Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

1.0 DOCUMENTS

  • 1.1 Is the safety management plan for this project or Project WHS Management Plan available on site.<br>Regulation 309

  • Comment and actons:

  • 1.2 Are there Safe Work Method Statements on site for all high risk construction work?<br>Regulations 291,299

  • Comment and actions:

  • 1.3 have The management plan & safe work method statements been reviewed/signed off.<br>Regulations 302 & 311

  • Comment & Actions:

  • 1.4 Is an emergency/serious accident procedure displayed on site? Do site workers understand the procedure?<br>Regulation 43

  • Comments & Actions:

  • 1.5 Is there a accident/injury register on site

  • Comments & actions:

  • 1.6 If an accident/incident has occurred was the Departmental representative informed and has an incident report been completed?<br>Procedure after an incident OPP-2101

  • Comments & actions:

  • 1.7 Is the Construction Environmental Management Plan on site?

  • Comments & actions

  • 1.8 Are there certificates of currency on site for Workers Compensation Insurance (or Personal Accident Insurance)?

  • Comments & actions:

2.0 INDUCTION AND TRAINING; HOUSEKEEPING; ACCESS AND EGRESS

  • 2.1 Are there records of site inductions and training on site?<br>Regulation 316,317

  • Comments & action:

  • 2.2 Have prohibited employment declarations been completed and included on induction register for all schools, TAFEs or other sites where children or vulnerable people are present?

  • Comments & actions:

  • 2.3 Are there any persons on site that have not had an induction<br>Regulation 316

  • Comments & actions:

  • 2.4 Is the site tidy with storage areas for materials and accessible and well maintained waste bins?

  • Comments & actions:

  • 2.5 Is there access and egress, including emergency exits and clear passage to emergency assembly area?

3.0 CONSULTATION

  • 3.1 What consultation process is in place with employees?<br>WHS Act Part 5: Act 47

4.0 IDENTIFYING SERVICES Reg 304 Work near underground assets guide 2007

  • 4.1 Has dial before you dig (1100) been contacted

  • Comment & actions

  • 4.2 Have asset owners "AS BUILT" drawings been consulted.

  • Comment & actions

  • 4.3 Has a services locator been engaged to locate services?

  • Comment & actions

  • 4.4 Are located services clearly identified on site?

  • Comment & actions

  • 4.5 Have located services been documented on drawings?

  • Comment & actions

  • 4.6 Have identified services been isolated?

  • Comment & actions

  • 4.7 Is potholing/hand digging used to locate services?

  • Comment & actions

  • 4.8 Is a safety observer/spotter used when excavating around underground services?

  • Comment & actions

5. WORK NEAR OVERHEAD POWER LINES WHS Reg Part 4.7. work near overhead power lines Code of Practice

  • 5.1 Has network operator been consulted regarding work

  • 5.2 Has the supply been de-energised

  • Comments & actions

  • 5.3 Has the location and voltage of the overhead power lines been determines

  • Are persons aware of approach distances (ordinary person)

  • Are persons aware of approach distances-Accredited Person

  • 5.4 Are spotters being used when plant is operating near overhead power lines

  • Comments & actions

  • 5.6 Is warning signage for overhead power lines located In The cab of the item of plant being used

  • Comments & actions

6. WORK NEAR PUBLIC PLACES

  • 6.1 Is the site securely fenced<br>Regs 298

  • Comments & actions

  • 6.2 Is the name & contact telephone numbers including an after hours emergency number of the principal contractor displayed!<br>Regs 308

  • Comments & actions

  • Add media

  • 6.3 Is appropriate construction and PPE signage displayed?<br>AS1319-Safety signs for occupied environments

  • Comments & actions

  • Add media

7. AMENITIES

  • 7.1 1 toilet per 20 workers?<br>Reg 40,41

  • Comments & actions

  • 7.2 Are there washing facilites?

  • Comments & actions

  • 7.3 Adequate fresh, cool drinking water?

