Information
-
Audit Title
-
Customer
-
Location/Well Site Name
-
911 Address and Coordinates
-
Well site entrance
-
Customer Representative/Consultant
-
Audit Conducted on:
-
Prepared by
-
Rig-up/Flow Hands on Site
Site Arrival
-
JSA filled out properly and signed by all personnel
-
Proper warning signs posted at entrance
-
All personnel in proper PPE
-
Location has designated smoking area
-
Lead flow hand identified
-
Name
-
ESD installed near entrance and identified
-
Other
-
Other
-
Additional Comments
Flow Lines
-
All flow iron upstream of choke must be tested to 10k and 5k downstream of choke banded/identified every 6 months
-
No threaded connections upstream of choke manifold
-
Minimize the use of threaded connections
-
Break apart ALL threaded connections and visually inspect before EVERY flow line installation
-
Tested to maximum anticipated pressure + an acceptable safety margin or working pressure
-
Unions are positioned correctly for direction of flow & checked for compatibility
-
Lines are not bowed or laid in a bind
-
Block tees are supported
-
All joints have whip-checks?
-
Other
-
Other
-
Additional Comments
Flow Line Anchors (CHK Standard)
-
Set as not to cause excessive dips, arches, or bows in flow lines
-
First anchor set as close to wellhead as feasible?
-
One anchor placed every joint upstream of manifold?
-
One anchor placed every other joint downstream of manifold?
-
When encountering bend or turn in flow line repeat process placing first one as close as feasible after turn with one every other joint thereafter
-
Verify that anchors have been driven flush to the top of line clamp (NO USE OF SUCKER RODS)
-
Verify that the clamps used with the anchors are correct size for the outside diameter of flow line
-
Verify that clamps/anchors are sufficiently bound together and annotate be broken apart
-
Insure that anchor clamps are 1/2" thick by 3" wide by 12" length with rod holes no greater than 1" or equivalent
-
Other
-
Other
-
Additional Comments
Sand Separator (if applicable)
-
Set in level position
-
Valves and related components function tested prior to flow back operations
-
All flanges contain correct nuts and bolts
-
Cleaned out prior to installation
-
Tested to maximum anticipated pressure plus and acceptable safety margin - if installed upstream of choke
-
By-pass installed and tested to system pressure
-
Rain cap installed on pop-off valve(s)
-
Fire extinguisher present and in proper working order
-
Annual and monthly inspections up to date
-
Other
-
Other
-
Additional Comments
Flow Back Separator
-
Set in level position
-
Adequate fall protection of tie-offs Built in or portable platforms if properly secured will suffice)
-
Valves checked prior to flow back and function tested at appropriate time.
-
Rain cap installed on pop-off valve(s)
-
Fire extinguisher present and in proper working order
-
Annual and monthly inspections up to date
-
Other
-
Other
-
Additional Comments
Flow Back Tank/ Gas Buster
-
Clean sand prior to transport
-
Set level
-
Adequate fall protection or tie-offs(built in or portable platforms if properly secured will suffice)
-
Easy access for tank gauging, walkways and stairs should not be damaged or missing pins
-
External valves not in use have barrier device installed in case of accidental opening
-
Set to provide easy truck access for hauling out produced fluids
-
Working wind sock installed near tank
-
Sight glass installed and clear
-
Fire extinguisher present and in proper working order
-
Annual and monthly inspections up to date
-
Other
-
Other
-
Additional Comments
Flare Line
-
Laid in straight line. All attempts made to cut down on direction changes.
-
Flanges have all bolts installed and uniformly tightened (no 1/2 nuts)
-
Line should extend 100 ft. From combustible source
-
Flare stack minimum of 6 inch OD with proper ignition system. Any changes must be per approved by Superintendant
-
Fire extinguisher present and in proper working order
-
-
Other
-
Other
-
Additional Comments
H2S
-
H2S contingency plan on location (if required)
-
H2S site specific procedures developed for location (if required)
-
H2S plan provided for well that may exceed 10 PPM
-
Personnel wearing 4 gas monitors?
-
Monitors charged and calibrated?
-
Other
-
Other
-
Additional Comments
Signature and Review
-
Signature of person conducting audit.