Information
-
Site
-
Add media
-
Alpha Code
-
Select date
-
Location
-
For this assessment the following applies
Safe -
At Risk -
Fail -
Section 1.0 - Site planning and mangement
Site Management and Planning
-
Scope of Works
-
Add media
-
Expected duration of works (days)
-
Is the site access information correct and up to date?
-
Is the Health and Safety plan on site, accessible and legible?
-
Outline areas to improve the Health and Safety plan with dates for completion
-
Select date
-
Stop work until this has been undertaken.
-
Has a hazard and risk assessment been undertaken for the site?
-
Outline areas to improve the Health and Safety plan with dates for completion
-
Select date
-
Ensure that a hazard and risk assessment is completed for the site before any further work is undertaken on site.
-
Have Safe Work Method Statements or JSA's been prepared for high risk activities on site and are being followed?
-
- Falls
- Asbestos
- Confined Space
- Live Electrical Work
- Remote and Isolated Work
- Falling objects
-
Select date
-
Ensure that a SWMS or JSA are completed for high risk activities before work continues
-
Outline areas to improve the Health and Safety plan with dates for completion
-
Select date
-
All contractors (including sub contractors) have been provided with information relating to health and safety for the work they are undertaking?
-
Is the time allowed suitable for the scope of work to be undertaken?
Summary
-
Site Management and Planning
Safety Gear
-
Hi Viz
-
Safety Helmet
-
Safety glasses
-
Appropriate clothing for the environmental conditions
-
Safety boots (or appropriate footwear for working on roofs)
-
Hearing protectors of the appropriate class
-
Sunscreen
-
Gloves
Summary
-
Safety Gear appropriate to the task is in being worn and is in good condition?
Competency
-
Principal Contractor Network Requirements
-
2 Degrees
-
Vodafone Sites
-
Telecom Sites - PTN Training
-
Workers on roofs with proprietary anchor systems in place have completed US23229 and have a copy of their current certification on site?
-
Workers on communication towers, poles and roofs have completed US 23229, 15757 and 17025 and have a copy of their current certificate on site?
-
Are all persons on site competent and trained to undertake the tasks on site?
-
Work should cease until persons competent to undertake the required tasks are on site. An incident report should also be sent to the relevant Principal Contractor
Summary
-
Competency
Emergency planning and equipment
-
Is the site able to call for emergency assistance - Fire, Police Ambulance?
-
Are appropriate Fire Extinguishers on site?
-
Add media
-
Emergency assembly point identified?
-
Add media
-
Are first aid kits, current, we'll stocked and readily available?
-
Add media
Summary
-
Emergency planning
Environmental
-
Working hours restrictions are being adhered to?
-
Noise and vibration are kept to acceptable levels?
-
Are hazardous substances clearly labelled and stored appropriately?
-
There is a spill kit on site appropriate for the type and amount of substances on site?
-
All site areas are kept tidy with litter removed from site appropriately?
Summary
-
Environmental
General
-
Have all visitors signed the visitor log?
-
Add media
-
Are hazards, risks and controls discussed with visitors prior to entering the site?
-
Incident report register on site and up to date?
-
Add media
-
Is the work site (including footpaths and roadways) clear and free from debris, rubbish and obstructions?
-
Add media
-
Are slip and trip hazards being adequately managed?
-
Add media
-
Is lighting adequate for carrying out tasks and and/or safe access?
Summary:
-
General
Section 2.0 Access to Roofs, Brittle Roofs and RF
Roof Access
-
Are persons on site working on the roof of a building?
-
An assessment has been made of any internal ladders used to gain access to the roof to ensure they are structurally sound?
-
Handrails are in place for ladders if required?
-
Evidence
-
Ladders extends 1 metre above the landing platform?
-
Portable ladders meet AS/NZS 1892?
-
Portable ladders are secured at the top and the bottom?
-
If access to the roof is via an internal crawl space this should be considered a restricted space and a safe work method planned. (This must include a standby person who does not enter the restricted space).
-
If work is being undertaken in a restricted space has a safe work method statement been established and implemented?
-
Work should cease until a safe work procedures are in place
Summary
-
Access to Roof
-
Add media
Brittle Roofs (Skylights, Asbestos Roofs, Openings, Roofs in Poor Condition)
-
Is the roof surface brittle, in poor condition or has skylights?
-
An assessment of the roof has been made to ensure it is strong enough to support the work activities being carried out. (Asbestos roofs are the majority of brittle roofs).
-
Has the roof been inspected internally (if possible) to ensure it is sound?
-
Has an competent person undertaken this assessment?
-
Are areas such as skylights, roof openings designated as no go zones and barricaded off or covered if required?