  • Comments & actions

  • 7.4 Are clean lunch and change rooms provided?

  • Comments & actions

  • 7.5 Are rubbish bins provided?<br>Codes of practice-amenities for construction work & work place amenities

  • Comments & actions

  • Add media

8. FIRST AID

  • 8.1 Is there a register of injuries and first aid treatment?<br>First aid in the workplace guide

  • Comments & actions

  • 8.2 Is a fully stocked first aid box on site?<br>Regs 42; first aid in the workplace guide 2001

  • Comments & actions

  • 8.3 Is there a qualified first aid person on site<br>Regs 42

  • Comments & actions

9. ELECTRICAL WHS regs Part 4.7

  • 9.1 Are all power supply outlets protected by earth leakage/RCD devices?<br>AS/NZ3012:2010, reg 164,165

  • Comments & actions

  • Add media

  • 9.2 Is there a lockable or non conductive material cover over circuit breakers & RCDs associated with outgoing circuits but which does not prevent access to isolating switches?

  • Comments & actions

  • Add media

  • 9.3 Do the machines/tools on site have guards fitted?

  • Comments & actions

  • Add media

  • 9.4 Are the leads and plugs in good condition?

  • Comments & actions

  • Add media

  • 9.5 Are double adapters being used?

  • Comments & actions

  • Add media

  • 9.6 Are the extension leads elevated and not extended more than 5m without support?

  • Comments & actions

  • Add media

  • 9.7 Are plugs in wet areas?

  • Comments & actions

  • Add media

  • 9.8 Are extension leads no more than 30m in length?

  • Comments & actions

  • 9.10 Is there any electrical equipment overdue foe inspection!.

  • Comments & actions

  • 9.11 Is there a record of inspections?<br>Regs 150, AS/NZ3012:2010

  • Comments & actions

10. WORKING AT HEIGHTS WHS Regs Part 4.4

  • 10.1 Is safety mesh being used & certificate provided?

  • Comments & actions

  • Add media

  • 10.2 Are gloves being worn?

  • Comments & actions

  • 10.3 Is there safe access to roof area?

  • Comments & actions

  • 10.4 Prevention of falls if work area is above 2m and within 2m of the edge are guard rails or scaffolding or harness being used?<br>Regs 299,303 (SWMS required) CoP Managing the risk of falls I. Workplaces

  • Comments & actions

  • Add media

  • 10.5 Are tools secured by lanyards?

  • Comments & actions

  • 10.6 Are floor and roof penetrations covered?

  • Comments & actions

  • Add media

  • 10.7 Are the ladders extended at least 1m above the top of the work platform?<br>CoP Managing the risk of falls at workplaces

  • Comments & actions

  • Add media

  • 10.8 Are the ladders at least 4.6m fro. Live conductors?

  • Comments & actions

  • 10.9 Are only timber or fibreglass ladders used for work near electrical equipment?

  • Comments & actions

  • Add media

  • 10.10 Are ladders in good order - No damaged stiles or rungs, rubber buffers on feet?

  • Comments & actions

11 SCAFFOLDING -STATIC

  • 11.1 Are the scaffolds secured against tipping (bracing in all directions tied to bulking every 3.6m)<br>coP Managing risk of falls at workplaces Reg 225

  • Comments & actions

  • Add media

  • 11.2 Are handrails, mid rails and toe boards in place along the fill length of the scaffold (platforms over 2.0m in height)

  • Comments & actions

  • Add media

  • 11.3 Are the planks secure - platforms fully decked?

  • Comments & actions

  • Add media

  • 11.4 Is proper ladder access provided to the scaffold working decks? (Fixed top & 1:4 slope)AS4576: clause 89

  • Comments & actions

  • Add media

  • 11.5 Has the risk of falling objects on the external face of the scaffold been prevented?

  • Comment & actions

  • 11.6 Has the risk of falling objects on the internal face of the scaffold been prevented?

