Title Page
-
Audit Title
Job/Fuser Information
-
Ticket or Layout Number
-
Ticket Number
-
Layout Number
-
Ticket Number
-
Layout Number
-
Address on Ticket
-
Inspector
- Morrissey, Mike
- Stone, Ashton
- Titus, Mark
- Quinones, Anthony
- Di Leonardo, Lauraine
- O'Brien, Jimmy
- Franca, Louis
- McBrien, Frank
- Giraldi, Nat
- Dvorak, Charlie
-
Company on Site
- Con Edison
- Bond Brothers
- CAC
- Creamer
- Danella
- ECI
- ECU
- Ferreira Construction
- Hallen
- Hawkeye
- Manetta
- MECC
- MFM
- Network
- PCT
- Persico Construction
- Petmar
- Posillico
- Safeway
- Stepmar
- Triumph
- Welkin Mech Co
- Other
-
Please write in Company Name
-
Inspection Date
-
Inspection Time
-
County
-
Municipalities
- A - Arsdey
- B - Bronxville
- BM - Briarcliff Manor
- BU - Buchanan
- C - Croton
- CY - City of Yonkers
- DF - Dobbs Ferry
- E - Elmsford
- H - Hastings
- I - Irvington
- L - Larchmont
- MB - Mount Kisco Town of Bedford
- MK - Mount Kisco
- MM - Village of Mamaroneck
- MN - Mount Kisco Town of New Castle
- MP - Mount Pleasant
- MR - Mamaroneck Town of Rye
- MV - Mount Vernon
- NC - New Castle
- NO - North Castle
- NP - North Pelham
- NR - New Rochelle
- NT - North Tarrytown
- O - Ossining (Village)
- P - Pelham
- PC - Portchester
- PK - Peelskill
- PL - Pleasantville
- PM - Pelham Manor
- R - Village of Rye
- RB - Rye Brook
- S - Scarsdale
- T - Tuckahoe
- TB - Town of Bedford
- TC - Town of Cortlandt
- TE - Eastchester
- TG - Town of Greenburgh
- TH - Town of Harrison
- TM - Town of Mamaroneck
- TO - Town of Ossining
- TR - Town of Rye
- TS - Town of Somers
- TT - Tarrytown
- Town of Yorktown
- City of White Plains.
-
M & S Plate
-
Pressure
Pipe Inspection
-
Is there fusion going on?
-
Picture Required
Add a Fuse
-
Joining Type
Butt Fuse
-
Hydraulic or Manual?
-
Straight or Coiled Pipe
-
Pipe Size
- 1 1/4" IPS
- 2 " IPS
- 3" IPS
- 4" IPS
- 6" IPS
- 8" IPS
- 10" IPS
- 12" IPS
- 16" IPS
-
Did you witness fuse being performed?
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Is the Fuser OQ'd in the correct Butt Fusion?
-
Automatic Failure
-
Is fusing equipment up to date on Inspection and Calibration?
-
Automatic Failure
-
Is Iron free of scratches and debris?
-
Automatic Failure
-
Was pipe properly cleaned?
-
Was the pipe marked for slippage?
-
Was the iron Temperature correct and verified?
-
Were the proper pressures used? (During Facing, Heating and Fusing)
-
Was the fuse signed by the Fuser?
-
Was the fuse peer inspected and signed by peer inspector?
-
Any other indications that the fusion process did not follow standards or procedures?
Visual Inspection
-
Uniform Roll Back completely around pipe?
-
High/Low Okay?
-
Properly aligned pipe? (No miter Joints)
-
Is bead size sufficient for size of the pipe?
-
Fusion clear of any contamination?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
Visual Inspection
-
Fuse fails visual inspection if any answer is no.
-
Is the Fuser OQ'd in Butt Fusion?
-
Uniform Roll Back completely around pipe?
-
High/Low Okay?
-
Properly aligned pipe? (No miter Joints)
-
Is bead size sufficient for size of the pipe?