-
Are walkways with guardrails provided when work on fragile roofs cannot be avoided?
-
If walkways are not provided is a fall arrest system being used?
-
Work on the roof must stop until safe work methods are in place.
Summary
-
Brittle Roofs
RF
-
Are there RF hazards on site?
-
RF warning signs are in place at access points?
-
Ensure that a report is made to the Mobile Company concerned that signs are not present.
-
Evidence
-
Are persons trained/competent/certified in RF Awareness
-
On co location sites, other mobile company antennae have been considered when planning the work?
-
Have adjacent buildings be assessed as a possible source of RF?
-
Are RF monitors calibrated?
-
Are appropriate RF monitors available and being used?
-
RF procedures and monitoring practices have been followed?
-
Telecom RF Shutdown Procedure ND4027 Ver 6.0 has been followed?
-
2 Degrees
-
Vodafone
Summary
-
RF
Section 3.0 - Equipment used for Working at Heights on Towers, Poles and Roofs
Machinery for working at Heights on Towers, Roofs and Structures
-
MEWP, Crane Scaffold or Guardrails being used on Site?
-
Move to the next section
-
Are workers on the ground wearing appropriate PPE e.g. Safety Helmets, Safety Boots, High Viz Vests and Eye Protection?
-
Add media
-
Have exclusion zones been implemented and sufficient for the tasks being carried out?
-
Add media
-
Do the exclusion zones prevent members of the public accessing the site?
-
Add media
-
Assess any of the following equipment on site
-
Mobile Elevated Work Platfrom
-
Has the operator carried out a carried out a pre start inspection of the MEWP that includes functional and visual tests (required each day)?
-
Is the MEWP clearly marked with the rated lifting capacity
-
Weight of lift?
-
Essential operating and maintenance instructions permanently displayed or stored in a conspicuous place on the MEWP?
-
Is the six monthly inspection certificate displayed?
-
Operator is trained and competent (US 23966 v1) and the corresponding unit for the type of MEWP being used?
-
Hazards associated with power lines are appropriately controlled (no closer than 6.4 metres, or between 4 - 6.4 metres with appropriate controls in place. No work can be carried out within 4 metres of a power line without the written consent of line owner and this consent must remain on site at all times?
-
Weather conditions are suitable for using the MEWP?
-
Are harnesses, lanyard and attachment points available to all workers undertaking tasks from the MEWP?
-
Is the MEWP set up on firm and level ground?
Summary
-
MEWP
-
Crane
-
Is the plan and information provided by the crane supplier signed and accepted by the contractor on site?
-
Is the crane set up on firm, level ground with barriers in place?
-
Safe working distances are maintained from overhead power lines?
-
No persons are standing under suspended loads?
-
Tag lines are used where there could be load spin?
-
The load does not exceed the lifting capacity of the crane
-
Lifting capacity of the crane
-
Weight of lift
-
Clear lines of communication exist between the dogman/persons in bucket and the crane operator?
-
Weather conditions suitable for the use of a crane?
Summary
-
Crane
-
Scaffold or Mobile Scaffold
-
Are the surface conditions suitable for scaffold access and stability - e.g level and safe to work on?
-
Is there a health and safety management plan on site that clearly identifies those responsible for implementing control measures for the scaffold?
-
Are site specific hazards e.g proximity to power lines and control measures included in the Safe Work Method Statement or JSA?
-
The scaffold was erected, altered or dismantled by a person(s) who have been trained and have suitable experience with the type of scaffold being used?
-
Are the wheels locked and turned out on mobile scaffolds?
-
If a portion of the scaffold is above 5 metres above the ground the following conditions must be met
-
The person assembling, altering or dismantling the scaffold have a certificate of competence
-
Scaffold inspection card/register (Safety Tag) clearly visible in place by the access ladder and checked weekly?
-
Notification has been sent to WorkSafe NZ
-
The maximum load (weight of workers and materials) has been determined and the scaffold is capable of supporting the weight
-
Edge protection provided where a person could fall 2 or more metres
-
Scaffold protected from passing vehicles or plant
-
Ladders are secured top and bottom.
-
Ladder extended 900-1000 mm above the landing platform.
-
Planks are in good condition, 3 planks minimum and butted and secured.
Summary
-
Scaffolds
-
Edge Protection?
-
Designed and constructed to by a competent person?
-
Positioned appropriately?
-
Will barriers and guard rails be regularly inspected
-
Includes a toe board or mesh infill to prevent tools, materials and debris falling from the roof?
-
Not used on a roof with greater than 35 degree slope (In this instance a MEWP, or Fall Restraint/Arrest system must be used)
Summary
-
Edge protection
-
Photo showing MEWP or CRANE
Section 4.0 - Fall Restraint and Fall Arrest
Fall restraint and fall arrest systems
-
Are fall restraint or fall arrest systems being used on site?
