Information
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Quality Management System (QMS)
-
1. Are current copies of QMS manuals accessible?
-
Has a CAPAR been raised?
-
CAPAR number:
-
2. Are superseded documents marked as superseded and removed from use?
-
Has a CAPAR been raised?
-
CAPAR number:
Project Quality Plan (PQP)
-
3. Has the project quality plan been reviewed and reissued with the revision status maintained within the document?
-
Has a CAPAR been raised?
-
CAPAR number:
-
4. Is the PQP<br>. Authorised for use?<br>. Correctly identified<br>. Controlled<br>. Quality policy and objectives clearly defines<br>. Organisational chart fined<br>. Roles and responsibilities defined and signed off
-
Has a CAPAR been raised?
-
CAPAR number:
-
5. Staff are inducted into the project quality plan (evidenced by signing the quality induction register)
-
Has a CAPAR been raised?
-
CAPAR number:
Drawings
-
6. Drawings have been signed as reviewed by the project manager?
-
Has a CAPAR been raised?
-
CAPAR number:
-
7. Construction documents are marked "for construction".
-
Has a CAPAR been raised?
-
CAPAR number:
-
8. Superseded documents have been marked as superseded and taken out of circulation.
-
Has a CAPAR been raised?
-
CAPAR number:
-
9. Changes to the scope of work are clearly marked on the construction drawings.
-
Has a CAPAR been raised?
-
CAPAR number:
-
10. Does the site manager know where the master document register is located in the IMS?<br><br>Has it been printed off and marked up as checked for being correct by the site manager?
-
Has a CAPAR been raised?
-
CAPAR number:
-
11. All documents are controlled and stamped?
-
Has a CAPAR been raised?
-
CAPAR number:
Design
-
12. Has the project manager forwarded the safety in design awareness letter to the client?
-
Has a CAPAR been raised?
-
13. Has the project manager reviewed the consultants design plans and stamped them "reviewed and accepted for use".
-
Has a CAPAR been raised?
-
14. Are design meeting minutes available?
-
Has a CAPAR been raised?
-
15. Are all design changes recorded on the design change register.
-
Has a CAPAR been raised?
-
16. Have safety in design risks been included in the project risk register and SWMS where applicable?
-
Has a CAPAR been raised?
Client Correspondence
-
17. Is incoming correspondence handled in accordance with the correspondence work instruction?
-
Has a CAPAR been raised?
-
CAPAR number:
-
18. Are all client site instructions recorded in the register and filed?
-
Has a CAPAR been raised?
-
CAPAR number:
-
19. Are all client site instructions closed out?
-
Has a CAPAR been raised?
-
CAPAR number:
RFI's, Variations, ETO's and Site Instructions (SI) to Subcontractors
-
Are RFI's, variations, EOT's and SIS recorded in the data?
-
Has a CAPAR been raised?
-
CAPAR number:
Internal Correspondence
-
21. Is incoming correspondence handled in accordance with company procedures?
-
Has a CAPAR been raised?
-
CAPAR number:
Project Management
-
22. Is the procurement schedule maintained and up to date?
-
Has a CAPAR been raised?
-
CAPAR number:
-
23. Have subcontractor interviews been carried out and are records available?
-
Has a CAPAR been raised?
-
CAPAR number:
-
24. Does the subcontractor interview identify quality requirements of the subcontractor?
-
Has a CAPAR been raised?
-
CAPAR number:
-
25. Is the project manager aware of the location of the unacceptable subcontractors list?
-
Has a CAPAR been raised?
-
CAPAR number:
-
26. Is it he evidence available to indicate that the project manager has checked the qualifications and suitability of consultants to indicate they are capable of doing the work. I.E; consultants design plan indicating the qualification and experience of key personnel.
-
Has a CAPAR been raised?
-
CAPAR number:
Project Establishment
-
27. Is the project establishment checklist completed?
-
Hs a CAPAR been raised?
-
CAPAR number:
Program of Works
-
28. Is project managers program prepared in an appropriate format and up to date?
-
Has a CAPAR been raised?
-
CAPAR number:
-
29. Is the works program on display?
-
Has a CAPAR been raised?
-
CAPAR number:
-
30. Is the works program regularly reviewed and the revision status/date shown?
-
Has a CAPAR been raised?
-
CAPAR number:
Site Surveillance
-
31. Are site inspection records available in the site diary?
-
Has a CAPAR been raised?
-
CAPAR number:
-
32. Are site photographs available in the IMS for all works undertaken?
-
Has a CAPAR been raised?
-
CAPAR number:
Tender/Contract Review
-
33. Tender contract review completed and filed correctly?
-
Has a CAPAR been raised?
-
CAPAR number:
Customer Property
-
34. Is the clients property handled in accordance with the procedure for customer property?
-
Has a CAPAR been raised?
-
CAPAR number:
-
35. Is the clients property stored in a designated storage area?
-
Has a CAPAR been raised?
-
CAPAR number:
Traceability
-
36. Are works or batches of supplies adequately identified to allow for traceability?
-
Has a CAPAR been raised?
-
CAPAR number:
-
37. Are contractual traceability requirements documented?
-
Has a CAPAR been raised?
-
CAPAR number:
-
38. Is there evidence available to indicate that the "product identification and traceability" procedure has been followed?
-
Has a CAPAR been raised?
-
CAPAR number:
Meetings
-
39. Are records of client meetings available?
-
Has a CAPAR been raised?
