Corridor 1st Fix Checklist
-
All containment fixed to the concrete slab with the correct Unistrut and fixings to enable it to take the allocated cable weight.
-
The horizontal containment installed is set out straight to the corridor and riser walls with the bends and sets fixed correctly with the correct slow radius bends in line with manufactures guild lines and the DWG’S
-
All horizontal Basket segregation is installed between the ELV, and LV is installed straight with the correct joining clips
-
All Bonding to be installed between baskets and to back to landlord Distribution boards
-
All SWA cables passing through the APT & riser wall have the correct (90 radius bend) and go through the wall straight to enable them to be fire stop it correctly.
-
All ELV cables passing through the walls are Mechanically protected by conduit or basket
-
APT SWA & ELV cables are left in the correct position on the floor and in the riser
-
All LV and ELV cables installed on containment are tie wrapped every 400mm with black plastic ties and metal ties on escape routes and every metre with metal ties, all ties are cut back
-
All ELV & LV cables are clipped 500mm max with no excessive cable lengths in the ceiling and are fixed with fire resistant metal screws and clips.
-