  • Comment & actions

  • 11.7 If the scaffold is under erection, has a safety barrier been set up near the scaffolding base, is signage used?<br>AS 4576

  • Comments & actions

  • Add media

  • 11.8 Are there so,I'd foundations under scaffolding?

  • Comment & actions

  • 11.9 Are there base plates and sole plates for the standards?

  • Comments & actions

  • Add media

  • 11.10 Has a sign off for licensed scaffolder been received for scaffolding of 4m or more in height confirming compliance with AS1576?<br>Reg 225, AS4576 Scaffolding

  • Comments & actions

  • Add media

12. MOBILE SCAFFOLDS

  • 12.1 Do mobile scaffolds have lockable wheels

  • Comments & actions

  • Add media

  • 12.2 Are the wheels locked

  • Comments & actions

  • 12.3 Is safe internal ladder access available?

  • Comments & actions

  • Add media

  • 12.4 Are handrails, mid rails and toe boards in place along the full length of the scaffold? (Platforms over 2.0m in height)

  • Comments & actions

  • Add media

  • 12.5 Is the height less than 3 times the width of the base?

  • Comments & actions

  • 12.6 Do outriggers have to be used?

  • Comments & actions

  • 12.7 Have overhead electrical hazards been considered?<br>AS 4576 clause 5.4

  • Comments & actions

13 FORMWORK

  • 13.1 Are exposed ends of concrete reinforcing protected? <br>Code of Practice - Formwork

  • Comments & actions

  • Add media

  • 13.2 Are floor and roof penetrations covered?<br>Code of Practice -formwork

  • Comments & actions

  • Add media

  • 13.3 Has the formwork been inspected by an independent qualified engineer?<br>Formwork CoP - prelims clause independent certification of formwork

  • Comments & actions

  • Add media

  • 13.4 Is there edge protection eg handrails on decks above 2m?<br>Reg 78,79

  • Comments & actions

  • 13.5 Are all temporary work platforms at least 450mm (2 planks) wide?

  • Comments & actions

  • Add media

  • 13.6 Are timbers de-nailed as it is removed?

  • Comments & actions

  • 13.7 Are barriers/signs erected to warn others that formwork erection/stripping are taking place

  • Comments & actions

  • Add media

14 PLANT AND EQUIPMENT WHS regs chapter 5

  • 14.1 Is there a register of plant and equipment on site?

  • Comments & actions

  • 14.2 Do plant operators have appropriate licenses, are copies retained on Site?<br>Part 4.5 high risk works division 1 license<br>Nosing of high risk work, Regs 3&4 fact sheet load shifting machines.

  • Comments & actions

  • 14.3 All machinery has registration/permits?<br>Regs 227

  • Comments & actions

  • 14.4 Are the safety check log books for machinery completed and signed?

  • Comments & actions

  • 14.5 Do backhoes/excavators have "beware of electrical hazards" signs?

  • Comments & actions

  • Add media

  • 14.6 Is the work close to power lines & are workers aware of regulations?<br>AS 2550.1 cranes safe use general requirements

  • Comments & actions

  • 14.7 Is plant in good order? (Visual inspection - no oil leaks - hydraulic hoses OK)

  • Comments & actions

  • 14.8 Is the safe working load (SWL) indicated on the boom of all cranes?<br>Regs 219

  • Comments & actions

  • Add media

  • 14.9 Do vehicles/earth moving plant have reverse alarms and rotating orange lights where necessary?<br>Regs 215, CoP moving plant on construction sites

  • Comments & actions

  • 14.10 Are site workers wearing high visibility vests?

  • Comments & actions

  • Add media

  • 14.11 re operators of elevated work platforms (EWP) that exceed 11m ticketed. Part 4.5 high risk works division 1 licensing of high risk work, regs schedule 3&4, fact sheer load shifting machines.

  • Comments & actions

  • 14.12 Has training been provided to operators of all EWP?

