Information

  • Title/Site

  • Site Address.

  • Conducted on

  • Prepared by

1. Introduction

  • This Plan of work is to be read in conjunction with the Cablesheer Standard Working Procedure version 5. Any alteration or amendments to this document are to be agreed with the contracts manager named inside. The supervisor should note that this Plan Of Work is subject to further assessment on arrival to site, any alteration to site conditions that do not match this plan and Risk assessment should be discussed with the contracts manager named inside. Section A. Below should be signed by the manager named inside. Section B. Below should be signed by the Operations manager preparing the document. Section C. Below should be signed by the Senior Manager or Director as part of our Plan of work audit scheme, 20% of Plans of works will be audited by Senior Manager or Director.

  • A. Plan of work reviewed By:

  • B. Plan of work reviewed By:

  • C. Plan of work reviewed By:

  • Contact details and relevant persons are as follows:
    David Brown = Managing Director
    Geoffrey Phillips = Associate Director
    Mark Dyerson = Senior contracts Manager
    Michael McKenna = Contracts Manager
    Gary Taylor = Contracts Manager
    Samantha Dyerson = Operations Manager
    Kevin Fagg = Compliance Manager
    Sean Hasler = Audit Manager
    Susan Reed = Admin Manager ( General Enquiries )
    Rebecca Froud = Admin ( Bookings )
    Liane Fenner = Admin ( Air test )
    Sam Brett = Admin ( Multibase )
    Tony Kynoch = Stores Manger
    Wayne Higgins = Store man
    Robert Verlander = Site Assessor
    All of the above staff can be contacted on 08442252997 or there mobile phones between 09.00-17.00 Mon - Fri. For out of hours enquiries please contact the Associate Director or Senior Manager on there mobile phones, if un contactable please leave a message.
    The Risk assessment section of this plan of work has a score system, this score system will identify high risk sites and will also determine the priority score the plan is given for our internal audit procedure, the scoring system is as follows:
    Scores between 0-20 = 20% chance of audit and management visit.
    Scores between 21-35 = 40% chance of audit and management visit.
    Scores between 36-50 = 70% chance of audit and management visit.
    Scores between 51-100 = 100% chance of audit and management visit.
    Works continuing for over 7 working days will have a 50% chance of audit and management visit.
    Works continuing for over 14 working days will have a 100% chance of audit and management visit.
    The site supervisor is responsible for conducting the site complying with current asbestos rules and regulations, he is responsible for maintaining health and safety standards and producing a site diary and record maintenance records for plant and equipment.
    AUDIT PROCESS IS CURRENTLY UNDER REVIEW.

  • A. Arrive on site and introduce team to occupier.
    B. Supervisor to Read, understand and relay information to operatives and all sign Plan of work.
    C. DCU set up as per diagram and section 9. ( If Applicable )
    D. Enclosure construction as per diagram and section 5.
    E. Removal works as per Method detailed in section 5.
    F. Clearance Air monitoring.
    G. Enclosure removal.
    H. Reoccupation certificate issued.
    I. Cablesheer team leave site clean and tidy.

  • Summary of work

  • Please see section 9. of this document for site diagram, site photographs, NPU Calculation & local accident and emergency unit, the site photos have been illustrated and should be used as visual aid in the help of understanding this plan of work and the details within. The NPU calculator will show the minimum number of air changes and the required NPU rating for the enclosure volume, it will also show the number air changes the chosen NPU will provide for the volume of the enclosure. The route needed for the local A&E department will be illustrated using google maps with the Address clearly displayed.

2. Contract Details

  • 1. Term client.

  • Please Enter Client details.

  • 2. Contracts Manager in charge of works.

  • 3. Supervisor name and contact details.

  • 4. Who will give access to the site.

  • Access information

  • 5. Welfare facilities

  • 6. Location and type of property.

  • 7.Parking area

  • Please see site diagram attached for location of parking.

  • 8. Fire risk and emergency exit route

  • Emergency exit routes.