-
Fusion clear of any contamination?
-
Was the fuse signed by the Fuser?
-
Was the fuse signed by the peer inspector?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
Electrofuse
-
Type of Electrofuse?
-
Pipe Size
- 1 1/4" IPS x 0.5" IPS
- 2" IPS x 0.5" IPS
- 2" IPS x 1" IPS
- 2" IPS x 2" IPS
- 3" IPS x 0.5" IPS
- 3" IPS x 1" IPS
- 3" IPS x 1 1/4" IPS
- 3" IPS x 2" IPS
- 4" IPS x 0.5" CTS
- 4" IPS x 0.5" IPS
- 4" IPS x 1" IPS
- 4" IPS x 1 1/4" CTS
- 4" IPS x 2" IPS
- 6" IPS x 0.5" IPS
- 6" IPS x 1" IPS
- 6" IPS x 1 1/4" CTS
- 6" IPS x 2" IPS
- 8" IPS x 0.5" IPS
- 8" IPS x 1" IPS
- 8" IPS x 1 1/4" CTS
- 8" IPS x 2" IPS
- 10" IPS x 0.5" IPS
- 10" IPS x 1" IPS
- 10" IPS x 1" CTS
- 10" IPS x 2" IPS
- 12" IPS x 0.5 IPS
- 12" IPS x 1" IPS
- 12" IPS x 2" IPS
-
Did you witness fuse being performed?
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Is Fuser properly OQ'd in Electrofusion Tee?
-
Automatic failure
-
Is fusing equipment current on inspections and calibrations?
-
Was the pipe and tee properly cleaned before scraping?
-
Was the pipe marked 1" past tee on both sides?
-
Was pipe properly scraped?
-
Was pipe cleaned after scraping?
-
Was tee properly secured to pipe with edges marked?
-
Was continuity verified?
-
Was fuse allowed proper amount of time to cool?
-
Was fuse marked with time to remove clamps?
-
Instruct Mechanic. Good work practice.
-
Was fuse signed by Fuser?
-
Was fuse inspected and signed by peer inspector?
-
Any other indications that the fusion process did not follow standards or procedures?
Visual Inspection
-
Tee centered?
-
Any melt out?
-
Exposed electro fusion wire?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
Visual Inspection
-
Fuse fails visual inspection if any answer is no.
-
Was Fuser properly OQ'd in Electrofusion Tee?
-
Automatic Failure
-
Is there evidence that pipe was scraped properly 1" past tee?
-
Is there evidence that fuse was marked 1" past tee?
-
Tee centered?
-
Any melt out?
-
Exposed electro fusion wire?
-
Did Fuser sign the fuse?
-
Was the Fuse signed by peer inspector?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
- 1/2" CTS
- 1" IPS
- 1" CTS
- 1 1/4" IPS
- 1 1/4" CTS
- 2" IPS
- 3" IPS
- 4" IPS
- 6" IPS
- 8" IPS
- 10" IPS
- 12" IPS
- 16" IPS
-
Did you witness fuse being performed?
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Is Fuser properly OQ'd in Electrofusion Coupling?
-
Automatic Failure
-
Is Fusing equipment current on inspections and calibration?
-
Automatic Failure
-
Was the pipe properly cleaned?
-
Was the stab mark properly made?
-
Was pipe properly scrapped?
-
Was pipe and coupling cleaned with alcohol wipe after scrapping?
-
Was coupling properly secured to pipe, and edges marked on pipe?
-
Was continuity verified?
-
Was fuse allowed proper amount of time to cool prior to handling?
-
Was fuse marked with the proper time to remove clamps
-
Was fuse signed by Fuser?
-
Was fuse peer checked and signed by peer inspector?
-
Any other indications that the fusion process did not follow standards or procedures?
Visual Inspection
-
Fuse fails visual inspection if any answer is no.
-
Proper alignment?
-
Tee centered?
-
Any melt out?
-
Exposed electro fusion wire?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Was the coupling properly centered?
