Title Page
-
Conducted on
-
Shift:
Production Audit
Team A: (MB,HM, Blenders, Line 6A/B)
-
1.) Masterbatch: All batch sheets being filled out properly. (Ex .initialed, pounds weighed, supervisor/operator sign off, bin numbers, locations wrote down)
-
2.) Masterbatch: Materials being stored properly, lids on barrels, clips on open bag, etc. (address any issues)
-
3.) Masterbatch: The area is in good order (floor, tool board, lids closed on vessels not in use) (address any issues)
-
4) Do the Operator(s) have any concerns at the end of their shift?
End of Shift: (6B/HM/Blending)
-
Line 6B:
-
MB/Blending:
-
HM:
Team B (Line 3)
-
1.) Line 3: Running to rate? The extruder audit sheet being filled out, any items out of tolerance.
-
2.) Line 3: Pellet quality assurance (Pellet Count) form filled out.
-
3.) Overall cleanliness of Team B (address any issues)
-
4.) Do the Operator(s) have any concerns (Safety, Quality, Production, etc.)
End of Shift: (Line 3)
-
Line 3:
Team C (Line 4)
-
1.) Line 4: Process Audit sheet being filled out completely, any items out of tolerance (if so address)
-
2.) Line 4: Pellet quality assurance (Pellet count)form filled out correctly.
-
3) Line 4 : Process Sheet: are the raw materials being used correct? Percentages correct on computer vs Process Sheet?
-
4.) Line 4: Raw Material Locator Sheets being filled out correctly with initials and weights/lot# used. (issues have operator correct)
-
5.) Line 4: Running to Rate, if not what are the factors
-
6.) Line 4: Process Sheet are the Special Instructions being followed. (Ex.Foil liner)
-
7.) Quench Tank and purge pan on Line 4, being used? (if not address immediately)
-
8.) Overall cleanliness of Line 4 and mezzanine? (address any issues)
-
9.) Does the Line 4 Operator have any concerns at the end of their shift?
End of Shift: Line 4
-
Line 4:
Team C (Line 4A)
-
1) Line 4A: Process Sheet: are raw material being used correct? Percentages correct on computer vs Process Sheet?
-
2.) Line 4A; Running to Rate, if not what are the factors
-
3.) Line 4A: Process Audit sheet being filled out completely, any items out of tolerance (if so address)
-
3.) Line 4A: Raw Material Locator Sheets being filled out correctly with initials and weights/lot # used (issues have operators correct)
-
4.) Line 4A: Pellet quality assurance (Pellet count) form filled out correctly.
-
5.) Line 4A: Process Sheet are the Special Instructions being followed.( Ex. Foil liners)
-
6.) Quench Tank and purge pans on Line 4A, being used? (if not address immediately)
-
7.) Overall cleanliness of Line 4A and mezzanine?
-
8.) Do the Line 4A Operator(s) have any concerns at the end of their shift?
End of Shift: Line 4A
-
Line 4A:
Team C (Line 5)
-
1.) Line 5: Process Audit sheet being filled out completely, any items out of tolerance (if so address)
-
2.) Line 5: Raw Material Locator Sheets being filled out correctly with initials and weights/lot # used. (issues have operators correct)
-
3.) Line 5: Pellet quality assurance(Pellet count)form filled out correctly.
-
4.) Line 5: Running to Rate, if not what are the factors
-
5.) Line 5: Process Sheet are the Special Instructions being followed?
-
6.) Quench Tank and purge pan on Line 5 being used? (if not address immediately)
-
7.) Overall cleanliness of Line 5 and mezzanine (address any issues)
-
8.) Do the Line 5 Operator(s) have any concerns at the end of their shift?
End of Shift: Line 5
-
Line 5:
Team D (Line 8)
-
1) Line 8: Line Audit sheet being filled out, any items out of tolerance (if so address)
-
2) Line 8: Locator, Solid add, liquid add, and pigment worksheets being filled out properly and correctly.(issues have operators correct)
-
3) Line 8: Pellet Quality Assurance (Pellet count) form being filled out correctly, any material out of spec.
-
4) Line 8: Special Instructions (op.10 text) being followed, if not please provide details.
-
5) Line 8: Is the Line running to rate? if not please provide details.
-
6.) Line 8: Overall cleanliness of Line 8.
-
7.) Do the operator(s) have any concerns at the end of their shift?
End of Shift: Line 8
-
Line 8:
Team D (Line 11)
-
1.) Line 11: Line Audit Quality Audit form being filled out, any items out of tolerance or issues.(if so address)
-
2.) Line 11: Pellet Quality Assurance (Pellet count) form being filled out correctly , any issues
-
3.) Line 11: Raw Material Locator Sheets being filled out correctly with initials and weights/lot # used.(issues have operators correct)
-
4.) Line 11: Is the Line running to rate? if not please provide details.
-
5.) Line 11: Overall cleanliness of Line 11 (address any issues)
-
6.) Quench Tanks: on Line 11 and being used?
-
7.) Do the operator(s) have any concerns at the end of their shift?
End of Shift: Line 11
-
Line 11:
3D Area, Quench Area
-
1) Filament (3D): Spot check 3 completed spools to confirm labels are correct
-
2.) Do the 3D operator(s) have any concerns at the end of their shift?
Quench Area
-
1.) Quench Area: Organized ,Chunk boxes labeled and not full, any Tanks need emptied? (Address any issues)
Positive safety observation noticed
-
1.)Witnessed the below positive observation
COMPLETED BY
-
Name & Signature