  • 9. First Aider

  • First Aid information

  • 10. Maximum number of employees on site ( All assigned staff names can be found on the plan of work Tool box register section ?? )

  • 11. CDM Information.

  • Please give details of CDMC and Principle contractor.

  • Weekend works.

  • Night Work.

  • 12. Times on site.

  • Please detail site times.

  • 13. Start date.

  • 14. Anticipated Finish date.

  • 15. Anticipated date and time for removal works.

  • Number of days

  • 16. Has an asbestos survey been received.

  • Management survey.

  • Refurbishment Demolition survey

  • Bulk Sample

  • Company who supplied asbestos information.

  • 17. Are other licence holders involved in the works.

  • Please give name address and contact number of relevant person.

3. Asbestos information

  • 1. Type of Asbestos

  • 2. Form of Asbestos.

  • 3. Is asbestos in good condition.

  • Has air monitoring evidence been supplied with satisfactory results

  • A pre clean of the area must be undertaken before works commence, operatives will carry out the pre clean prior to erecting the enclosure, the operatives will transit from the DCU in protective Type 5 overalls and Half mask respirator and enter the work area, the work area will be pre cleaned using a H Type vacuum cleaner and wiped with anti static rags before erecting the enclosure, full method in section 5.

  • 4. Is the Asbestos sealed.

  • Painted

  • Wallpaper

  • Over clad

  • 5. Is the asbestos at high level.

  • Type of access equipment needed.

  • 6. Location of asbestos to be worked on.

  • Please detail.

  • 7. Asbestos fixing.

  • Asbestos Fixings.

  • 8. Total quantity of asbestos to be removed

  • Average approx size of panels, sheets, tiles, sections etc.

  • Number of panels, Sheets, tiles, sections etc.

  • Photo of panels, sheets with measurements.

  • Additional information.

  • 9. Anticipated number of waste bags.

  • 10. Anticipated number of waste Wraps.

  • 11. Have voids been identified behind asbestos material.

  • Voids have been taken into account during enclosure measurements, following the removal of the asbestos the void will be open, the void will be cleaned using H Type vacs and anti static rags, if voids ingress then the void will be sealed either using a small bag filled with expanding foam or 1000g polythene sealed with Glue and tape. The void will be shown to the analyst to include a visual inspection. The void shall be unsealed as part of the procedure for dismantling the enclosure.

  • 12. Is anything attached to the asbestos.

  • Does the item need to be saved.

  • Please detail saved item.

4. Control Measures.

  • 1. Expected exposure without control measures.

  • 2. Is Air Monitoring required.

  • 4 stage clearance

  • Personal monitoring

  • Reassurance test

  • Background test

  • Leak test

  • Time and date analyst is required.

  • Name of Analytical company employed.

  • Required PPE for general site conditions

  • Colour of coveralls for General Duties

  • Colour of coveralls for Removal works

  • Colour of coveralls for Transiting between Enclosure/DCU

  • Colour of coveralls for Transiting Waste from Enclosure

  • Who will witness the smoke test.

  • Please detail who will witness smoke test.

  • Is a secondary barrier required

  • Location of secondary barrier

  • Vision panels

  • Location of CCTV.

  • Please detail location of CCTV.

  • Please state type of mask to be worn for General Duties

  • Please state type of mask to be worn for Pre cleaning

  • Please state type of mask to be worn for Works on asbestos

  • Please state type of mask to be worn for Transiting waste

  • Please state type of mask to be worn for Transiting from DCU to enclosure

  • Please note operatives should only wear a half mask for 45 mins in every hour, with a rest period of 15 mins. During the rest period the mask should be cleaned and dried inside and out, operatives should ensure a correct fit is archived before returning to working duties.

  • 13. Type of BS8520 Equipment to be utilised

  • Shadow vacuuming

  • Air management systems

  • Roving head attachment

  • Roving head attachment is to be connected to the NPU prior to a smoke test, the roving head will be moved around the enclosure as the supervisor see fit and following the removal works, the bends in the Ducting have been taken into account with a percentage uplift applied to the final calculation of the total number of air changes the chosen NPU will provide.