Visual Inspection
-
Fuse fails visual inspection if any answer is no.
-
Was Fuser properly OQ'd in Electrofusion Coupling?
-
Automatic Failure
-
Proper alignment?
-
Was pipe properly marked?
-
Was pipe properly scraped?
-
Was pipe inserted properly? (No Miter Joints)
-
Any melt out?
-
Exposed electro fusion wire?
-
Did the Fuser sign the pipe properly?
-
Was the fuse peer checked and signed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
-
Did you witness fuse being performed?
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Is Fuser properly OQ'd in Electrofusion Coupling?
-
Is fusing equipment current on inspections and calibrations?
-
Was the pipe properly cleaned? Wiped with an alcohol wipe that meets standards?
-
Was the pipe marked 1" past fitting on both sides?
-
Was pipe properly scraped?
-
Was pipe and tee cleaned with alcohol wipe after scrapping?
-
Was tee properly secured to pipe, and edges marked on pipe?
-
Was continuity verified?
-
Was fuse allowed proper amount of time to cool?
-
Was fuse marked with time to remove clamps?
-
Instruct Mechanic. Good work practice.
-
Was fuse signed by Fuser?
-
Was fuse inspected and signed by peer inspector?
-
Any other indications that the fusion process did not follow standards or procedures?
Visual Inspection
-
Any melt out?
-
Exposed electro fusion wire?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
Visual Inspection
-
Fuse fails visual inspection if any answer is no.
-
Was Fuser properly OQ'd in Electrofusion Coupling?
-
Automatic Failure
-
Was pipe properly scraped?
-
Was pipe properly marked?
-
Any melt out?
-
Exposed electro fusion wire?
-
Did Fuser sign the fuse?
-
Was the Fuser peer checked and signed by peer inspector?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Was fuse allowed was fuse marked with time to remove clamp?
Mechanical
-
What type of mechanical fitting?
-
Pipe Size
- 1/2"
- 1"
- 1 1/4"
- 1 1/2"
- 2"
- 3"
- 4"
- 6"
- 8"
- 10"
- 12"
- 16"
-
Did you witness connection being made?
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Was mechanic properly OQ'd in Stab mechanical fittings?
-
Automatic Failure
-
Was pipe properly checked for imperfections?
-
Was the pipe properly cleaned?
-
Was pipe chamfered?
-
Was pipe properly measured and marked?
-
Was connection signed by OQ mechanic?
-
Was connection peer checked and signed?
-
Any other indications that the fusion process did not follow standards or procedures?
Visual Inspection
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
Visual Inspection
-
Was mechanic properly OQ'd in Stab Mechanical fittings?
-
Automatic Failure
-
Is pipe properly marked?
-
Did the OQ mechanic sign the pipe properly?
-
Was the connection peer checked and signed?
-
Any other visual indications of a poor connection observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
- 1/2"
- 1"
- 1 1/4"
- 1 1/2"
- 2"
- 3"
- 4"
- 6"
- 8"
- 10"
- 12"
- 16"
-
Did you witness connection being made?
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Was mechanic properly OQ'd in Nut Follower mechanical fittings?
-
Automatic Failure
-
Was pipe visually inspected for imperfections?
-
Was the pipe properly cleaned?
-
Was pipe properly measured and marked?
-
Was Stiffener applied (if plastic)?
-
Was coupling tightened correctly (One bolt at a time)?
-
Was proper sized wrench used? (for proper torque)
-
Was connection signed by OQ Mechanic?
-
Was connection Peer Inspected and signed?
-
Any other indications that the connection process did not follow standards or procedures?
Visual Inspection
-
Was Anode Bag installed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
Visual Inspection
-
Was mechanic properly OQ'd in Nut Follower Mechanical fittings?
-
If fuser is not qualified, then fuse needs to be cut out and redone.
-
Is there evidence pipe properly marked?
-
Was Anode Bag installed?
