Title Page
-
Site conducted
Programmed Facility Management - 61 054 742 264
-
Conducted on
-
Prepared by
Electrical Contractors Number: EC005821
-
Work Order Number
-
Location
-
Property Number and Street Name
-
Document Number
Safe Work Method Statement (SWMS) Electrical Testing - All sections must be completed in full ahead of works commencing.
Personal Protective Equipment
-
Mandatory PPE
Additional PPE
-
Hand Protection
-
Insulated Gloves
-
Insulated Floor Mat
-
Flame Proof Clothing
-
Arc Flash Clothing
-
Other
-
* After completing this section, please proceed to the next section.
SWMS Tasks & Details
-
Electrical Testing
STEP 1 |Attend site and advise of interruption to supply on circuits under test
-
HAZARD(S): Tenant objects to works being performed
-
Risk Rating
-
CONTROL: Communicate & coordinate with Tenant. Service Center & Supervisor to prevent downtime
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 2 | Perform Take 5 Site Risk Assessment
-
HAZARD(S): Risks as identified
-
Risk Rating
-
CONTROL: Apply risk management processes to additional identified risks using the Hierarchy of Control
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 3 | Assess Switchboard for condition and age
-
HAZARD(S): Door falling off, Falling Debris into Switchboard, Electrocution, Identification of Asbestos & safe handling requirements
-
Risk Rating
-
CONTROL: If Switchboard in Poor Condition isolate main switch before removing covers
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 4 | Isolate, test, tag and lock out main supply
-
HAZARD(S): Electrocution
-
Risk Rating
-
CONTROL: Ensure use of calibrated electrical test equipment (if Live, conduct work in accordance with AS/NZS 4836 Safe Work Live Practices and AS/NZS 3017 Testing & Inspecting guidelines, ensure voltage disconnected)
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 5 | Remove switchboard covers
-
Is this work task required? If Yes proceed with risk assessment
-
HAZARD(S): Manual Handling injuries (Sprains, Strains); Trip hazard, cuts and pinch points
-
Risk Rating
-
CONTROL: Ensure workers are trained in correct Manual Handling techniques, Ensure SWB cover is away from traffic areas, wear gloves where appropriate
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 6 | Assess behind switchboard covers for condition and age
-
Is this work task required? If Yes proceed with risk assessment
-
HAZARD(S): Electrocution, Falling Debris into, Switchboard, Breakdown of insulation on bus-bars, UN-terminated cables
-
Risk Rating
-
CONTROL: Test all exposed terminals for dead, if switchboard is deemed unsafe reinstate covers, Take Photos and Report issue and seek direction on how best to proceed.
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 7 | Reinstate Switchboard covers
-
Is this work task required? If Yes proceed with risk assessment
-
HAZARD(S): Manual Handling injuries (Sprains, Strains); Trip hazard, cuts and pinch points
-
Risk Rating
-
CONTROL: Ensure workers are trained in correct Manual Handling techniques, Ensure SWB cover is away from traffic areas, wear gloves where appropriate and before leaving ensure cover is secure
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 8 | Reinstate power supply if isolated in step 3
-
HAZARD(S): Electrocution
-
Risk Rating
-
CONTROL: All employees to be aware of live services, Use of Insulation Mats where applicable
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 9 | Conduct Earth Fault Loop Impendence Test - From Field Outlet
-
Hazards(S):
Arcing of contacts projecting foreign matter into eye
Electric Shock from Tester -
Risk Rating
-
CONTROL: Safety glasses or face shield to be worn and be aware of live services, Use of Insulation Mats where applicable and use calibrated electrical test equipment, insulated gloves. Follow SOP Electrical Testing
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 10 | Conduct push button test, confirm operation
-
Hazard: Arcing of contacts projecting foreign matter into eye
-
Risk Rating
-
CONTROL: Safety glasses or face shield to be worn and be aware of live services, Use of Insulation Mats where applicable and use calibrated electrical test equipment, insulated gloves. Follow SOP Electrical Testing
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 11 | Conduct RCD Injection Test - From Field Outlet
-
Hazards(S):
Arcing of contacts projecting foreign matter into eye
Electric Shock from Tester -
Risk Rating
-
CONTROL: Safety glasses or face shield to be worn and be aware of live services, Use of Insulation Mats where applicable and use calibrated electrical test equipment, insulated gloves. Follow SOP Electrical Testing
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 12 | If RCD fails either push button or trip time tests then replace RCD and repeat tests
-
HAZARD(S): Electrocution
-
Risk Rating
-
CONTROL: Isolate circuit, wear safety glasses (refer to step 4)
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 13: Perform Smoke Alarm visual check and push button test.