  • How is surfactant to be applied.

  • Surfactant mixed at 10:1 will be applied at a rate of 1 litre per meter to the asbestos product being removed. Surfactant will be issued in 5 gallon drums pre mixed by the stores department to ensure the correct mix, this also allows our monitoring team to monitor the use of surfactant and record details for training needs analysis.

  • Needle pattern for injection

  • Please detail needle pattern.

  • Decontamination requirements

  • Type of unit required

  • Waste water disposal.

  • Preferred location of unit.

  • 21. Additional comments.

  • 23. Expected exposure using control measures.

  • Expected exposure levels are calculated using Multi base, Personal air monitoring data is used to formulate a company average.

5. Methods

  • 1. Enclosure dimensions.

  • 2. Is a power source for enclosure plant available.

  • 3. High level access equipment.

  • Type of access equipment needed.

  • For enclosure building

  • For removal works

  • Pre clean of General Dust

  • Pre cleaning of general dust and debris will be carried out using H Type vacs and anti static rags, all ledges and surfaces will be vacuumed clean and wiped before the enclosure material is erected, this should ensure the enclosure has maximum adhesion to the support. Operatives will be required to wear General PPE and General works coveralls.

  • Pre clean of poor condition asbestos

  • A pre clean of the area must be undertaken before works commence, operatives will carry out the pre clean prior to erecting the enclosure, the operatives will transit from the DCU in protective Type 5 overalls and Half mask respirator and enter the work area, the work area will be pre cleaned using a H Type vacuum cleaner and wiped with anti static rags before erecting the enclosure. Operatives will carry out this duty erecting a respirator zone around the entry/exit points.

  • 600mm Air locks

  • 3 x 600mm x 600mm x 2m air locks will be constructed and attached to the enclosure. The air locks will be constructed using purpose built metal frames wrapped in 1000g polythene sealed with adhesive tape along the seams. The air locks will be interconnecting with oval shaped openings cut into each section. The oval openings will each have a weighted flap attached facing the enclosure, the flap will cover the oval shape at least 100mm each side. The air lock system will house pre decontamination facilities in the form of 2 x Buckets and sponges, 1 to be used to clean working footwear 1 to be used to clean face mask 1 x H type vacuum cleaner hose. The site supervisor will communicate verbally with the operatives via the air lock system.

  • 1m2 Air locks

  • 3 x 1m2 x 1m2 x 2m air locks will be constructed and attached to the enclosure. The air locks will be constructed using purpose built metal frames wrapped in 1000g polythene sealed with adhesive tape along the seams. The air locks will be interconnecting with oval shaped openings cut into each section. The oval openings will each have a weighted flap attached facing the enclosure, the flap will cover the oval shape at least 100mm each side. The air lock system will house pre decontamination facilities in the form of 2 x Buckets and sponges, 1 to be used to clean working footwear 1 to be used to clean face mask 1 x H type vacuum cleaner hose. The site supervisor will communicate verbally with the operatives via the air lock system.

  • Adjustable Air lock

  • 3 x adjustable air locks will be constructed and attached to the enclosure. The air locks will be constructed using purpose built metal frames wrapped in 1000g polythene sealed with adhesive tape along the seams. The air locks will be interconnecting with oval shaped openings cut into each section. The oval openings will each have a weighted flap attached facing the enclosure, the flap will cover the oval shape at least 100mm each side. The air lock system will house pre decontamination facilities in the form of 2 x Buckets and sponges, 1 to be used to clean working footwear 1 to be used to clean face mask 1 x H type vacuum cleaner hose. The site supervisor will communicate verbally with the operatives via the air lock system.

  • 9. Location of Air locks.

  • 10. Additional comments.

