Corridor 1st Fix Checklist

  • The LTG, Power, AOV and FA is set out to the correct construction drawings and RCP's, Review attached drawings

  • All LTG / EM lighting and Exit signs are wired in the correct location, in line with the fire strategy and latest designed / Lux levels.

  • The fire alarm cable installed is Red FP enhance cable and the cable bending radius is correct on the basket and conduits with no pressure faults.

  • All LSF cable installed is the correct type / colour and number of cores in line with the specification and technical requirements.

  • No signs of visible damage to the LTG/ Power/ELV and SWA cables installed, all cables are on the correct side off the segregation on the basket

  • All LV and ELV cables installed on containment are tie wrapped every 400mm with black plastic ties and metal ties on escape routes and every metre with metal ties, all ties are cut back

  • All ELV & LV cables are clipped 500mm max with no excessive cable lengths in the ceiling and are fixed with fire resistant metal screws and clips.

  • Corridor Photos

  • Issues Detailed

  • Photo Evidence

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.