-
Is this work task required? If Yes proceed with risk assessment
-
HAZARD(S): Manual Handling injuries (Sprains, Strains); Noise, Trip hazard, Fall from Ladder
-
Risk Rating
-
CONTROL: Ensure workers are trained in correct Manual Handling techniques, Ensure ladder is fit for use, secure and on flat surface and all trip hazards removed from work area and hearing protection worn.
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 14: If Smoke Alarm tests fail, then replace smoke alarm with approved brand and label, reconnect supply, test and commission
-
HAZARD(S): Manual Handling injuries (Sprains, Strains); Noise, Falling debris, Trip hazard, Fall from Ladder
-
Risk Rating
-
CONTROL: Ensure workers are trained in correct Manual Handling techniques, Ensure ladder is fit for use, secure and on flat surface and all trip hazards removed from work area and hearing & eye protection worn.
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 15: Perform visual inspection of main earth wire and electrode, where damaged repair or replace (isolate supply if replacing) refer to Step 4.
-
HAZARD(S): Manual Handling injuries (Sprains, Strains); Trip hazard
-
Risk Rating
-
CONTROL: Ensure workers are trained in correct Manual Handling techniques and all trip hazards removed from work area.
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 16: Perform Earth Continuity testing on equipotential earthing bonds (Pool, Pool Fencing, Pool Equipment etc)
-
HAZARD(S): Manual Handling injuries (Sprains, Strains); Trip hazard, Tenant animals,
-
Risk Rating
-
CONTROL: Ensure workers are trained in correct Manual Handling techniques and all trip hazards removed from work area, all animals secured. Follow SOP Electrical Testing
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
STEP 17: Once all Tasks have been completed and before leaving site, Reinstate power supply
-
HAZARD(S): Electrocution
-
Risk Rating
-
CONTROL: All employees to be aware of live services, Use of Insulation Mats where applicable
-
Residual Risk after Control Implemented (NOTE: Where High or Extreme risks have been identified - Stop Work and report to Supervisor)
-
RESPONSIBLE PERSONS: Supervisors, Workers
Verification and Sign Off
TOOLS AND EQUIPMENT MAINTENANCE INSPECTIONS | Checked Ladders for compliance, Checked all electrical leads are tested with current compliance tag, Checked all tools and all testing equipment is calibrated and fit for use.
REFERENCES| Legislation/ regulations/ standards/ codes of practices/ guidelines that are relevant to this activity/ task: AS/NZS 4836 Safe Work Live Practices, AS/NZS 3017 Electrical Installations, testing and inspections guidelines, Electricity (Licensing) Regulations, Programmed Policies, Programmed Life Saving Rules and Procedures, Manufactures Product Instructions
I have reviewed this Safe Work Method Statement (SWMS) and agree with this safe work procedure. I am aware of all the job steps, hazards and control measures that will be implemented and will work to this safe work procedure. I will complete a daily JSEA as required. I have also reviewed all the Safety Data Sheets (SDS) and have assessed all the plant and equipment that is to be used by myself for this task. I will work within the recommended safe procedures for SDS, plant and equipment for this period.
-
Workers Sign Off
-
Date
-
Electrical Workers Number
-
Name and Signiture