  • 600mm Bag lock

  • 3 x 600mm x 600mm x 2m bag locks will be constructed and attached to the enclosure. The bag locks will be constructed using purpose built metal frames wrapped in 1000g polythene sealed with adhesive tape along the seams. The bag locks will be interconnecting with oval shaped openings cut into each section. The oval openings will each have a weighted flap attached facing the enclosure, the flap will cover the oval shape at least 100mm each side. The bag lock system will be for the sole use of removing waste and should not be used to transit from. Warning signs will be displayed on the bag locks and surrounding area warning of the dangers presented by site conditions.

  • 1m2 Bag locks

  • 3 x 1m2 x 1m2 x 2m bag locks will be constructed and attached to the enclosure. The bag locks will be constructed using purpose built metal frames wrapped in 1000g polythene sealed with adhesive tape along the seams. The bag locks will be interconnecting with oval shaped openings cut into each section. The oval openings will each have a weighted flap attached facing the enclosure, the flap will cover the oval shape at least 100mm each side. The bag lock system will be for the sole use of removing waste and should not be used to transit from. Warning signs will be displayed on the bag locks and surrounding area warning of the dangers presented by site conditions.

  • Adjustable Bag lock

  • 3 x adjustable bag locks will be constructed and attached to the enclosure. The bag locks will be constructed using purpose built metal frames wrapped in 1000g polythene sealed with adhesive tape along the seams. The bag locks will be interconnecting with oval shaped openings cut into each section. The oval openings will each have a weighted flap attached facing the enclosure, the flap will cover the oval shape at least 100mm each side. The bag lock system will be for the sole use of removing waste and should not be used to transit from. Warning signs will be displayed on the bag locks and surrounding area warning of the dangers presented by site conditions.

  • 14. Additional comments.

  • 15. Location of Bag locks.

  • Enclosure build using the fabric of the building

  • The enclosure will be erected using the fabric of the building sealing all openings, floors and walls. All openings will be covered with 1000g polythene sealed with adhesive tape and glue if needed, staples may be used in timber works but must be removed as part of dismantling the enclosure. The floors will be covered with 1000g polythene sealed with adhesive tape and glue. The walls will be covered with 1000g polythene sealed with adhesive tape and glue if needed. 700g poly is to be used for secondary sacrificial sheeting where practicable. The integrity of the enclosure will be tested before works commence by means of a smoke test, the supervisor with the help of the operative will fill the enclosure with smoke via a hand held battery operated cordless fog machine. Smoke will be aimed at potential voids or areas of possible ingress including the enclosure walls, joints and seals the external accessible areas around the enclosure will be visually checked including adjacent rooms, voids and shafts possibly leading from the enclosure. Any smoke visually seen outside the enclosure will indicate a leak, the leak will be sourced and sealed using adhesive tape and spray glue if needed, expanding foam may be used for larger holes or voids and will be sprayed into a small bag inside the hole or void if accessible, if the leak cannot be sealed from inside the enclosure the leak will be sealed externally using the same method above, once all leaks detected have been satisfactory sealed the supervisor will sign the smoke test report and instruct the works to proceed.

  • Enclosure build using 2x2 timber frames

  • The enclosure will be erected using 2x2 timber supports. Timber frames will be constructed using 2x2 timber cut to size fixed together using cross head screws, 1000g polythene will be attached to the timber supports using staples sealed at the seams using adhesive tape and spray glue. The floors will be covered with 1000g polythene sealed with adhesive tape and glue. 700g poly is to be used for secondary sacrificial sheeting where practicable. The integrity of the enclosure will be tested before works commence by means of a smoke test, the supervisor with the help of the operative will fill the enclosure with smoke via a hand held battery operated cordless fog machine. Smoke will be aimed at potential voids or areas of possible ingress including the enclosure walls, joints and seals the external accessible areas around the enclosure will be visually checked including adjacent rooms, voids and shafts possibly leading from the enclosure. Any smoke visually seen outside the enclosure will indicate a leak, the leak will be sourced and sealed using adhesive tape and spray glue if needed, expanding foam may be used for larger holes or voids and will be sprayed into a small bag inside the hole or void if accessible, if the leak cannot be sealed from inside the enclosure the leak will be sealed externally using the same method above, once all leaks detected have been satisfactory sealed the supervisor will sign the smoke test report and instruct the works to proceed.

