Part 1: GENERAL INFORMATION
-
A current fire risk assessment is required but The Regulatory Reform (Fire Safety) Order 2005.
This is a live document to be updated by the FM with input from occupier representatives:
1. Whenever there is significant change to the premises which may affect fire strategy
2. If there is a significant change in work activity or process or an increase in storage or use of hazardous materials in a building
3. If there is a significant increase in staff or student numbers
4. Immediately after a fire
5. Following an audit by UOB safety office or an enforcement agency
6. Annually
The risk assessment will form part 2 of the fire manual
The responsible person for fire safety
-
Contact details of Operations/facilities manager
-
Date of assessment
Re-Assessment
-
Recommended date for re-assessment
1 The Building
-
Building address
-
Take a photo of the building
-
Approximate age of building
-
Listed building?
-
Number of staircases
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10+
- 00
-
Number of Passenger lifts
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10+
- 00
-
Number of Goods lifts
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10+
- 00
-
Number of Evacuation lifts?
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10+
- 00
-
Number of final exits
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10+
- 00
-
Floor area: (m2 per floor)
-
Brief details of construction:
-
Construction class
-
Does the building contain asbestos?
-
What hazards should the fire officer be aware of before entering the building?
-
Describe the layout (number of rooms, corridors,height of ceiling,hazardous areas
-
Basement
-
Ground floor
-
1st floor
-
2nd floor
-
3rd floor
-
4th floor
-
5th floor
-
Use of building
2 The occupants
-
Name of Building fire coordinator
-
Names of technical managers
-
Names of school / section safety advisors
-
Maximum number of occupants:
-
Maximum number of occupants at any given time:
-
Maximum number of members of the public at one time:
-
The fire wardens are
Fire warden
-
Name
-
Location
3 Occupants at special risk
-
Are any people aged under 16 employed at the premises?
-
Are there sleeping occupants?
-
Are there disabled occupants?
-
Are there occupants in remote areas?
-
Are there lone workers?
-
Are instructions, information given on specific hazards in the form of an induction?
-
Are max number of occupants clearly defined for lecture theatres?
-
Are evacuation arrangements in place for conferences, ceremonies and public events?
4 Previous Fire loss experience
-
Is there any previous history of fire loss in the premises (if yes give details)
5 Other relevant background
-
Are there any residential properties in or attached to the building
-
Are there any outstanding actions from formal cautions or Notices issued by an enforcement agency?
-
Have all actions been completed from the previous fire risk assessment?
Part 2: FIRE HAZARDS AND ELIMINATION OR CONTROL
6 Sources of ignition
-
Can all naked flames be isolated locally?
-
Is there a gas supply including bottled gases?
-
Is the electrical supply tested and records available?
-
Is the location of isolation switch for oil fired equipment known and documented?
-
Are portable appliances tested/inspected?
-
Does temperature thermostats on hot works/cooking processes or lab equipment work?
-
Has all faulty, misued electrical equipment or poorly installed equipment been reported and isolated?
-
Is all lighting in a good state of repair?
-
Is there a suitable limitation on the use of trailing leads and adapters?
-
Is the use of portable heaters avoided as far as reasonably practicable?
-
If portable heaters are used, are the more hazardous types (radiant bars and LPG) avoided?
-
If portable heaters are used are suitable measures taken to minimise the risk of ignition of combustible materials?
-
Are fixed heating installations subject to regular maintenance?
-
Does the building have lightning protection system?
-
Are reasonable measures taken to prevent cooking fires?
-
Are suitable extinguishers available?
-
Are filters changed and ductwork cleaned regularly?
-
Does the basic security against arson appear reasonable?
-
Is there sufficient control of unnecessary fire load in close proximity to the building or available for ignition by outsiders?
7 Other significant ignition sources that warrant consideration
-
Are the ignition risks from hot process controlled? eg welding, grinding, curing in autoclave?
-
Are their procedures for managing heat produced from chemical reactions?
-
Are procedures in place for self heating or spontaneous ignition sources?
-
Does smoking occur only in external areas away from the building?
-
Are risks from mechanical equipment documented?
-
List other ignition sources:
8 sources of fuel
-
Is there an inventory of hazardous substances present on the premises?
-
Is there an inventory of flammable substances and is it up to date?
-
Has the risk to relevant persons been adequately eliminated or reduced?
-
Is the standard of housekeeping adequate?
-
Are combustible materials separated from ignition sources?
-
Is the unnecessary accumulation of combustibles and waste avoided?
-
Is there appropriate storage of hazardous materials?
-
Are combustible materials stored appropriately?
9 Laboratory gases
-
Are there oxidising processes in use?
-
Is there a piped laboratory gas supply and is it maintained and tested?
-
Are oxygen cylinders stored correctly with segregation of empty cylinders?
10 Hazards introduced by contractors and building works
-
Is there sufficient control over works by contractors (e.g. Permits to work & hot works permits)?
-
Are there arrangements for the safe storage of gas bottles and others hazardous materials
-
Are fire safety conditions and instructions communicated to contractors?
Part 3: FIRE SPREAD
11 Measures to limit fire spread and development.
-
Is there a sufficient standard of compartmentation and sub-compartmentation?
-
Are routes that promote fire spread avoided as far as reasonably practicable?
-
Is fire spread limited by correct use and maintenance of fire precautions?
-
Do riser cupboard doors, corridors have keep shut signs?
12 Fire alarm and detection system
-
What is the fire alarm sound?
-
Can the fire alarm be heard though out the building?
-
Are there alternative provisions for deaf or the hard of hearing?
-
Are there arrangements in place for noisy environments?
-
Are arrangements in place for noise sensitive areas?
-
Is the fire alarm system provided suitable and sufficient?
-
Is automatic fire detection provided throughout?
-
Is there remote transmission of alarm signals via university systems?
-
Are fire alarm call points located by storey and final exits?
-
Are the call points unobstructed?
-
Are compliant fire action notices displayed near to call points?
-
Is there weekly testing and periodic servicing of the fire detection and alarm system?
13 Fire Fighting equipment
-
Is there suitable and sufficient provision of fire fighting equipment?
-
Are hose reels provided?
-
Is it maintained and stored correctly?
-
Is there a wet or dry riser and is it maintained?
14 Means of escape
-
Is the building provided with adequate means of escape in case of fire?
-
Are there sufficient exits?
-
Are exits easily and immediately openable where necessary?
-
Do fire exits open in the direction of travel where necessary?
-
Have sliding or revolving doors been avoided as fire exits?
-
Are there adequate means of securing exits?
-
Are there reasonable distances of travel where there is a single direction of travel?
-
Are there reasonable distances of travel where there are alternative means of escape?
-
Are escape routes adequately protected?
-
Are there suitable fire precautions for all inner rooms?
-
Are horizontal, vertical and external escape routes unobstructed?
-
Is the location of fire assembly point suitable for building?
-
Are there suitable means of escape for disabled occupants?
-
Is the access statement in place?
-
Are Personal Emergency Evacuation Plans (PEEP) up to date?
15 Emergency exit lighting
-
Is there a reasonable standard of escape lighting provided?
-
Is there monthly, six-monthly and annual testing of the emergency lighting?
16 Fire safety signs and notices
-
Are fire safety signs and notices suitable and sufficient?
-
Are fire exit signs suitable and sufficient?
-
Are emergency break glass door secure systems interfaced with the fire alarm?
-
Do fire exit doors have suitable and sufficient signage?<br>
-
Are door release systems tested regularly?
-
Are hazardous areas approximately signed and flammable materials clearly labelled?
17 Relevant automatic fire extinguishing systems
-
Type of system:
-
Comments and observations:
18 Facilities, equipment and devices for the protection of Fire-Fighters
-
Types of facilities:
-
Comments and observations:
Part 4: MANAGEMENT OF FIRE SAFETY
19 Procedures and arrangements
-
Person responsible for fire safety:
-
Are there competent persons available to assist in implementing fire safety arrangements?
-
Are appropriate fire procedures in place? (including arrangements for calling the fire service)
-
Fire Emergency Plan in place and details recorded?
-
Does the plan take account of other Fire Emergency Plans applicable in the building?
-
Is the Fire Emergency Plan readily available for staff to read?
-
Is the Fire Emergency Plan available to the enforcing authority?
-
Are there persons nominated to respond to fire?
-
Are persons nominated to assist with evacuation?
-
Is there appropriate liaison with the fire service?
-
Do routine in-house inspections of fire precautions take place?
-
Are there arrangements in place to inform temporary staff, students or contractors?
20 Training and drills
-
Are staff given instruction on induction?
-
Do staff receive periodic refresher training at suitable intervals?
-
Are staff with special responsibilities for hazardous substances given appropriate training?
-
Are fire drills carried out every term?
-
Has the occupier provided an appropriate number of trained fire wardens?
21 Testing and maintenance
-
Is the workplace adequately maintained?
-
Are the university test logs completed and up to date?
-
Other relevant inspection and test
22 Locations of specific hazards
-
Are there specific hazards?
Hazard
-
Is there gas bottles, radioactive sources or other flammables?
-
Location (floor / room no)
-
Type of hazard
-
Quantity
-
Size
-
Contact
Part 5: ACTIONS AND RECOMMENDATIONS
Risk Items
-
Are there risks to address?
Risk
-
Description and location of risk
-
Non compliance or observation?
-
Risk rating score (probability x consequence)
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
-
Action
-
Owner
-
Target date
PART 6: QUALITY ASSURANCE
-
Received by responsible person / representative
-
Assessor Signature
-