Information

  • Audit Title

  • Customer

  • Location/Well Site Name

  • 911 Address and Coordinates
  • Well site entrance

  • Customer Representative/Consultant

  • Audit Conducted on:

  • Prepared by

  • Rig-up/Flow Hands on Site

Site Arrival

  • JSA filled out properly and signed by all personnel

  • Proper warning signs posted at entrance

  • All personnel in proper PPE

  • Location has designated smoking area

  • Lead flow hand identified

  • Name

  • ESD installed near entrance and identified

  • Other

  • Other

  • Additional Comments

Flow Lines

  • All flow iron upstream of choke must be tested to 10k and 5k downstream of choke banded/identified every 6 months

  • No threaded connections upstream of choke manifold

  • Minimize the use of threaded connections

  • Break apart ALL threaded connections and visually inspect before EVERY flow line installation

  • Tested to maximum anticipated pressure + an acceptable safety margin or working pressure

  • Unions are positioned correctly for direction of flow & checked for compatibility

  • Lines are not bowed or laid in a bind

  • Block tees are supported

  • All joints have whip-checks?

  • Other

  • Other

  • Additional Comments

Flow Line Anchors (CHK Standard)

  • Set as not to cause excessive dips, arches, or bows in flow lines

  • First anchor set as close to wellhead as feasible?

  • One anchor placed every joint upstream of manifold?

  • One anchor placed every other joint downstream of manifold?

  • When encountering bend or turn in flow line repeat process placing first one as close as feasible after turn with one every other joint thereafter

  • Verify that anchors have been driven flush to the top of line clamp (NO USE OF SUCKER RODS)

  • Verify that the clamps used with the anchors are correct size for the outside diameter of flow line

  • Verify that clamps/anchors are sufficiently bound together and annotate be broken apart

  • Insure that anchor clamps are 1/2" thick by 3" wide by 12" length with rod holes no greater than 1" or equivalent

  • Other

  • Other

  • Additional Comments

Sand Separator (if applicable)

  • Set in level position

  • Valves and related components function tested prior to flow back operations

  • All flanges contain correct nuts and bolts

  • Cleaned out prior to installation

  • Tested to maximum anticipated pressure plus and acceptable safety margin - if installed upstream of choke

  • By-pass installed and tested to system pressure

  • Rain cap installed on pop-off valve(s)

  • Fire extinguisher present and in proper working order

  • Annual and monthly inspections up to date

  • Other

  • Other

  • Additional Comments

Flow Back Separator

  • Set in level position

  • Adequate fall protection of tie-offs Built in or portable platforms if properly secured will suffice)

  • Valves checked prior to flow back and function tested at appropriate time.

  • Rain cap installed on pop-off valve(s)

  • Fire extinguisher present and in proper working order

  • Annual and monthly inspections up to date

  • Other

  • Other

  • Additional Comments

Flow Back Tank/ Gas Buster

  • Clean sand prior to transport

  • Set level

  • Adequate fall protection or tie-offs(built in or portable platforms if properly secured will suffice)

  • Easy access for tank gauging, walkways and stairs should not be damaged or missing pins

  • External valves not in use have barrier device installed in case of accidental opening

  • Set to provide easy truck access for hauling out produced fluids

  • Working wind sock installed near tank

  • Sight glass installed and clear

  • Fire extinguisher present and in proper working order

  • Annual and monthly inspections up to date

  • Other

  • Other

  • Additional Comments

Flare Line

  • Laid in straight line. All attempts made to cut down on direction changes.

  • Flanges have all bolts installed and uniformly tightened (no 1/2 nuts)

  • Line should extend 100 ft. From combustible source

  • Flare stack minimum of 6 inch OD with proper ignition system. Any changes must be per approved by Superintendant

  • Fire extinguisher present and in proper working order

  • Other

  • Other

  • Additional Comments

H2S

  • H2S contingency plan on location (if required)

  • H2S site specific procedures developed for location (if required)

  • H2S plan provided for well that may exceed 10 PPM

  • Personnel wearing 4 gas monitors?

  • Monitors charged and calibrated?

  • Other

  • Other

  • Additional Comments

Signature and Review

  • Signature of person conducting audit.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.