-
CAPAR number:
-
40. Have actionable items recorded in client meeting minutes been closed out?
-
Has a CAPAR been raised?
-
CAPAR number:
-
41. Are minutes of subcontractor coordination meetings available on a fortnightly basis?
-
Has a CAPAR been raised?
-
CAPAR number:
-
42. Are performance evaluations by the client available?
-
Has a CAPAR been raised?
-
CAPAR number:
-
43. Are subcontractor performance reports (SPRs) completed?
-
Has a CAPAR been raised?
-
CAPAR number:
Project Plans
-
44. If an industrial relations plan is required, is it available?
-
Has a CAPAR been raised.
-
CAPAR number:
-
45. If a training plan is required, Is it available?
-
Has a CAPAR been raised.
-
CAPAR number:
-
46. If an aboriginal participation plan is required, is it available?
-
Has a CAPAR been raised.
-
CAPAR number:
-
47. Are WHS and environmental plans available?
-
Has a CAPAR been raised.
-
CAPAR number:
-
48. If a traffic plan is required, is it available?
-
Has a CAPAR been raised.
-
CAPAR number:
-
49. Is a dilapidation report available?
-
Has a CAPAR been raised.
-
CAPAR number:
-
50. Dial before you dig and service locators certificate available if required?
-
Has a CAPAR been raised.
-
CAPAR number:
-
51. Are NCNs recorded in the database?
-
Has a CAPAR been raised.
-
CAPAR number:
-
52. Are NCNs closed out by the nominated date?
-
Has a CAPAR been raised.
-
CAPAR number:
Training and Development/Levels of Competency
-
53. How many individual levels of competency determined?<br><br>How are various individuals assigned to various projects and/or takes? On what basis?
-
Has a CAPAR been raised?
-
CAPAR number:
-
54. Are training records available for all site staff?
-
Has a CAPAR been raised?
-
CAPAR number:
Internal Auditing
-
55. Is there an internal audit schedule in place?
-
Has a CAPAR been raised?
-
CAPAR number:
-
56. How many trained auditors are there? <br>Verify qualifications.
-
Has a CAPAR been raised?
-
CAPAR number:
-
57. Are external audit reports available?
-
Has a CAPAR been raised?
-
CAPAR number:
-
58. Have NCNs identified during external audits been closed out?
-
Has a CAPAR been raised?
-
CAPAR number:
-
59. Are internal audit reports available?
-
Has a CAPAR been raised?
-
CAPAR number:
-
60. Have NCNs and observations identified during internal audits, safety walks, spot audits and project management checklists been closed out?
-
Has a CAPAR been raised?
-
CAPAR number:
Inspection and Test Plans (ITP's)
-
61. Is there an up to date ITP's register?
-
Has a CAPAR been raised?
-
CAPAR number:
-
62. Have the ITP's been reviewed?
-
Has a CAPAR been raised?
-
CAPAR number:
-
63. Are ITP's being progressively signed off as work is completed?
-
Has a CAPAR been raised?
-
CAPAR number:
-
64. Are delivery dockets available and filed appropriately?
-
Has a CAPAR been raised?
-
CAPAR number:
-
65. Are ITP's logically set out?
-
Has a CAPAR been raised?
-
CAPAR number:
-
66. Is the test equipment register maintained?
-
Has a CAPAR been raised?
-
CAPAR number:
-
67. Are calibration certificates available for all test equipment?
-
Has a CAPAR been raised?
-
CAPAR number:
-
68. Calibration carried it by a NATA approved organisation (noise and asbestos monitoring)
-
Has a CAPAR been raised?
-
CAPAR number:
-
69. Does the equipment show calibration status?
-
Has a CAPAR been raised?
-
CAPAR number:
-
70. Is equipment out of calibration kept from being used?
-
Has a CAPAR been raised?
-
CAPAR number:
-
71. Is equipment correctly stored?
-
Has a CAPAR been raised?
-
CAPAR number:
-
72. Is subcontractors test equipment calibrated?
-
Has a CAPAR been raised?
-
CAPAR number:
-
73. Has the rood safety certificate been obtained from the roofers?
-
Has a CAPAR been raised?
-
CAPAR number:
Concrete Test
-
74. Are concrete inspection and pour records available?
-
Has a CAPAR been raised?
-
CAPAR number:
-
75. How is non conforming work identified?
-
Has a CAPAR been raised?
-
CAPAR number:
Non-Conforming Product
-
76. Are non conforming products prevented from being included in the project?
-
Has CAPAR been raised?
-
CAPAR number:
-
77. How is non conforming work identified?
-
Has CAPAR been raised?
-
CAPAR number:
-
78. Are records available to indicate that appropriate persons have been notified of non conforming products?
-
Has CAPAR been raised?
-
CAPAR number:
-
79. Are NCNs issued for non conforming products?
-
Has CAPAR been raised?
-
CAPAR number:
-
80. Are NCNs for non conforming products closed out by the nominated date?
-
Has CAPAR been raised?
-
CAPAR number:
-
81. Are all complaints (client, member of the public etc) reviewed and handled as per the project quality plan. IE; an NCN issued and followed through?
-
Has CAPAR been raised?
-
CAPAR number:
-
82. Is a defects list compiled?
-
Has CAPAR been raised?
-
CAPAR number:
-
83. Are records available to indicate that subcontractors have been advised of defects (NCNs issued to subcontractors)?
-
Has CAPAR been raised?
-
CAPAR number:
-
84. Has the defects list been closed out and signed off?
-
Has CAPAR been raised?
-
CAPAR number: