Information
-
Site
-
Conducted on
-
Prepared by
-
Personnel
-
Location
1.0 HIGH RISK WORKS CONDUCTED ON SITE
-
Earthworks Stockpiles Excavation and trenching Earthworks haulage Export material on public roads Traffic management Public safety Overhead powerlines Excavation in front of retaining walls Subcontractor management
- earthworks
- stockpiles
- excavation and trenching
- earthworks haulage
- export material on public road
- traffic management
- public safety
- overhead powerlines
- excavation in front of retaining walls
- subcontractor management
2.0 EARTHWORKS
-
Excavator setup on bench that it is positioned to slew towards dump trucks on its non- blind side where practicable
-
Loading machines not slewing over cabs
-
Excavation floors kept clean <br>
-
Borrow pits edges wind rowed adequately
-
Ramp declines / inclines adequate
-
Fill areas, rollers are facing towards incoming machines (scrapers / dump trucks etc)
-
Exclusion zones maintained by dump trucks or semi trucks until loading machine (excavator / loader) calls them in
-
Machines on same uhf radio channel
-
Call up points in place? Operators following call up protocol?
2.1 STOCKPILES
-
Stockpiles are at the correct height ratio for soil types / sheer faces knocked down at end of the day
-
Stockpiles are not creating blind spots or hazards to traffic on site
-
Stockpiles to be kept below 2m where possible
-
If the stockpile is over 2m they will be stabilises by hydromulch or other method.
-
If stockpile over 2m where plant is required to travel over or work on top windrows will be built up on outer extremities
-
Where multiple mobile plant and or trucks intersect around stockpiles, directional traffic management has been established
-
Plant movement is uncontested around screens and stockpile locations
2.2 EXCAVATION AND TRENCHING(OSH Regulations 1996 3.109-3.113)
-
Permit to dig in place for area of works
-
Workers signed onto permit to dig
-
Services identified within brownfield permit to dig have been physically identified by pothole methodology or ground penetrating radar
-
External asset authority permits in place
-
Where batter and benching cannot meet the excavation code of practice adequate shoring to be installed
-
Excavation sides battered / benched (horizontal to vertical ratio)dys
-
Trench excavations exceeding a depth of 1m, ladders, ramps or other forms of access and egress are provided at intervals of not more than 30m. Distances of travel for a worker to access / egress is not more than 15m
-
Windrow of adequate size around excavation. The windrow will be at least equal to the axel height of the largest unit.
-
Adequate barriers and deep excavation signs around excavation
-
Adequate distance between passing traffic and excavation edge
-
No excavated material or other loads are placed near the excavated area where there is risk that the sides of an excavation may collapse or plant/load may fall into excavated area. Stockpiles at least 600mm away from edge of the excavation
-
Hard hats worn in excavation greater than 1.5m regardless of benching
-
Hard hats worn in any trench at any trench where there is risk of objects falling onto someone in a trench
-
Hardhats worn where there is risk of objects falling onto someone in a trench
-
For excavations greater than 6m the deep excavation checklist is in use (SF 4.25-1.10)
-
Excavations of 1.5m deep there is at least one other person in the vicinity unless the sides of the excavation have been assessed as self supporting
2.3 EARTHWORKS HAULAGE
-
Internal traffic management in place, signage to match risk
-
Traffic management plan adhered to by operators
-
Haulage route width ample for two way haulage (approx 15m)
-
Haulage route segregated from other works eg) away from workers on the ground and other machines
-
Haulage route free from potholes and rocks
-
Haulage route declines and bends minimised as far as practicable
-
Haulage route two way traffic are adequately separated by windrows where practicable
-
Haulage route edges adjacent excavations are built up and windrows sufficient to axel height
-
No unauthorised vehicles or subcontractors using haul route
-
Giveaway protocol followed
2.4 EXPORT MATERIAL ONTO PUBLIC ROADS
-
Large export jobs have machine with loadrite
-
Verification of load rite data to ensure legal compliance - trucks are not overloaded
-
Export material without load rite - calculation has been conducted for truck configurations and bucket size. Reference export SWMS.
3.0 TRAFFIC MANAGEMENT (PUBLIC AREAS)
-
Works conducted within road reserve or on adjacent public road has an approved TMP?
-
Reference TMP document and TCD
-
Traffic management on site matches TCD
-
Photograph signage and tick off TCD
-
Photograph marked up TCD
-
Traffic management plan is relevant to the stage of works
-
A daily inspection log is conducted by a BWTM (minimum 3 times a day)
-
Signs are legible to road users and in reasonable condition
-
The road speed is reduced to 40km where workers on foot are within 1.2m to the traffic and delineation installed
-
Excavation near public road adequately protected for workers and public vehicles
4.0 PUBLIC SAFETY ( OSH Act 1984 Section 20-22, OSH Regulations 3.17)
-
Site entrance signage in place (if principle contractor)
-
Construction materials kept within the workplace
-
Any risk of objects falling on members of the public
-
Any risk of trip hazards to the public
-
Public access controlled
-
Site perimeter fencing or barricades erected
-
Warning signs in place and relevant to risk
-
Construction signage at interfaces between works and public roads / access
-
Works adjacent public thoroughfare demarcated / barricaded
5.0 OVERHEAD POWERLINES (OSH Regulations 1996 3.64)
-
Electrical clearances over main access roads to job e-mailed to sub contractors
-
Permit to work (RJV)under lines available and implemented. JSA in place
-
Danger zones clearances measured and displayed on signage in the vicinity of powerlines
6.0 RETAINING WALLS
-
Excavations in front of retaining walls are risk assessed and authorised by Project Manager/Structural Engineer (OP 4.18-3.23A)<br>Controls from Engineer/PM are reflected in JSEA.<br>Workers are signed onto JSEA
-
Controls from engineer / PM are in place on ground that is documented in JSA
-
Workers signed into JSEA
-
Fall prevention in place
-
Hard hats worn where any task of wall builders are in line of fire (block delivery or swinging grab)
7.0 SUBCONTRACT MANAGEMENT
-
Are JSA / SWMS in place for the task being conducted
-
Is the JSA/ SWMS specific to the site and stage ?
-
Have all personnel working under the JSA / SWMS signed onto the document
GENERAL
-
Add media
SIGN OFF
-
RJV On site representative
-
Auditor