  • Comments & actions

15 CONFINED SPACES WHS regs part 4.3 SWMS required

  • 15.1 Any work in confined space? <br>Reg part 4.3 confined spaces

  • Comments & actions

  • 15.2 Are crews trained and equipped for confined space work?

  • Comments & actions

  • 15.3 Is there a confined space permit signed off for the work?

  • Comments & actions

  • 15.4 Are rescue, first aid and emergency arrangements in place eg tripod over hole, harnesses are being worn?

  • Comments & actions

  • Add media

  • 15.5 No equipment capable of generating noxious gas in the work area (generators, etc)?

  • Comments & actions

  • 15.6 Is there suitable ventilation of the confined space?

  • Comments & actions

  • 15.7 Are barricades and signs erected?

  • Comments & actions

  • Add media

  • 15.8 Are confined spaces secured after work is completed?

  • Comments & actions

16 WORK NEAR or OVER WATER SWMS required

  • 16.1 Are there safe work plat forms over water?

  • Comments & actions

  • Add media

  • 16.2 Is there adequate safety line/fall arrest system in place?

  • Comments & actions

  • 16.3 Is there an adequate safety line eg life buoy, life lines, safety boats?

  • Comments & actions

17 DEMOLITION

  • 17.1 Have gas, electricity and other services been located disconnected and verified by sign offs by competent persons?

  • 17.2 Is a licensed demolition contractor being used?

  • Comments & actions

18 EXCAVATION

  • 18.1 Are barricades/fences/signage along/around trenches and work areas<br>Regs Division 3 excavation work

  • Comments & actions

  • Add media

  • 18.2 Are excavations correctly shored, benched or battered? (More then 1.5m in depth) and access ladders provided?<br>Regs 306: excavation code of practice

  • Comments & actions

  • Add media

  • 18.3 Are materials placed or stacked within 1m of the edge of the excavation?<br>Excavation code of Preactice

  • Comments & actions

  • Add media

  • 18.4 Have existing services been verified (dial before you dig), have existing services been de-energised (electrical, gas, etc)?<br>Reg 304

  • Comments & actions

19 ASBESTOS REMOVAL

  • 19.1 Has asbestos been identified within the work site?

  • Comments & actions

  • 19.2 Is there and asbestos register on site?<br>Regs 425

  • Comments & actions

  • 19.3 Have warning signs or labels been affixed to areas asbestos is located on site?

  • Comments & actions

  • Add media

  • 19.4 Is a licensed asbestos removal isn't engaged to carry out the work?<br>Rags 458

  • Comments & actions

20 MANUAL/MATERIALS HANDLING

  • 20.1 Are areas where loading and unloading occurs secured to prevent unauthorised entry whilst task is auctioned?

  • Comments & actions

  • Add media

  • 20.1 Have all personnel been trained in safe manual handling processes?

  • Comments & actions

  • 20.3 Are all operators of plant engaged in loading/unloading licensed?

  • Comments & actions

21 PERSONAL PROTECTIVE EQUIPMENT

  • 21.1 Are site safety rules displayed around the site?

  • Comments & actions

  • Add media

  • 21.2 Are safety helmets being worn by all?<br>Regs chapter 3 part 3.1 & 3.2, including Reg 44, 45

  • Comments & actions

  • Add media

  • 21.3 Are safety boots being worn?<br>Regs clause 44,45

  • Comments & actions

  • Add media

  • 21.4 Are workers wearing hearing protection whilst doing/ or working near noisy work?<br>Regs 44,45, Regs part 4.1 noise

  • Comments & actions

  • Add media

  • 21.5 Are warning signs displayed?

  • Comments & actions

  • Add media

  • 21.6 When working in dusty conditions, are masks being worn and was the dust suppressed?

  • Comments & actions

  • Add media

  • 21.7 Are workers exposed to ultra violet rays adequately protected:

  • Comments & actions

22 HOT WORK

  • 22.1 Are suitable fire extinguishers on site?

  • Comments & actions

  • Add media

  • 22.2 Are barricades or screens and warning signs used in areas where work is being done?

