Eminence Fab Plant Shift Handoff
-
Conducted on
-
Shift
-
Prepared by
Franklin 1
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Franklin 2
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Franklin 3
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Boschert 1
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Boschert 2
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Komatsu
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Presses
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Queen
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Pega
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Trumpf
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Ehrt
-
Were there any safety incidents or near misses during the shift?
-
Were there any quality issues during the shift?
-
Note issue and quantity
-
Was the production goal met or exceeded for the shift?
-
Note issues and amount of shortfall
-
Is the area clean and in order with all tools and supplies in place?
-
Take a picture of the Tier 4 board - complete shift
Additional Comments
-
Any Additional Comments or Issues for Next Shift?