  • Enclosure build using the fabric of the building and 2x2 timber supports

  • The enclosure will be erected using the fabric of the building and 2x2 timber supports sealing all openings, floors and walls. The openings will be covered with 1000g polythene sealed with adhesive tape and glue if needed, staples may be used in timber works but must be removed as part of dismantling the enclosure. The walls will be covered with 1000g polythene sealed with adhesive tape and glue if needed. Timber frames will be constructed using 2x2 timber cut to size fixed together using cross head screws, polythene will be attached to the timber supports using staples sealed at the seams using adhesive tape and spray glue. 700g poly is to be used for secondary sacrificial sheeting where practicable. The integrity of the enclosure will be tested before works commence by means of a smoke test, the supervisor with the help of the operative will fill the enclosure with smoke via a hand held battery operated cordless fog machine. Smoke will be aimed at potential voids or areas of possible ingress including the enclosure walls, joints and seals the external accessible areas around the enclosure will be visually checked including adjacent rooms, voids and shafts possibly leading from the enclosure. Any smoke visually seen outside the enclosure will indicate a leak, the leak will be sourced and sealed using adhesive tape and spray glue if needed, expanding foam may be used for larger holes or voids and will be sprayed into a small bag inside the hole or void if accessible, if the leak cannot be sealed from inside the enclosure the leak will be sealed externally using the same method above, once all leaks detected have been satisfactory sealed the supervisor will sign the smoke test report and instruct the works to proceed.

  • 19. Additional comments.

  • 800 NPU

  • Number of units required

  • Location of units.

  • NPU will be sealed into the enclosure wall using adhesive tape and spray glue if needed venting out to atmosphere, the NPU filter will be changed at the end of each shift and will be monitored during the course of works for blockage, the NPU and vent ducting location is detailed in the site diagram section. The NPU will be thoroughly cleaned prior to the analyst starting his visual, the filter will be changed and the enclosure left to vent for a minimum of 30 mins before the unit is sealed using adhesive tape, the enclosure will then be handed over to the analyst to start the visual inspection of the enclosure.

  • 2300 NPU

  • Number of units required

  • Location of units.

  • NPU will be sealed into the enclosure wall using adhesive tape and spray glue if needed venting out to atmosphere, the NPU filter will be changed at the end of each shift and will be monitored during the course of works for blockage, the NPU and vent ducting location is detailed in the site diagram section. The NPU will be thoroughly cleaned prior to the analyst starting his visual, the filter will be changed and the enclosure left to vent for a minimum of 30 mins before the unit is sealed using adhesive tape, the enclosure will then be handed over to the analyst to start the visual inspection of the enclosure.

  • 5000 NPU

  • Number of units required

  • Location of units.

  • NPU will be sealed into the enclosure wall using adhesive tape and spray glue if needed venting out to atmosphere, the NPU filter will be changed at the end of each shift and will be monitored during the course of works for blockage, the NPU and vent ducting location is detailed in the site diagram section. The NPU will be thoroughly cleaned prior to the analyst starting his visual, the filter will be changed and the enclosure left to vent for a minimum of 30 mins before the unit is sealed using adhesive tape, the enclosure will then be handed over to the analyst to start the visual inspection of the enclosure.

  • 23. NPU locations.

  • 24. Additional comments.

  • Large H Type Vcas

  • Number of vacs required.

  • Small H Type Vcas

  • Number of vacs required.

  • 27. Additional comments.

  • 28. Method for works on asbestos.

  • 29. Will the DCU transit route need to be chaperoned.

  • Operatives will transit in PPE & RPE and will leave the DCU via the dirty end following the pre defined route from DCU as per the site diagram to the enclosure leaving transit coveralls and shoes in the clean end of the air lock system then entering the enclosure. Operatives leaving the enclosure will use the pre decontamination facilities provided to clean Boots, Mask and vacuum clean body and around face mask, the operative will follow the pre defined route back to the DCU and enter the dirty end of the unit and begin the decontamination process.