-
Did the OQ mechanic sign the pipe properly?
-
Was the connection peer checked and signed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
- 1/2"
- 1"
- 1 1/4"
- 1 1/2"
- 2"
- 3"
- 4"
- 6"
- 8"
- 10"
- 12"
- 16"
-
Did you witness connection being made?
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Was mechanic properly OQ'd in Bolt (7/11) mechanical fittings?
-
Automatic Failure
-
Was pipe inspected for imperfections?
-
Was the pipe properly cleaned?
-
Was pipe properly measured and marked?
-
Was stiffener applied (if plastic)?
-
Was coupling tightened correctly (Star Pattern)?
-
Were Bolts properly Torqued?
-
Was connection signed by OQ Mechanic?
-
Was connection peer inspected and signed?
-
Any other indications that the fusion process did not follow standards or procedures?
Visual Inspection
-
Was Anode Bag installed?
-
Was mastic coating applied?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
Visual Inspection
-
Was mechanic properly OQ'd in Bolt (7/11) Mechanical fittings?
-
Automatic Failure
-
Is the pipe properly marked?
-
Was Anode Bag installed?
-
Was mastic coating applied?
-
Did the Fuser sign the pipe properly?
-
Was the fuse peer checked and signed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
- 1/2"
- 1"
- 1 1/4"
- 1 1/2"
- 2"
- 3"
- 4"
- 6"
- 8"
- 10"
- 12"
- 16"
-
Did you witness connection being made?
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Was mechanic properly OQ'd in Compression (Metfit) mechanical fittings?
-
Automatic Failure
-
Was pipe inspected for imperfections?
-
Was pipe properly measured and marked?
-
Was pipe properly signed by OQ Mechanic?
-
Was connection peer inspected and signed?
-
Any other indications that the fusion process did not follow standards or procedures?
Visual Inspection
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
Visual Inspection
-
Was mechanic properly OQ'd in Compression (Metfit) Mechanical fittings?
-
Automatic Failure
-
Is the pipe properly marked?
-
Did the OQ Mechanic sign the pipe properly?
-
Was the connection peer checked and signed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
Saddle / Sidewall Fusion
-
WARNING Sidewall or Saddle Fusions can only be performed by the development lab
-
Type of Saddle Fusion?
-
Pipe Size
- 1 1/4" IPS
- 2 " IPS
- 3" IPS
- 4" IPS
- 6" IPS
- 8" IPS
- 10" IPS
- 12" IPS
- 16" IPS
-
Did you witness fuse being performed?
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Is the Fuser OQ'd in Saddle Fusion?
-
Automatic Failure
-
Is fusing equipment up to date on Inspection and Calibration?
-
Automatic Failure
-
Is Iron free of scratches and debris?
-
Automatic Failure
-
Was Pipe probably supported?
-
Was the pipe and fitting properly scrapped?
-
Was the pipe and fitting properly cleaned?
-
Was the pipe marked with the proper pressures?
-
Were the correct temperatures used and verified?
-
We're correct pressures used? (During heat, heat soak, and fusion)
-
Was fuse allowed proper amount of time to cool?
-
Was the fuse signed by the Fuser?
-
Was the fuse peer inspected and signed by peer inspector?
-
Any other indications that the fusion process did not follow standards or procedures?
Visual Inspection
-
Is there evidence of scraping?
-
Is there evidence of pressures marked on pipe?
-
Are there 3 uniform adequately sized beads with no sign that the iron slipped?
-
Is the fitting centered on pipe?
-
Fusion clear of any contamination?
-
Is the base of the tee level or above bead pattern?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
Visual Inspection
-
Is the Fuser OQ'd in saddle fusion?
-
Is there evidence of scraping?
-
Is there evidence of pressures marked on pipe?
-
Are there 3 uniform adequately sized beads with no sign that the iron slipped?
-
Is the fitting centered on pipe?
-
Fusion clear of any contamination?
