Title Page

  • Person Carrying out Audit

  • Name of project being audited

  • Name of operatives being audited

  • Date

  • Location

Details of project & work tasks monitored

  • Type of works being carried out at time of audit

Documentation

  • Can operatives access all relevant H&S information via the FLOW system? (requires demonstration by each operative)

  • Are the correct risk assessments for the tasks present and the control measures in place?

  • Are the correct method statements present and being followed?

  • Is there a valid / up to date copy of the waste carriers license and Vehicle insurance certificate?

Housekeeping

  • Is the entrance / exit to the premises free from obstructions caused by the work in progress

  • Is the working area kept in a clean and safe manner?

  • Are barriers and signage being used where necessary?

  • Are materials stored in a safe location?

  • Are sheets in place to protect property / furniture where necessary?

Electrical

  • Have isolations and disconnections been complete correctly?

  • Does all portable electrical equipment have a valid PAT test label attached?

  • Has an RCD been used on all electrical equipment?

Tools and Equipment

  • Are all tools / equipment in good / safe working condition?

  • Are all tools / equipment being used safely?

  • Are tools stored safely when not in use?

  • Is all electrical equipment unplugged and stored safely when not in use?

PPE

  • Are minimum requirement (safety boots) being worn?

  • Is all other PPE that’s required for the task being used?

  • Are all other PPE items present in the operatives vehicle and within expiry date (e.g., hard hat)?

  • Is all PPE in good working condition

Environmental - Are control measures in place to:

  • Minimise Noise

  • Minimise Dust

  • Prevent Pollution

  • Adequately dispose of waste

Other

  • Is there a fire extinguisher present and has it been inspected within the past year?

  • Is there a first aid kit present, containing the minimum contents and in date?

  • Do operatives have means for cleaning eg, hand care (containing adequate contents) hand wipes etc?

  • where applicable has a hot works checklist been completed and are the necessary controls in place?

Gas

  • Has a tightness test / necessary isolations been carried out?

  • Is a fire extinguisher present at the hot works location?

  • Is a heat mat or fire resistant coverings (eg, sheets) present in the van?

  • When hot working have nearby combustible materials been either removed or adequately protected?

RPE Check

  • Make, Model and Size of Respirator

  • Is the respirator and its seals working and not damaged?

  • Is the filter working adequately?

  • Are the head straps and buckles working and not damaged?

  • Are the valves and seals working and not damaged?

  • Based on the above checks, is the mask safe for use?

CDM Documentation

  • Is the F10 valid

  • What is the F10 reference number and expiry date

  • Is the CPP vaild

  • What is the CPP expiry date

  • Is the overarching RAMS document valid & relevant

  • Are there any other issues with the CDM documentation

Remedial Action

  • Please give details of all remedial action taken including date completed and by whom. Please sign below on completion

  • Sign

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.