-
Move to the next section
-
All personnel trained and certified for working at height?
-
Has the rigger undertaken a visual inspection of the structure, pole etc prior to work commencing?
-
Is each person familiar with the work plan?
-
Are personnel attached at all times while working at height?
-
Has a drop zone been implemented and sufficient for the tasks being carried out?
-
Is all equipment secure to prevent a fall from height?
-
Does each member of the team have the required PPE?
-
Add media
-
Riggers gloves
-
A rescue, climbing or caving safety helmet
-
Self rescue kit carried
-
Clothing to suit the environmental conditions
-
Eye protection from glare and also flying objects/particles.
-
First aid kit?
-
Boots that are appropriate to the task ( AS 2210)
-
Is there a written rescue plan that is known to each member of the team?
-
Add media
-
Two certified rescue climbers are on site at all times?
-
Notification has been sent to WorkSafe NZ of the work?
-
Are all members of the team trained and competent for the tasks they are carrying out?
-
Has a SWMS or JSA been prepared for height work on site?
-
Are there established safe access pathways to the anchor points?
-
Is a certified fall restraint system available for use?
-
Add media
-
If using a fall arrest system are suitable certified anchor points being used?
-
Date anchor points certified to?
-
Certified load?
-
Add media
-
If certified anchor points are not available a Temporary Anchor Point Permit must be completed and a copy held on site
-
The temporary anchor point permit has been signed by a competent rigger?
-
Rope access work must cease until the permit is completed
-
The temporary anchor point permit has been signed by the rescue climber?
-
Rope access work must cease until the permit is completed
Summary
-
Fall restraint and fall arrest
Section 5.0 - Other Safety Critical Risks
Pedestrian and Public Safety
-
Are members of the public/pedestrians passing the site?
-
Is a spotter required on site?
-
Is safe pedestrian access maintained on site at all times?
-
Are appropriate barriers in place that create a safe zone around activities that involve working at height?
-
When plant and machinery are in operation (e.g. MEWP, Crane, Container Delivery) these are isolated from the general public?
-
Work vehicles are parked safely?
Summary
-
Pedestrian and public safety
Electrical Safety
-
Is electrical work being undertaken on site?
-
Procedures are in place for ensuring electrical equipment is de-energised before electrical work is carried out and methods in place to ensure that it cannot <br>be inadvertently re-energised (isolation, tagging and lockout)?
-
Persons conducting work on electrical equipment are appropriately trained, registered and hold a practising license for the type of work being undertaken?
-
Proven to be de-energised before work commences?
-
Only ladders constructed of timber or fibreglass are to be used for work on or near electrical apparatus?
-
All electrical equipment, extension leads and portable power tools are in good condition and regularly inspected, tested and tagged?
-
Undertaken a CPR course (within the last 12 months) and Basic First Aid course (within the last 2 years)?
Live electrical work
-
Is live electrical work being undertaken on site?
-
A risk assessment and safe work method statement has been prepared before any live work is undertaken?
-
When working on or near live electrical apparatus the following Safety Gear (PPE) is being worn
-
Clothing covers the body from neck to wrist to ankle, (cotton)
-
Sleeves rolled down and shirts tucked into trousers (protecting against entanglement and arc flash)
-
Non metallic fasteners (or fasteners are protected by a layer of the same material as that of the garment)?
-
Suitable eye protection?
Summary
-
Electrical
Traffic Management
-
Is the worksite in the road corridor or subject to frequent vehicle movements?
-
Copy of the traffic management plan signed by the contractor and maintained on site?
-
Traffic management setup is correct and according to the TMP?
-
STMS contact number listed?
-
Is there an escape route for the traffic controller?
-
Comes and barriers in good condition?
-
After hours TMP in place if necessary?
Summary
-
Traffic Management
Section 6.0 - Health and Safety Summary
Summary
-
If any of the following areas are not being managed appropriately then work at the site should be halted until the area(s) of concern are addressed.
-
Site planning and management
-
Roof access, brittle roofs and RF
-
Equipment and plant for working on towers, roofs and structures
-
Fall restraint, arrest and anchor points
-
Pedestrian, Public and Traffic Safety
-
Competency of workers on site?
-
Are any other hazards present on site, list below
-
Are these hazards and risks being appropriately controlled?
-
Were any unsafe work practices observed at the time of the assessment
-
Please describe the unsafe practice observed below
-
Comments -enter below
Agreement
-
Required corrective actions
-
Agreed date for completion of corrective actions
-
Assessor
-
Company
-
Site representative
-
Company
-
Select date