Title Page

  • Conducted on

  • ELECTRICIANS NAME

  • COMPANY NAME

  • TOW NUMBER

  • NODE SITE ID

  • SITE ADDRESS.

SITE INFORMATION

  • WHO IS THE POWER UTILITY COMPANY.

  • WHATE STATE IS THIS AUDIT CONDUCTED IN?

  • IS THE SWITCHBOARD, PIT OR POLE MOUNTED?

  • WHAT IS THE METER NMI NUMBER.

  • IS THE METER, METERED OR UNMETERED?

PREPARE SITE

  • HAS FTTN NOC BEEN ADVISED WORK IS BEING UNDERTAKEN AT SITE.<br><br>

  • HAVE YOU CONDUCTED A HSE RISK ASSESSMENT AND PRE START CHECKLIST.

  • HAS A SAFETY PRE START BEEN CONDUCTED AND APPROPRIATE CONTROLS BEEN IMPLEMENTED.

CONFIRM BACKUP SUPPLY AND ISOLATE NORMAL SUPPLY.

  • IS THE BATTERY CAPACITY SUFFICIENT TO COMPLETE THE WORK WITHOUT LOSS OF SERVICE?<br><br><br>

  • HAVE YOU ISOLATED AT THE MAIN SWITCHBOARD FUSE?

  • HAVE YOU TESTED AND CONFIRMED OUTGOING SUBCIRCUIT AT MAIN SWITCHBOARD IS ISOLATED?

  • HAVE YOU TESTED AT THE CABINET, TO CONFIRM THE INCOMING SUPPLY IS ISOLATED?

REWIRE CABINET

  • HAS ALL WIRING BEEN COMPLETED AS PER NBN-CON-TIB-3374?

  • TAKE A PHOTO OF GENERATOR N - E BOND CABLE LABELED AND CONNECTED TO CABINET PE BAR.

  • TAKE A PHOTO OF GENERATOR CHANGEOVER SWITCH WIRING CHANGE.

  • TAKE A PHOTO OF THE GENERATOR CHANGEOVER SWITCH COVER LABELED TIB - 3374 COMPLIANT.

  • CONFIRM SIZE OF MAINS AND MAIN ECC

REPLACE RCBO

  • REMOVE EXISTING RCBO AND NOTE (MANUFACTURER, RATING AND MODEL)

  • TAKE A PHOTO OF THE SWITCHBOARD WITH EXISTING RCBO REMOVED

  • INSTALL APPROVED SI RCBO AND NOTE (MANUFACTURER, RATING AND MODEL)

  • TAKE A PHOTO OF THE SWITCHBOARD WITH SI RCBO INSTALLED

  • HAS ALL TESTING BEEN COMPLETED?

ENERGISE, TEST AND SUBMIT

  • HAVE YOU RE-CONNECT THE SUPPLY (AT FUSE IN MAIN SWITCHBOARD)?

  • ENSURE SUPPLY IS WORKING AND CABINET IS POWERED ON.

  • COMPLETE REMAINING TESTS, I.E. THOSE THAT REQUIRE SUPPLY TO BE AVAILABLE.

  • HAVE YOU REPLACED THE EXISTING WIRING DIAGRAM WITH NEW ONE?

  • PHOTOGRAPH OF UPDATED SCHEMATIC (TO BE PLACED IN CABINET DOCUMENT HOLDER)

  • CONTACT FTTN NOC TO ADVISE JOB IS COMPLETE PRIOR TO LEAVING SITE.

  • WILL ALL ARTEFACTS BE SUBMITTED TO NBN .

  • TAKE A PHOTO OF COMPLETED EXTERNAL (POLE,PILLAR OR PIT) SWITCHBOARD

  • FOR POLE-MOUNTED SWITCHBOARDS: PHOTO OF CONDUIT AT TOP OF POLE (I.E. AT POINT OF CONNECTION TO MAINS)

ELECTRICAL INSPECTION

  • HAS THE ELECTRICAL INSPECTOR BEEN ADVISED SITE IS READY FOR INSPECTION

  • PHOTOGRAPH OR SCAN OF CERTIFICATE OF ELECTRICAL SAFETY

  • ADDITIONAL COMMENTS

SIGN OFF

  • ELECTRICIANS NAME AND SIGNATURE

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.