Inspection Checklist
-
Are all welds in good working condition?
-
Are all testing assemblies in good working condition?
-
Are the pressure gauges in good working condition?
-
Are calibration certificates current and completed?
Test Information
-
Nominal (D) Size of Pipe
-
Length of Main Being Tested
-
Test Pressure (kPa)
-
Mains Material
Test Details
-
Start Time
-
Start Pressure Test - Pressure Gauge Photo
-
Start Pressure (kPa)
-
End Time
-
End Pressure Test - Pressure Gauge Photo
-
End Pressure (kPa)
-
Did the main hold pressure at 800 kPa for 15 minutes?
-
Additional Comments
-
Additional photos
-
This is to certify that the main in question passed the required pressure testing and was witnessed by an SEW Project Engineer.
-
This is to certify that the contractor is in agreement with the assessment conducted by SEW.