the project registered to produce hazardous waste (over 500kg)?

  • 20.2 - Is the Site Waste Management Plan available, completed and communicated to relevant personnel?

  • 20.3 - Are there exemptions in place for on-site crushing etc.?

  • 20.4 - Are Waste Transfer Notes and Consignment Notes held on site for all waste movements?

  • 20.5 - Is all waste stored and segregated with physical barriers and signed?

  • 20.6 - Are all significant impacts controlled?

  • 20.7 - Have all waste streams been identified and suitable storage obtained?

  • 20.8 - Have all hazardous waste streams been identified and suitable storage obtained?

  • 20.9 - Have waste improvement targets been set and uploaded onto the intranet (AIMS) on a monthly basis?

  • 20.10 - Is there evidence of Internal waste transfer notes and are they completed properly for ENGIE and Subcontractor? (where required)

  • 20.11 - Is there a copy of ENGIE/Subcontractors Waste Carriers Licence in relevant ENGIE/Subcontractors vehicles?

  • 20.12 - Are all minor risks and impacts controlled?

  • 20.13 - Are skips secure and if appropriate covered?

  • 20.14 - Are skips clearly and correctly signed where applicable?

  • 20.15 - Is the site free from waste accumulation?

  • 20.16 - Where possible energy usage (electricity / gas / other site fuel) is monitored and recorded (monthly) on the online recording system.

  • Completed by:

  • Received by:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.