Information
-
Document No.
-
POKAYOKE CHECK SHEET
-
TOYOTA MOTOR MANUFACTURING MISSISSIPPI
-
Conducted on
-
Prepared by
-
Personnel
-
GROUP:
-
QCPS#:
-
PROCESS:
-
CHECKED BY:
-
Select date
-
PSET
-
START
-
1st TARGET
-
LOW
-
TARGET
-
HIGH
TOOL CAPABILITY
-
PSI (at regulator) -
-
COMMENT:
-
RANK A / ¥ Cpk => 2.0 or 1.3 (Rank B Cpk => 1.0)
-
COMMENT:
-
Tool in use matches QCPS
-
COMMENT:
-
Tool shuts off when torque is achieved ( hold trigger until green)
-
COMMENT:
-
Back up tool matches QCPS
-
COMMENT:
-
Controller dynamic value => target or cut
-
COMMENT:
-
Reverse disabled
-
COMMENT:
-
Target tool settings match Dynamic Torque
-
COMMENT:
-
MIN =. +1 = Target or Cut : MAX :
-
COMMENT:
-
Parameter Set Up Sheet & Tool Change Record (b)
-
COMMENT:
-
Angle MAX : $ MIN : Settings
-
COMMENT:
AVI / PNC
-
PI box labeled with correct node address & tool ID
-
COMMENT:
-
POKAYOKE operates correctly under normal conditions ( Stack light turns green with correct # of individual OK)
-
COMMENT:
-
PSET running matches POKAYOKE program for katashiki
-
COMMENT:
-
Resets after crossing L-10 or when next part is present (Green stack light goes off, Orange turns on)
-
COMMENT:
-
ANDON comes on correctly (approx. 70% yellow & red at line stop)
-
COMMENT:
ANDON/FAULTS (N=2) - (Use Back page for multiple programs)
-
Low torque - turns red beacon & stops line at end of pitch.
-
COMMENT
-
Low torque-turns on red beacon & stops line at end of pitch.
-
COMMENT:
-
Incorrect number turns on red light at judge point & stops line.
-
COMMENT:
-
Incorrect number turns on red light at judge point & stops line.
-
COMMENT:
-
Correct number of QLLS clicks release line.
-
COMMENT:
-
Correct number of QLLS clicks releases line.
-
COMMENT:
-
Tool does not pass on a REHIT.
-
COMMENT:
-
Tool does not pass on a REHIT.
-
COMMENT:
PROCESS SETUP
-
QLLS Registers in QIS as NGO - all items backup comp
-
COMMENT:
-
QLLS registers as a defect in CIS (list defect name)
-
COMMENT:
-
Next process cannot be started until next car crosses L-10 or next part is placed on/in sub assembly process.
-
COMMENT:
-
Tool / QLLS /QLLS cannot go outside L-10
-
COMMENT:
-
No part / wrong part selection ( interlock confirmation)
-
COMMENT:
BYPASS KEY SWITCH
-
Bypass key not present in switch ( only in possession of GL
-
COMMENT:
-
Red beacon comes on and registers in CIS as POKAYOKE Bypass when INTERLOCK OFF (back key)
-
COMMENT:
-
When forced complete?
-
COMMENT:
GREEN BEACON
-
Light goes solid green when process judgement is OK
-
COMMENT:
TRUTH TABLE CONFIRMED
-
All models programmed
-
COMMENT:
-
Model Year Updated
-
COMMENT:
DOCUMENTATION CONFIRMATION
-
DELTA C CONTROL CHART & notebook, MIS & QCPS revised (a)
-
COMMENT:
-
QLLS/QL setting confirmed (daily click wrench check sheet) (c)
-
COMMENT:
-
Abnormality check (pokayoke abnormality check repair log ) (d)
-
COMMENT:
SIGNATURES
-
Responsible Engineer
-
TEMA Representative
-
Production Representative
-
Responsible Engineer