Title Page
-
Conducted on
-
Job Number
-
Prepared by
-
Line
-
Supplied Drawings
Chassis, 1st fix plumbing and deck.
-
Center lugs equal over both halves.
-
Boarding as specification
-
Evidence
-
Pressure Test. Pre Decking
-
Evidence
-
Pressure Test. Deck Down.
-
Evidence
-
Radiator Pipework As Spec. Location And Size
-
Evidence
-
Pipework Defined Hot+Cold
-
Evidence
-
Open Ends Of Pipework Sealed
-
Evidence
-
Flow And Return Defined
-
Evidence
-
Condition of fixing points. Timber and Fixings.
-
Evidence
-
Coach Bolts Secure To Chassis
-
Evidence
Stage 2. Superstructure post roof
-
Velux fitted
-
Window Liners fitted
-
Evidence
-
Ceiling running level, in line.
-
Evidence
-
Fire Place fitted and boarded
-
Cuts And Halvings
-
Evidence
-
Condition Of Timber
-
Evidence
-
Openings. Dimensions And Square
-
Location as per drawings
-
Internal And External Walls Square, Level And Plumb
-
Location as per drawings
-
Wall Plate Condition
-
Evidence