Information
-
Document No: (Project Number-Audit No for this Project-Year-Month)
-
Audit Title:
-
Conducted on:
-
Location
-
Client / Site
-
Prepared by:
-
Personnel In Attendance:
Previous Audit
-
Have all Opportunities for Improvement and Non-Conformances from the previous Audit been closed out?
-
Were they closed out in the appropriate timeframe?
Site Inspection
-
Is/Are the Wiley Site Signage Boards in a conspicuous location?
-
Is the Site Entry easily located, well sign posted?
-
Is there sufficient additional signage around the site?
-
PPE - Is PPE being used throughout the site? Is PPE Signage in place?
-
Site Entry is well controlled?
-
Excavations are barricaded and any plant movement is not occurring without agreed control methods?
-
Excavations over 1.5m are Battered or Benched or have Geo-Tech sign-off?
-
Adequate Lighting is in use in construction and personnel movement areas?
-
Housekeeping is being performed daily?
-
Ladder Safety is being addressed - Ladders are secured and all necessary control measures are in place?
-
Step Ladders are rated to 120KG and are Industrial Grade?
-
Extension Ladders are only being used for safe access, are secured top/bottom, and extend 1.0m above the landing platform, have safe mounting/dismounting features?
-
Mobile Scaffolds have been erected correctly - have adequate bracing and are not being moved with personnel on the platform?
-
Mobile Scaffolds with Platform height over 4.0m have been erected by qualified personnel and in accordance with the manufacturers specifications?
-
Fixed Scaffolds have been erected by qualified personnel, are suitable for the work and have all the necessary features as per the COP?
-
Electrical Extension Leads, Power Packs, battery Chargers and all electrical equipment on site is Tested and Tagged and in date?
-
Electrical Distribution Boards are tested and tagged, RCD's are tested Monthly? (Power Pack RCD's test daily before use)
-
Permit Systems are in use?
-
All Hot Works have an associated Hot Works Permit, and Fire Fighting equipment is close by and adequate?
-
Fire Fighting Equipment extinguishers, FHR's, Fire Blankets, etc, exist wherever an increased fire load exists?
-
Plant & Equipment storage around the site is not interfering with works requirements, dunnage is in use, barricading and signage is in place?
-
Site Fencing is adequate, suitable to the security requirements, provides adequate protection to the public/clients personnel?
-
High Risk Construction Activities are being controlled appropriately? WMS In place for all HRCW?
Traffic Management
-
Parking is being controlled on site and in accordance with agreements with the client?
-
Vehicle / Personnel segregation has been considered and positive Communications with vehicle operators is in place?
-
Is Safe Access Addressed? Pedestrian Crossings? Signage? Traffic Control? Defined and segregated walkways?
-
Are there any delays caused by Construction Traffic?
-
Is there adequate Signage for Construction vehicles? Laydown Ares? Stockpiles? Deliveries?
-
Is the Construction Carpark being maintained adequately and is adequately sign posted?
-
Are Site Vehicle (trucks) complying with the Clients' requirements?
Health & Safety Management System
Construction Management Plan (CMP)
-
Is the CMP on site, signed by all relevant parties, and the correct revision?
-
Have all necessary personnel been tool-boxed into, and signed onto the CMP? (Labourers, carpenters, additional Wiley Site Personnel, CA, incl Labour Hire personnel)
-
Has the CMP been distributed to the necessary people external to Wiley?
-
Is the Site Manager / Foreman aware of the contents of the Appendices?
-
Is there a Daily Site Diary being completed?
Registers
-
Is the Incident & Non-Conformance Register Up To Date?
-
Is the Site Visitor/Worker Register in use and being completed?
-
Has the Haz Sub Register been kept up to date?
-
Is the Corrective Action Register in Use?
-
Is the Plant & Equipment Register for the site in use?
-
Is there a current Site Induction Register?
-
Is there a Work Method Statement Register?
-
Is a First Aid Register being maintained in the First Aid kit?
Certificates
-
Temporary Power Certificate?
-
Plant & Lifting Equipment Certificates?
-
Scaffold Certificates?
-
Other?
Crane Records
-
Maintenance Records, lifting equipment and slings, safety certificates, etc?
-
Maintenance Records for Concrete Pumps?
Workforce Safety Knowledge Documents - (Laminated)
-
Site Safety Rules?
-
Site Layout Plan?
-
Emergency Evacuation Plan? Has this been disseminated to the Workforce?
-
SQE Policy and Certificates?
