Title Page

  • Tilcon Connecticut Inc.- Plainville Facility

  • Spill Prevention Control and Countermeasure (SPCC) Plan

  • Stormwater Pollution Prevention Plan (SWP3)

  • Tilcon personnel should conduct a detailed inspection of the entire facility once per month. the monthly inspections log identifies the principal ares, systems, and equipment that should be evaluated, at a minimum to meet the SPCC/SWP3 inspection requirements. A check should be placed (either "OK" or "Corrective Action Needed") next to each item evaluated. Where corrective action(s) is/are required, facility personnel should complete a Corrective Action Form. The inspector should sign and date this log immediately upon completion of the inspection.

  • Employee Name:

1.0 Above-Ground Storage

  • (Above-Ground Storage Tank inspections for oil/petroleum products are performed on a monthly basis using the Steel Tank Institute (STI) forms that are included in Appendix M of the SPCC/SWP3 Plan. The consolidated findings should be identified here as acceptable "OK" or as not acceptable "Corrective Action Needed". If corrective action is required, a Multi-media Corrective Action Form should be completed.

2.0 Secondary Containment Structures

  • (Above-Ground Storage Tank inspections for oil/petroleum products are performed on a monthly basis using the Steel Tank Institute (STI) forms that are included in Appendix M of the SPCC/SWP3 Plan. The consolidated findings should be identified here as acceptable "OK" or as not acceptable "Corrective Action Needed". If corrective action is required, a Multi-media Corrective Action Form should be completed.

3.0 Miscellaneous

  • Housekeeping (trash,rags,etc.)

  • Miscellaneous chemical storage

  • Vegetation (fire hazard)

4.0 Security

  • Entrance/exit gates (operational, locks)

  • Lighting (operational)

5.0 Communication Equipment

  • Telephones

  • Handheld radios (operational, charged, location)

6.0 Spill Response Equipment

  • A. Sorbents (Pads, Spedi-Dry)

  • If corrected action is needed: select which categories apply:

  • B. hand Tools (Maintenance Garage)

  • If corrected action is needed: select which categories apply:

  • C. Communication Equipment

  • If corrected action is needed: select which categories apply:

  • D. Fire Fighting and Personal Protective Equipment

  • If corrected action is needed: select which categories apply:

7.0 Fire Protection Response Equipment

  • Water hydrants

  • Extinguishers

8.0 Product Transfer Piping

  • Signs of product leakage (droplets of product, discoloration, stains)

  • Condition (rust,corrosion)

  • Valves

9.0 Drainage System

  • Drainage Swale (to small on-site ponds)

  • On-Site Ponds

Above-Ground Storage Tank Inspection

T-24

1.0 Tank Containment

  • 1.1 Containment Structure

  • 1.2 Primary Tank

  • 1.3 Containment Drain Valves

  • 1.4 Pathways and Entry

2.0 Leak Detection

  • 2.1 Tank

  • 2.2 Secondary Containment

  • 2.3 Surrounding Soil

  • 2.4 Interstice

3.0 Tank Equipment

  • 3.1 Valves

  • 3.2 Spill Containment Boxes

  • 3.3 Liquid Level Equipment

  • 3.4 Overfill Equipment

4.0 Tank Attachments and Appurtenances

  • 4.1 Ladders and Platforms

5.0 Other Conditions

  • if there are other conditions that should be addressed for continues safe operation or that may affect the SPCC plan explain in comments section.

  • Comments:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.