Bathroom Inspection check list Hurlingham Walk
Activity: 1st fix-timber framing in the bathrooms
-
Check type of bathroom/ensuite.
-
Check the area is clear of materials and debris.
-
Check ceilings completed in the bathroom including bulk head
-
Check type of bathroom/ensuite.
-
Check WC framing ( Installed by plumbing sub-contractor ) to centre line & check levels.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: Low level vanity boxing and bath framework support .
-
Check that bath support frame is installed according to the drawing
-
Check low level framing been installed according to the drawing setting out ,plumb and level<br>
-
Check framework been cladded in plywood and all necessary access panels been installed according to the drawing and on keku clips
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: Bath framework
-
Check that bath installed by M&E Contractor
-
Check that Bath panel framework been completed and cladded in plywood including access panel
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: Survey and installation of glass panel surround and associated trims
-
Check that glass trims been installed according to the drawings and the glass been surveyed .
-
Check that glass been installed
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor
Activity: Installation of Mirrored Vanity Unit
-
Check that Mirrored Vanity Unit been installed according to the drawing .<br>
This inspection sheet confirms that the item or area detailed above is 100% completed in line with the current specification, drawings and pre agreed sample panels although still remaining Sub Contractors responsibility until practical completion has been achieved.
-
Signed on behalf of Sub-Contractor
-
Signed on behalf of Main Contractor