Installation of new EPDM to masonry / Window Pod interface (Type 2 and 3)

  • 1.Using scrapers, flat-bladed tools remove all existing EPDM to window pods frame and adjacent structure (photo)

  • 2. Prior to EPDM works commencing ensure temperature is a minimum of 5 degrees centigrade and RH not less than 40%

  • 3. Using 250/400mm wide ARBO EPDM and associated products, clean and prime masonry surface with ARBO AF S. De-grease aluminium Pod with ARBO Cleaner Nr16 applied to cloth. Leave to dry for at least one hour no more than 8 hours

  • 4. Apply ARBO Adhesive in 8mm beads, spread liberally to masonry and aluminium pod to ensure good adhesion

  • 5. Lay and press (using rollers) EPDM membrane strip onto the prepared zone and ensure good adhesive contact. Spread excess adhesive at edges. Sequencing to be cill, then both jambs, and finally heads, 250mm EPDM to cill and jambs, 400mm to head (interfaces with floor slab). Complies with App. M ER's (photo)

Installation of new fasteners / brackets to window pods (Type 2 and 3)

  • 1. Head Detail: Per SCF Cons Drwgs measure/markup new bracket location (BK1) not to exceed 300 c/c<br>a. Notch window pod flange to enable new Fischer FAZ II anchor installed at no greater than 5 degrees off perpendicular <br>b. Fit 1Nr Fischer FAZ II per new bracket / concrete edge distance 45mm. Torque setting 45Nm. Embedment 40mm / 10mm dia <br>c. Ensure metal packing to brackets as necessary to level d. Fit EJOT JT3-6-5.5 x 30mm through bracket into Pod frame. 2 x JT3 per bracket <br>NOTE: Type 2 Window = 6 new brackets / Type 3 Window = 8 new brackets

  • 2. Cill Detail: Per SCF Cons Drwgs measure/markup new bracket locations (BK2) not to exceed 300 c/c <br>a. Fit 1Nr EJOT SDF KB 10V x 60E masonry fixing (50mm embed / 10mm dia) per bracket. <br>b. Operatives to ensure masonry fixing is centered in brick / 100mm away from edge / clear of mortar joint <br>c. Ensure metal packing to brackets as necessary to level d. Fit EJOT JT3-6-5.5 x 30mm through bracket into Pod frame. 2 x JT3 per bracket<br>NOTE: Type 2 Window = 6 new brackets / Type 3 Window = 8 new brackets

  • 3. Jamb Detail: Per SCF Cons Drwgs measure/markup new bracket locations (BK4) not to exceed 300 c/c a. Fit 2Nr EJOT SDF KB 10V x 60E masonry fixing (50mm embed / 10mm dia) per bracket. b. Operatives to ensure masonry fixing is centered in brick / 100mm away from edge / clear of mortar joint <br>c. Ensure metal packing to brackets as necessary to level d. Fit EJOT JT3-6-5.5 x 30mm through bracket into Pod frame. 2 x JT3 per bracket<br>NOTE: Type 2 Window = 4 new brackets / Type 3 Window = 4 new brackets per jamb

undefined

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.