Amenities
-
Are Amenities being maintained in a clean manner? Soap? Hand Towels, Toilet paper, adequate cubicles for gender separation?
-
Is there a lunchroom in use, Microwave, adequate fridge space, adequate tables for the workforce, and maintained in a clan and tidy manner daily?
-
Drinking Water is located at regular intervals around site or other means of obtaining water have been discussed?
-
Is there an adequately stocked First Aid Kit on site and is the equipment in date?
-
Are First Aiders names shown on Notice Boards or recorded anywhere?
High Risk Construction Work
-
All HRCW is being performed with the required controls in place?
-
Are all HRC Activities being recognised and managed accordingly?
Communication and Consultation
-
Are site communications being performed adequately? Prestart Meetings, Toolbox Meetings, Safety Committee Meetings?
-
Are Minutes being recorded for all Meeting types being used on the project, and being distributed to the relevant parties as required?
-
Is there a Notice Board set up on site to provide an information platform to the workforce?
-
All personnel on site are Site Inducted, or are being escorted at all times?
-
A Sign-In / Sign-Out Register is in place and compliance is mandatory?
Quality Management System
-
An Inspection & Test Plan exists for the project and is being completed in accordance with the requirements?
-
inspections and Tests are being signed off by the relevant consultants / Client where required?
-
Are Subcontractors performing all necessary Inspections and Tests?
-
Is there a documented defect or non-conforming capturing system in place?
-
Are defective or non-conforming works notified to the subcontractor and followed up to closure?
-
Is the general Permit to Work System in use on this Project?
-
If 'Yes', are the diciplines in the Form being completed to maximise effectiveness?
Environmental Management Systems
-
Is effective Storm Water protection is in place. Sausages at Yard Gullies, Silt fencing is effective and maintained, and storm water run-off is controlled as required by use of fenders, diverters or similar?
-
Site Compound is Clean & Tidy, all rubbish in receptacles, no trip hazards lying around?
-
Are Drainage inlets open to receive flow?
-
Are Earthworks Stock Piles protected using sediment fence etc?
-
Spill Kits. Is there a spill Kit(s) available on site?
-
Is the Spill Kit correctly stocked and is it being replenished after use each time?
-
Does hazardous Substance Storage conform with the requirements? Has appropriate staff been trained in Haz Sub?
-
Dust extraction is in place where required or the correct PPE is being used?
-
Are roadways dirty / dusty from construction traffic and in need of cleaning?
-
Have there been any Environmental complaints received - Dust? Noise? Other? and hve any Authority Notices been received? (Council / EPA / Govt Authoirity)
-
Site Rubbish is being dealt with effectively? Bins are regularly emptied?
-
A Recycling Plan is in place as required and is being adhered to?
-
Toilet Tanks are being emptied so as not to risk an overflow?
SITE FOLDERS 1 TO 8
FOLDER 1
-
Project Start-Up - 1, 2, 3
-
SQE Management - 4, 5, 6
-
WHS Management - 7 - 12
-
Quality Management - 13, 14
-
Environmental Management - 15 to 17
FOLDER 2
-
Work Method Statements - 1 to 4
FOLDER 3
-
Site Specific Inductions - 1 to 4
FOLDER 4
-
Meeting Minutes - 1 to 4
-
Incident Management - 5 to 8
FOLDER 5
-
SQE Inspections - 1 to 4
-
Work PERMITS - 5 to 12
FOLDER 6
-
Plant & Equipment and Electrical Registers - 1, 2
-
Plant & Equipment Records - 3 to 16
FOLDER 7
-
Document Control 1 to 4
FOLDER 8
-
Hazardous Substances - 1 to 3
SIGN OFF - WILEY PERSONNEL
-
Summary Comments from person conducting the Audit
-
Name, Role and Signature of Wiley person conducting the Audit
-
Date and Time Audit completed
SIGN OFF - Persons consulted during the Audit
-
Name, Occupation and PCBU Name of person consulted during the Audit
SIGN OFF - Project Manager and Site Manager/Safety Advisor
-
Name, Position and Signatures of PM
-
Comments
-
Name Position and Signature of SM/SA
-
Comments
CLOSE OUT REQUIREMENTS - HIGH PRIORITY (<24HRS)
-
Close Out Requirements
CLOSE OUT REQUIREMENTS - ROUTINE PRIORITY (<7 DAYS)
-
Close Out Requirements
CLOSE OUT REQUIREMENTS - LOW PRIORITY (< 1 MONTH)
-
Close Out Requirements