  • Transit route from enclosure to DCU including length of route.

  • 30. Will the waste transit route be the same as the DCU transit route.

  • Waste disposal method.

  • Type of waste carrier method.

  • Waste route from enclosure to sealed lockable unit.

  • The asbestos product will be removed following the method in section 5. then placed into a red asbestos waste sack and sealed at the neck, the waste will be placed close to the air lock system in readiness for removal from the enclosure the waste will be removed from the enclosure by double bagging into clear waste sacks following detailed procedures set out in the Cablesheer standard working procedures document, the waste will be transited following the pre defined route as per the site diagram in section 9. The waste will be carefully transited to the sealed waste unit for disposal at a registered landfill site. Warning signs will be displayed along the transit route clearly defining the route. Documentation in the form a waste note will be produced on site for use when waste is carried to the landfill site, the waste note will be stamped by the registered landfill site for filling at head office.

  • 31. Additional comments.

  • Cleaning of existing supports

  • Existing supports will be cleaned using H Type vacuum cleaners to shadow vac wire brushing of supports following the application of wetting agent. The holes left from the fixings will be cleaned using a hand held bradawl whilst shadow vacuuming. The supports will then be wiped clean using anti static rags, the supports will be dried thoroughly before the analyst is invited in. Supports must be shown to the analyst for inclusion into the 2nd stage of the 4 stage clearance.

  • Final clearance

  • When all waste material has been removed and double bagged from the enclosure the enclosure will be subject to a fine clean, all surfaces and ledges will be vacuumed clean using a H Type vac to remove dust and debris, the operatives will wipe clean all surfaces and ledges including the enclosure walls and floors, the final clean will be a vacuum of the floor on the way out of the enclosure. Once the supervisor has carried out a visual inspection of the works and is happy with the cleanliness the appointed analyst will be invited in to carry out the 2nd stage of the 4 stage clearance test. Once the enclosure has been cleared by the analyst the enclosure material will be removed in its entirety before leaving site. The analyst will then be invited to carry out out stage 4 of the 4 stage clearance. Once the analytical documentation has been received the Cablesheer team will leave the site clean and tidy. All Documentation relating the the works will be handed back to the office in the Box provided.

6. COSH Data sheets required

  • 1. Wetting agent.

  • Please see COSH Data sheet number 01

  • 2. Aerosol adhesive.

  • Please see COSH Data sheet number 02

  • 3. Adhesive tape.

  • Please see COSH Data sheet number 03

  • 4. Expanding Foam.

  • Please see COSH Data sheet number 04

  • 5. Smoke fluid.

  • Please see COSH Data sheet number 05

  • 6. X Tex Artex remover.

  • Please see COSH Data sheet number 06

7. Risk assessment

  • 1. Working at height.

  • Working at height must be undertaken with care and attention at all times, the site supervisor is responsible for maintaining the access equipment condition and recording findings in the site diary. The chosen access equipment must be protected from contamination if used inside an enclosure, all access equipment must be thoroughly cleaned before leaving an enclosure. Operative will will carry heavy or awkward items in pairs.

  • Podiums

  • Podiums will be used to gain the required access, the operatives using the podiums must make sure the wheels are locked and the door is securely closed with the podium sitting on level ground, the podiums must be maintained during site use by the supervisor, he must record all findings in the working at height log. The podiums will be protected from contamination by sealing poly to open areas, the podium must be thoroughly cleaned before it leaves the Work area. Podiums will be handled in pairs due to the awkwardness of the podium.

  • Steps with edge protection

  • Steps with edge protection will be used to gain the required access, the operatives using the steps must make sure the chain is secured with the steps sitting on level ground before works proceed, the steps must be maintained during site use by the supervisor, he must record all findings in the working at height log. The steps will be protected from contamination by sealing poly to open areas, the steps must be thoroughly cleaned before they leaves the Work area. Steps will be handled by one operative and will have wheels attached for ease of manual handling.

