  • Document No.

  • Audit Title: Daily Safety Audit

  • Client / Site : TEMA/ TMMK Georgetown

  • Conducted on

  • Prepared by

  • Location: 1001 Cherry Blossom Way
  • Personnel

Section C JSA Post Audit Review

  • TCSR Reviewed by workers, signed

  • TCSR Follows Work: Applicable

  • TCSR Posted, Easy access

  • TCSR Required Documents on Control Board

Section D Environmental/Site Conditions

  • OSHA 1926.50 First Aid Kit ,stocked, eye wash, accessible

  • OSHA 1926.51 Sanitation: toilets clean,stocked (portables)

  • OSHA 1926.52 Noise: below 85 dba,protection used

  • OSHA 1926.56 general, task

  • OSHA 1926.57 Ventilation: heat, odors

  • OSHA 1926.55 Dust Control

Section E Personal Protective Equipment

  • OSHA 1926.95 Stand: hard hat,safety glasses,hi vis clothing,boots

  • TCSR Other: correct for area, task,department

Section F Fire Protection

  • OSHA 1926.150(c) Extinguishers : present,sized for task

  • OSHA 1926.152(a) Flammable liquids: controlled,stored properly

  • OSHA 1926.152 Fuel: stored correctly,(propane,oxygen)

Section G Signs, Barricades

  • OSHA 1926.202 Proper Barricades:placement

  • OSHA 1926.200 Signs:correct,posted,phone number,red/yellow tape

Section H Materials/Handling//Storage/5S

  • OSHA 1926.250 Material,Tools,Equipment :stored properly,neatly stacked

  • OSHA 1926.250(a)(3) Trip Hazards: cords neatly run, areas clean

  • OSHA 1926.34(c) Liquids on floor: spill kit available

  • OSHA 1926.251 Rigging for material handling correct,stored properly

Section I Tools:hand and power

  • OSHA 1926.300(a) Condition : handles used, cord not damaged

  • OSHA 1926.300(b) Guarding: used, adjusted correctly

  • OSHA 1926.300 Proper Usage:correct tool for the job

  • TCSR Identification: on gang boxes, tools, equipment

Section J Welding,Cutting, and Grinding

  • TCSR Hot Work Requirements Met: issued

  • OSHA 1926.95(a) Proper PPE: non flammable clothing

  • OSHA 1926.352(a) Shields, Barriers:equipment, area protected

  • OSHA 1926.350 Gas Equipment : proper storage,flash arrestors used

Section K Electrical

  • OSHA 1926.404(b)(1)(ii) GFCI Protection: tested

  • OSHA 1926.405(a)(2)(ii)(i) Extension Cords: condition,protected,inspected

Section L Scaffolds

  • OSHA 1926.451(b) No missing planking,bracing,guardrails

  • OSHA 1926.451(f)(3) Inspected: tagged,hazards noted

  • OSHA 1926.451(h) Falling Object Protection: toeboards

  • OSHA 1926.452(w)(2) Rolling Scaffolds: wheels locked

  • OSHA 1926.453 Workers tied off in aerial lifts, proper fall protection

  • TCSR BASKET' floor cleaned, materials loaded properly

Section M Fall protection

  • OSHA 1926.502 PFAS: inspected, good condition, worn properly

  • OSHA 1926.502 Proper Anchorage: clamps, straps,lines

  • TCSR Workers tied off in scissor lifts

  • OSHA 1926.502 100% tie off in use (double lanyards)

  • OSHA 1926.501(b)(2) Leading Edges: identified,protected

  • OSHA 1926.502(f) Warning lines: used, proper distance

  • TCSR For Openings: permit issued, followed

  • TCSR Roof work: permitted,weather conditions

Section O Motor Vehicles/Mechanized Equipment

  • TCSR Daily inspections, equipment identified

  • OSHA 1926.600 Safety Devices:seat belts,lights, alarms

  • TCSR Operators : certified, authorized, licenced

  • OSHA 1910.178 Forklifts operated correctly

Section P Excavations

  • OSHA 1926.652 Over 5 Foot: sloped, benched,shored,shielded

  • OSHA 1926.651(c) Over 4 Foot: ladder access, every 25 ft.

  • OSHA 1926.651(j) Spoils: back 3 ft.

  • OSHA 1926.651(h) Water Intrusion: rain, seepage

  • OSHA 1926.651(j)(2) Excavation Protected: equipment, workers

Section Q Concrete and Masonry Construction

  • OSHA 1926.701(b) Impalement: rebar, rods, capped, protected

  • OSHA 1926.706 Masonry walls supported, Limited access zone

Section R Steel Erection, Equipment Placement

  • OSHA 1926.759 Area protected from overhead lifts

  • OSHA 1926.752 Site specific erection plan in place

  • TCSR Area will support equipment and load

Section T Demolition

  • TCSR Engineer survey by Competent Person made

  • TCSR All Services: shut off, capped, disc, removed

Section V Power Transmission/Distribution/LO

  • OSHA 1910.147 Energy Sources: identified, isolated, locked out

  • TCSR Sign In /Sign Out Sheet: used and correct

  • OSHA 1910.147(f)(3)(ii)(D) Group LO: key box used, key inside

  • OSHA 1910.147(c)(5)(ii)(D) Locks: labeled, contain required information

  • NFPA 70e Arc Fashion: proper PPE, workers trained

Section X Ladders

  • OSHA 1926.1053(b)(1) Secured: used properly, right type for work

  • TCSR NON-Conductive: no metal side rails

  • OSHA 1926.1053(a) Good Condition: rungs, rails, bracing

Section Z Toxic/Hazardous Substances

  • TCSR Chemicals: identified, labeled

  • TCSR Stored Properly: correct containment

  • TCSR SDS Sheets: available, correct

  • TCSR Proper PPE being used

Section CC Cranes and Derricks

  • OSHA 1926.1427(a) Crane Operator Certified: card checked

  • OSHA 1926.1412 Crane Inspections: certified, current

  • OSHA 1926.251 Rigging: condition, inspected, rating tag

  • OSHA 1926.1401 Rigger Qualified: checked

  • OSHA 1926.1419 Signal Person: qualified, checked

Section A1 Confined Space

  • OSHA 1910.146(c)(5)(ii)(C) Air Quality Tested

  • OSHA 1910.146(c)(2) Permit/ Checklist posted

  • OSHA 1910.146(g) Workers Trained/rescue notified

Section

  • TEMA Representative signature

  • TEMA Representative signature.

  • Walbridge DIG Safety signature

  • Walbridge DIG Superintendent signature

  • Walbridge DIG Team Member signature

  • Contractor Signature

  • Contractor Signature

  • Contractor Signature

  • Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.