Página de título
TITTLE
-
Site
-
Creation Date
-
Created by
-
Localization
-
Supplier name
Work Off Site
CONTROL OF WORK - WORK OFF SITE
-
[1] HSE - compliance: The documentation has been verified in the eCoordina
-
Please, to continue with this inspection, the documentation should be verified and validated on eCoordina, if the documentation is not verified or validated, the worker won't do the work
-
[2.1.1] RAMS - The Supplier has presented the QHSE Risk Assessment
-
Please, to continue with this inspection, the supplier should be presented the QHSE Risk Assessment
-
[2.1.2] RAMS - The list of materials to use is valid?
-
Please, to continue with this inspection, it is necessary to confirm that the list of Materials are validated
-
[2.2.2] RAMS - Supplier has submitted the Method Statement regarding impact the Critical Operation?
-
Don't continue with this inspection if it hasn't submitted the Method Statement regarding impact the Critical Operation
-
[2.2.2.1] Method Statement has been approved?
-
You can't continue with this inspection if the Method Statement hasn't been approved
-
Please, Upload the Method Statement approved
-
[2.2.3] RAMS - Check for conflict for other work occurring of the same time
-
[2.3] RAMS: How is the POC (Person of Contact)?
-
[3]. Site Access Authorization: Was it processed accross the Genetech
-
Please, to continue with this inspection, the Site access Authorization should be processed on Genetech, if the Site Access Authorization is not approved , the worker won't do the work
Work On Site
CONTROL OF WORK - WORK ON SITE
-
[4] Site Induction Training: The documents associate to the Site Induction Training is VALID
-
Please, before to continue with this inspection, it is necessary to renovate the Site Induction Training
-
[5] ATW - Authorisation to Work: The Control of Work has been managed through of the iAuditor inspection
-
[6] PTW - Permit to Work. The work to be done is one of the following: Confined Space, Hot-Works, Electrical Work, Working at heights and Log Out Tag Out
-
Please, you should request a "Permit to Work" through of the iAuditor inspection
-
[7] Last Minute Risk Assessment: The LMRA has been managed through of the iAuditor inspection
-
Now you can begin to start the work (Job plan, MOP)
Post Work
POST-WORK
-
[8.1] All tasks completed in accordance with the scope of service agreed & legal standars?
-
[8.1.1] Please inform contractor and take suitable measure.
-
[8.2.1] Has the work area been left safe, clean and tidy by the contractor's employees?
-
[8.2.1.1] Please inform contractor and take suitable mesures (For example. Get the contractor back to clean up the area before releasing invoice)
-
[8.2.2] Has all waste been suitably removed?
-
[8.3] Have all Waste Duty of Care documents, e.g. Waste Transfer Notes or Consignment Notes been completed?
-
[8.3.1] Please inform contractor and take suitable mesures (For example. Get the contractor to send the relevants documents before releasing invoice)
-
[8.4] Have all test and/or completion certificates been adequately completed and received?
-
[8.4.1] Please inform contractor and take sutiable measures (For example. Get the contractor to send the relevant documents before releasing invoice)
Closure
CLOSURE
-
[9.1] PTW
-
[9.2] ATW
-
[9.3] Access
-
[9.4] Communication with Client
-
[9.5] Sign by