  • Ladders

  • Ladders will be used to gain the required access, the operatives using the ladders must make sure they sitting on level ground before works proceed, if ladders are to be used for long periods in one place then the ladders must be tied down. The ladders must be maintained during site use by the supervisor, he must record all findings in the working at height log. The ladders will be protected from contamination by sealing poly to open areas, the ladders must be thoroughly cleaned before they leaves the Work area. Ladders will be handled in pairs due to the awkwardness and the weight.

  • Alloy tower

  • Alloy towers will be used to gain the required access, operatives erecting the tower will be PASMA trained. The operatives using the towers must make sure they sitting on level ground and that all components are in place including edge protection and toe boards before works proceed. The tower must be maintained during site use by the supervisor, he must record all findings in the working at height log. The tower will be protected from contamination by sealing poly to open areas and the boards, the tower must be thoroughly cleaned before it leaves the Work area. Alloy tower will be handled in pairs due to the awkwardness and the weight.

  • Fixed scaffold

  • Fixed scaffold will be used to gain the required access, the scaffold will only be used once a completion certificate has been received. The operatives using the scaffold must make sure it sitting level and that all components are in place including edge protection and toe boards before works proceed. The scaffold must have either a hoist or rope and pulley present for transporting materials. The scaffold must be monitored during site use by the supervisor, he must record all findings in the working at height log. The scaffold will be protected from contamination by sealing poly to open areas and the boards, the scaffold must be thoroughly cleaned before the Cablesheer team leaves site.

  • Mobile elevated working platform

  • MEWP will be used to gain the required access, operatives using the unit will be IPAF trained. The operatives using the unit must make sure it is sitting on level ground and that all components are in place including edge protection and the door is closed before works proceed. The unit must be inspected during site use by the supervisor, he must record all findings in the working at height log. The unit will be protected from contamination by sealing poly to open areas and the floor, the unit must be thoroughly cleaned before it leaves the Work area. MEWP must only be handled by IPAF trained personnel.

  • Roof boards with edge protection

  • Roof boards will be used to gain the required access, operatives erecting the boards will be PASMA trained. The operatives using the boards must make sure it is sitting level and that all components are in place including edge protection and toe boards before works proceed. The boards must be maintained during site use by the supervisor, he must record all findings in the working at height log. The boards will be protected from contamination by sealing poly to open areas and the boards, the board must be thoroughly cleaned before it leaves the Work area. Roof boards will be handled in pairs due to the awkwardness and the weight.

  • 9. Additional information.

  • 10. Are services Live.

  • Are services safe.

  • Services to be isolated by.

  • Isolation requirements.

  • 11. Manual handling of plant and waste.

  • Heavy items will only be carried if the operative feels comfortable and the weight does not exceed between 18-20kg. Heavy items will be transported using an aid to prevent injuries from manual handling.

  • Hand tools

  • Operatives to wear gloves and eye protection when using hand tools along with required PPE, operatives will ensure the tool being used is in good working condition before it is used. Operatives will ensure that lighting is sufficient for the task.

  • Erection of enclosure

  • Operatives to wear the required PPE & RPE operatives will ensure the tools being used are in good working condition before they are used. Operatives will ensure that lighting is sufficient for the task. Operatives will ensure the plan of work is followed at all times.

  • 14. Additional information.

8. Equipment list

  • 1. H Type vacuum cleaner complying with BS8520-3

  • Number of units

  • 2. Negative pressure unit complying with BS8520-2

  • Number of units

  • 3. Low pressure spray containing pre mixed surfactant.

  • Number of units

  • 4. DCU.

  • Number of units

  • 5. CCTV.

  • Number of units

  • 6. Vision panels.

  • Number of units

  • 7. Steps with edge protection.

  • Number of units

  • 8. Alloy tower.

  • Number of units

  • 9. Podiums.

  • Number of units

  • 10. Ladders.

  • Number of units

  • 11. Additional information.

9. Site Diagrams including snapshot of NPU calculator & Local A&E unit.

  • 1. Site plans

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.