  • Comments & actions

  • Add media

23 ENVIRONMENTAL MANAGEMENT

  • 23.1 Is this site in a sensitive area?<br>Eg heritage, heavily vegetated contaminated, creeks or water ways, if so seek advice from Environmental Representative.

  • Comments & actions

  • 23.2 Is there documentary evidence of compliance with any previously issued comments and actions?

  • Comments & actions

  • 23.3 Are there any obvious sings of construction related disturbance out side the construction zone?

  • Comments & actions

  • Add media

  • 23.4 Is there a copy of signed off environmental management plan on site?

  • Comments & actions

  • 24.5 Have required erosion control measures been correctly installed nd are hey functional?<br><br>Check that there are/is:

  • Comments & actions

  • 23.6 Is there a spill kit readily accessible?

  • Comments & actions

  • 23.7 Is dust suppression equipment readily available eg water cart or hose?

  • Comments & actions

  • Add media

  • 23.8 Are there any obvious signs of dust deposition outside of construction areas?

  • Comments & actions

  • Add media

  • 23.9 Is spoil being prevented from being tracked onto public roads (eg rattle Gris, wash down area).

  • Comments & actions

  • 23.10 Do trucks removing spoil from site have their loads covered?

  • Comments & actions

  • Add media

  • 23.11 Archaeology/heritage - Are protection measures in place and functional? (If applicable)

  • Comments & actions

  • 23.12 Are any construction vehicles obstructing the passage of local traffic (including pedestrians)

  • Comments & actions

  • Add media

  • 23.13 Is the complaints register complete and have actions detailed been implemented?

  • Comments & actions

  • 23.14 Are all required vegetation protection measures in place and functional? (Eg parra web fencing, tree guards)

  • Comments & actions

  • Add media

  • 23.15 Any other issues if so seek advice from Environmental Representative?

  • Comments & actions

24 HAZARDOUS CHEMICALS/SUBSTANCES WHS regs chapter 7

  • 24.1 Documentation?

  • Comments & actions

  • 24.2 Labelling<br>Are containers of chemicals adequately labelled (including decanted ones)?<br>Regs 357,360

  • Comments & actions

  • 24.3 Training<br>Have site workers been trained in how to use the chemicals/spill kits safely?<br>Regs 357,360

  • Comments & actions

  • Comments & actions

  • 24.4 Srorage<br>Are chemicals segregated and stored appropriately?

  • Comments & actions

  • Add media

  • 24.5 Ventilation - Is adequate ventilation provided when chemicals are stored or in use?

  • Comments & actions

25 WORKCOVER, DEC (EPA) or Local Authority Visits

  • 25.1 Have any WorkCover, DEC (EPA) or local Authority representatives attended the site since the last meeting?<br>If yes when did they attend?

  • Comments & actions

  • 25.2 were there any Prohibition and Improvement Notices (PINs) issued?

  • Comments & actions

  • 25.3 were there any on the spot fines issued to the contractor and/or sub-contractor and/or employee?

  • Comments & actions

26 QUALITY MANAGEMENT

  • 26.1 Is there a copy of the signed off Project Quality Management Plan on site?

  • Comments & actions

  • 26.2 Is there a corrective action request (CAR) register in use on site?

  • Comments & actions

  • 26.3 Is there any evidence of a representative of the Principal of the Contract signing off a witness on the contractors ITPs?

  • Comments & actions

  • 26.4 Are there any hold points on the contractor's ITPs that have not been endorsed by the Principal or the Principals Authorised Representative?

  • Comments & actions

  • 26.5 Are sub contractors using the latest drawings according to the Drawing Register?

  • Comments & actions

27 OVERALL COMMENTS

  • 27.1 What is the best area of safety management and what needs most improvement?

  • Comments & actions

  • 27.2 General comments about this site (including follow up action recommended)?

  • Comments & actions

SIGN OFF

  • Principals Authorised Person

  • Select date

  • Contractor site manager

  • Select date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.