-
Is the base of the tee level or above bead pattern?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
Process Inspection
-
Answer all if they performed the step without any prompting or Forced remediation
-
Is the Fuser OQ'd in Saddle Fusion?
-
Automatic Failure
-
Is fusing equipment up to date on Inspection and Calibration?
-
Automatic Failure
-
Is Iron free of scratches and debris?
-
Automatic Failure
-
Was Pipe probably supported?
-
Was the pipe and fitting properly scrapped?
-
Was the pipe and fitting properly cleaned?
-
Was the pipe marked with the proper pressures?
-
Were the correct temperatures used and verified?
-
We're correct pressures used? (During heat, heat soak, and fusion)
-
Was fuse allowed proper amount of time to cool?
-
Was the fuse signed by the Fuser?
-
Was the fuse peer inspected and signed by peer inspector?
-
Any other indications that the fusion process did not follow standards or procedures?
Visual Inspection
-
Is there evidence of scraping?
-
Is there evidence of pressures marked on pipe?
-
Are there 3 uniform adequately sized beads with no sign that the iron slipped?
-
Is the fitting centered on pipe?
-
Fusion clear of any contamination?
-
Is the base of the tee level or above bead pattern?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Fuser ID
-
Fuser Name
-
Fuser NGA QR Code
-
Peer Fuser
-
Peer Inspector Name
-
Peer Inspector NGA QR Code
-
F2F Unique ID #
-
Take a picture of the fuse
Preexisting Fuses
-
Are there any preexisting fuses that are not part of the current job?
Add a Preexisting Fuse
-
Joining Type
Butt Fuse
-
Pipe Size
- 1 1/4" IPS
- 2 " IPS
- 3" IPS
- 4" IPS
- 6" IPS
- 8" IPS
- 10" IPS
- 12" IPS
- 16" IPS
Visual Inspection
-
Is there evidence that the pipe was properly marked?
-
Uniform Roll Back completely around pipe?
-
High/Low Okay?
-
Properly aligned pipe? (No miter Joints)
-
Is bead size sufficient for size of the pipe?
-
Fusion clear of any contamination?
-
Was the fuse signed by the Fuser?
-
Was the fuse signed by the peer inspector?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
Electrofuse
-
Type of Electrofuse?
-
Pipe Size
- 1 1/4" IPS x 0.5" IPS
- 2" IPS x 0.5" IPS
- 2" IPS x 1" IPS
- 2" IPS x 2" IPS
- 3" IPS x 0.5" IPS
- 3" IPS x 1" IPS
- 3" IPS x 1 1/4" IPS
- 3" IPS x 2" IPS
- 4" IPS x 0.5" CTS
- 4" IPS x 0.5" IPS
- 4" IPS x 1" IPS
- 4" IPS x 1 1/4" CTS
- 4" IPS x 2" IPS
- 6" IPS x 0.5" IPS
- 6" IPS x 1" IPS
- 6" IPS x 1 1/4" CTS
- 6" IPS x 2" IPS
- 8" IPS x 0.5" IPS
- 8" IPS x 1" IPS
- 8" IPS x 1 1/4" CTS
- 8" IPS x 2" IPS
- 10" IPS x 0.5" IPS
- 10" IPS x 1" IPS
- 10" IPS x 1" CTS
- 10" IPS x 2" IPS
- 12" IPS x 0.5 IPS
- 12" IPS x 1" IPS
- 12" IPS x 2" IPS
Visual Inspection
-
Is there evidence that the pipe was properly marked?
-
Is there evidence that the pipe was properly scraped?
-
Is fuse signed by fused?
-
Was fuse inspected and signed by peer inspector?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
- 1/2" CTS
- 1" IPS
- 1" CTS
- 1 1/4" IPS
- 1 1/4" CTS
- 2" IPS
- 3" IPS
- 4" IPS
- 6" IPS
- 8" IPS
- 10" IPS
- 12" IPS
- 16" IPS
Visual Inspection
-
Proper alignment?
-
Is there evidence that the pipe was properly marked?
