Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Extraction Face Location: E2 Excavation. E3 Stripping
-
Has Extraction (E2) been undertaken since last inspection?
-
Has there been any deviation from the development scheme or excavation rules?
-
Any changes in general appearance or shape since the last inspection?
Crests (Top of Face)
-
Is there inadequate stand-off to the site boundary or haul road?
-
Is there any cracking along the top of the face?
-
If cracks are present is any water entering them?
-
Is there any lowering or settlement of the ground behind the crest of the face?
-
Is there any ponding of water behind the crest?
-
Has there been any placement of material behind the crest?
Face
-
Is the face being excavated steeper than the max specified in excavation rules?
-
Is there any evidence of bulging or cracking on the faces?
-
Has there been any slumping/collapse of the faces since the last inspection?
-
Has there been any erosion or is there any loose material on the face?
-
Is there any water issuing from the face?
-
Is there any uncontrolled discharge of water over the face causing scouring or erosion?
-
Have any unexpected geological conditions appeared in the face since the last inspection?
-
(Excavation below water) Is there any wave erosion or potential instability between the waterline and crest of the face?
Toe
-
Can any movement of the foundation adjacent to the toe of the face be seen?
-
Is there any unexpected standing water accumulating at the toe of the face?
-
Has there been any excavation at or near the toe of the face which is not in accordance with the design?
-
Has Stripping (E3) been undertaken since last inspection?
-
Has there been any deviation from the development scheme or excavation rules?
-
Any changes in general appearance or shape since the last inspection?
Crests (Top of Face)
-
Is there inadequate stand-off to the site boundary or haul road?
-
Is there any cracking along the top of the face?
-
If cracks are present is any water entering them?
-
Is there any lowering or settlement of the ground behind the crest of the face?
-
Is there any ponding of water behind the crest?
-
Has there been any placement of material behind the crest?
Face
-
Is the face being excavated steeper than the max specified in excavation rules?
-
Is there any evidence of bulging or cracking on the faces?
-
Has there been any slumping/collapse of the faces since the last inspection?
-
Has there been any erosion or is there any loose material on the face?
-
Is there any water issuing from the face?
-
Is there any uncontrolled discharge of water over the face causing scouring or erosion?
-
Have any unexpected geological conditions appeared in the face since the last inspection?
-
(Excavation below water) Is there any wave erosion or potential instability between the waterline and crest of the face?
Toe
-
Can any movement of the foundation adjacent to the toe of the face be seen?
-
Is there any unexpected standing water accumulating at the toe of the face?
-
Has there been any excavation at or near the toe of the face which is not in accordance with the design?
-
Has there been any deviation from the development scheme or excavation rules?
-
Any changes in general appearance or shape since the last inspection?
General
-
Did you note any other points of interest or concern (if yes please give details)?
-
Details of Interests or Concerns
-
Any defects requiring Geotechnical Department / Specialist Notification?
-
Details of recommended remedial works / actions
Completion
-
Sign off