Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Job Specific HSSE Audit
-
1. The SPI JHA / Task Planner / EAP was completed for the job audited (Job being performed). . .
-
2. All elements of the JHA were completed per policy and job assignment - No blank areas noted. .
-
3. All crew members assigned to specific task were signed onto the JHA. . .
-
4. All contact information was completed including emergency contact information. . .
-
5. Was evacuation location communicated to employee?
-
6. Crew members audited understood job assignment, site requirements, and job hazards. . .
-
7. Safety requirements of the JHA were being met - Including barricade tape, overhead work posted, material handling requirements, and hazards were communicated to other crafts
-
8. Job walk (Review) confirmed all hazards were addressed on the JHA
-
9. PPE requirements were outlined, understood, and were being met
-
10. Was lockout / tag out required for job assignment?
-
11. Did all crew members lock on, sign on, as part of the lockout / tag out requirement? . .
-
12. Was CSE required for job assignment?
-
13. Were hazards communicated to crew members?
-
14. We're all elements of CSE in place and being followed? (Permit, testers, entry log). . .
-
15. Was scaffold being built per Solid Platforms structural requirements/OSHA standards? . .
-
16. Are plank sills laid beneath racks on grading / cat walks to distribute weight / avoid point-loading? . .
-
17. Is staging platform outfitted with toe-board, and orange mess for falling object protection, or fully decked and pans set on edge against vertical uprights and wired to prevent materials from falling?
-
18. Are elevated staged materials organized and separated so erectors can pull components from staged piles without upsetting other piled materials?
-
19. Walkways & work platforms provided with a clear path "to do the work" so erectors don't have to climb over materials.
-
20. Are unused staged elevated materials stacked neatly and secure at the end of shift as to not be toppled after hours from inclement weather or other similar events?
-
21. All crew members tools tethered per SPI policy?
-
22. All company vehicles being used on site have daily vehicle inspections completed?
-
23. Are all Employees and safety lock labels legible?
Job Audited
Corrective Actions
-
Enter corrective actions taken or to be taken by item number (i.e. 1, 2, 3....)
Crew Audited
-
Include names of all crew members
Foreman Signature
-
Foreman Name
General Foreman Signature
-
General Foreman Name
Auditor Signature
-
Auditor Name