Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Site information
-
Survey date
-
Surveyor Name
-
Building
-
Floor
-
Comms Room Name
-
Any Special Access Requirements
-
ACM Status
-
Location pictures
-
Take photo of location
-
Approx Room Dimensions
Cabinets
-
How many Cabinets
-
Type / Size of Cabinets
-
Information
-
Take photo of each cabinet front & Rear if possible
-
Plinth/Stage required?
-
Size of Plinth /Stage
-
New cabinet specified?
-
Are above Suitable including Footprint
-
If Wall Mount, State Wall Structure/ Fixing required
-
Cabinet labelling Scheme
PDU's
-
How Many Existing PDU's
-
State Size & Type
-
Are they hard wired in?
-
New specified PDU's
-
Are the above suitable
Power
-
Type of existing power sockets
-
New specified power sockets
-
Quantity
Bonding
-
Are there enough existing earth bonds?
-
If No how many are required?
Containment
-
What containment is required for new position/ cabling
-
Vertical quantity and type
-
Horizontal quantity and type
Cabling
-
How many Cat5/5e cables enter room?
-
is above approximate ?
-
What is the Cat5/5e split?
-
is above approximate ?
-
Is Cat5/5e separate in looms?
-
Take photo of cable path into room
-
Are any cables flagged to be removed?
Fire stopping
-
Is Fire stopping required?
-
Take photo of incoming penetrations
-
State new Fire stopping requirements
Patch Panels
-
How many existing 24 way non krone cat5 PCB panels?
-
How many existing 24 way krone PCB panels?
-
How many existing 24 way non krone modular panels?
-
How many existing 24 way krone modular panels?
-
How many existing 48 way non krone cat5 PCB panels?
-
How many existing 48 way krone PCB panels?
-
How many existing 48 way non krone modular panels?
-
How many existing 48 way krone modular panels?
-
How many existing 24 way krone Panels are required?
-
How many existing 48 way krone Panels are required?
-
Existing labelling scheme
-
Are there any obvious specific non data ports?
-
CCTV qty?
-
Voice and qty
-
Access control and qty?
-
Will there be issues with above at cutover weekend?
-
Are highlands required?
-
If Yes how many circuits?
-
Take photo of proposed HiBand location
Switches
-
How many existing switches?
-
State type & Port quantity?
-
New switch quantity?
-
Take photo of switches
Patch Leads
-
New patch leads requirements
-
New patch leads requirements
-
New patch leads requirements
Fibre
-
Is Fibre present?
-
What type of fibre panels
-
What fibre type
-
Existing fibre labelling scheme?
-
Source location
-
Survey and specify source location
-
What fibre panels at source location?
-
What fibre type at source location
-
Are new fibre patch leads required if Yes what type ?
Copper backbone
-
Are copper backbones present?
-
What cable
-
What panels
-
Existing labelling scheme
-
Source location
-
Survey and specify source location
-
What cable
-
What panels
Materials
-
Are there any extra parts required in addition to those specified
20% for expansion?
-
Will the rework achieve this?
-
If No what changes will be required to scope?
Labour resource
-
How many days will the upgrade take?
-
If works to be split over multiple weekends state plan?
General site Conditions
-
Is parking available at the building location? State location
-
Any special unloading condition at location? Please specify
-
Has a temp storage location been identified?