-
Is there evidence that the pipe was properly scraped?
-
Was pipe inserted properly? (No Miter Joints)
-
Is fuse signed by fused?
-
Was the fuse peer checked and signed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
- 1 1/4" IPS x 0.5" IPS
- 2" IPS x 0.5" IPS
- 2" IPS x 1" IPS
- 2" IPS x 2" IPS
- 3" IPS x 0.5" IPS
- 3" IPS x 1" IPS
- 3" IPS x 1 1/4" IPS
- 3" IPS x 2" IPS
- 4" IPS x 0.5" CTS
- 4" IPS x 0.5" IPS
- 4" IPS x 1" IPS
- 4" IPS x 1 1/4" CTS
- 4" IPS x 2" IPS
- 6" IPS x 0.5" IPS
- 6" IPS x 1" IPS
- 6" IPS x 1 1/4" CTS
- 6" IPS x 2" IPS
- 8" IPS x 0.5" IPS
- 8" IPS x 1" IPS
- 8" IPS x 1 1/4" CTS
- 8" IPS x 2" IPS
- 10" IPS x 0.5" IPS
- 10" IPS x 1" IPS
- 10" IPS x 1" CTS
- 10" IPS x 2" IPS
- 12" IPS x 0.5 IPS
- 12" IPS x 1" IPS
- 12" IPS x 2" IPS
Visual Inspection
-
Fuse fails visual inspection if any answer is no.
-
Is there evidence that the pipe was properly marked?
-
Proper alignment?
-
Is there evidence that the pipe was properly scraped?
-
Was pipe inserted properly? (No Miter Joints)
-
Is pipe signed by fused?
-
Was the Fuser peer checked and signed by peer inspector?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
Mechanical
-
What type of mechanical fitting?
-
Pipe Size
- 1/2"
- 1"
- 1 1/4"
- 1 1/2"
- 2"
- 3"
- 4"
- 6"
- 8"
- 10"
- 12"
- 16"
Visual Inspection
-
Was mechanic properly OQ'd in Stab Mechanical fittings?
-
Automatic Failure
-
Is pipe properly marked?
-
Is pipe signed by joiner?
-
Was the connection peer checked and signed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
- 1/2"
- 1"
- 1 1/4"
- 1 1/2"
- 2"
- 3"
- 4"
- 6"
- 8"
- 10"
- 12"
- 16"
Visual Inspection
-
Is there evidence that the pipe was properly marked?
-
Was Anode Bag installed?
-
Is pipe signed by joiner?
-
Was the connection peer checked and signed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
- 1/2"
- 1"
- 1 1/4"
- 1 1/2"
- 2"
- 3"
- 4"
- 6"
- 8"
- 10"
- 12"
- 16"
Visual Inspection
-
Is there evidence that the pipe was properly marked?
-
Was Anode Bag installed?
-
Was mastic coating applied?
-
Is pipe signed by joiner?
-
Was the fuse peer checked and signed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Pipe Size
- 1/2"
- 1"
- 1 1/4"
- 1 1/2"
- 2"
- 3"
- 4"
- 6"
- 8"
- 10"
- 12"
- 16"
Visual Inspection
-
Is there evidence that the pipe was properly marked?
-
Is pipe signed by joiner?
-
Was the fuse peer checked and signed?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Passes Visual Inspection?
-
Please Enter Comments. Include what Actions taken.
Visual Inspection
-
Is there evidence of scraping?
-
Is there evidence of pressures marked on pipe?
-
Are there 3 uniform adequately sized beads with no sign that the iron slipped?
-
Is the fitting centered on pipe?
-
Fusion clear of any contamination?
-
Is the base of the tee level or above bead pattern?
-
Any other visual indications of a poor fuse observed? If yes, please make documentation below
-
Fuse Pass Inspection?
-
Please Enter Comments. Include what Actions taken.
-
Fuser ID
-
Peer Fuser
-
Take a picture of the fuse