GENERAL REQUIREMENTS

  • During the Inspection, Representatives are present from Landlord, Tenant & Contractor

  • All necessary equipment & tools such as Ladders and steps, torch, etc. should be provided by the Tenant

  • All necessary testing equipment and Trained staff to perform the testing to be provided by the Tenant

  • Tenant to provide laborers to assist the Team in the inspection process

  • Tenant to provide approved Drawing from QCDD for reference

  • All access panels shall be required to be opened

Phase 1: PreInspection Checklist

  • Visual inspection of Fire Alarm System installation

  • Visual inspection of Fire Fighting System installation

  • Visual Inspection of Emergency exit & lighting system installation

  • Visual inspection of smoke extract system installation

  • Visual inspection of Fire suppression system

  • Conduct General inspection to identify any apparent item that may represent a fire risk or hazard or inhibit the operation of the Life Safety System

Phase 2: Witness Testing

Fire Fighting System

  • Close Sprinkler isolating valve and confirm signal is received at Landlord Panel

  • Put the Sprinkler Isolating valve into its normal Open position after testing

  • Open Drain valve and confirm signal is received at Landlord Panel

  • Put the Drain valve into its normal Close position after testing

Fire Alarm System (FAS) Note - As part of the fire alarm system, the cause and effect should be verified based on a review of the tenant cause and effect.

FAS Panel

  • FAS Panel - Inspect Fire alarm panel and check if panel is clear of faults

  • FAS Panel - Turn off power supply of FAS panel and confirm if panel remains active

Smoke detectors and manual call points - 20% of smoke detector devices installed by Tenants shall be witness tested, which shall include one manual call point, or 3 devices including one manual call point, whichever is greater.

  • Smoke Detectors & Manual Call Points - Smoke detectors are properly tagged

  • Smoke Detectors & Manual Call Points - Test smoke detector with smoke detector test cup or operation test key, confirm that this activates the fire alarm panel & sounders or PAVA

  • Smoke Detectors & Manual Call Points - Record witness tested device address and location in provided log sheet

  • Smoke Detectors & Manual Call Points - Mute the FAS panel, confirm that the panel remains in fire state but fire alarm sounders and PAVA cease

  • Smoke Detectors & Manual Call Points - Test manual call point and confirm that this activates the Fire alarm panel and sounders

  • Smoke Detectors & Manual Call Points - Remove 1 smoke detector head and observe if fault will register in the FAS panel

Heat detectors -50% of heat detector devices installed by Tenants shall be witness tested or 2 devices, whichever is greater.

  • Heat Detectors - Heat detectors are properly tagged

  • Heat Detectors - Test heat detector with heat detector test cup or operation test key, confirm that this activates the fire alarm panel & sounders or PAVA

  • Heat Detectors - Record witness tested device address and location in provided log sheet

  • Heat Detectors - Mute the FAS panel, confirm that the panel remains in fire state but fire alarm sounders and PAVA cease

  • Heat Detectors - In the case of any failure the number of devices to be witness tested shall be increased 40% or 6 devices whichever is greater

Fire alarm cause and effect - As part of the fire alarm system, the cause and effect should be verified based on a review of the tenant cause and effect, this may include but not limited to the following;

  • Music Activation of FAS results in any music system ceasing to operate

  • FCUActivation of FAS results in FCU turning off

  • Roller shutter - Test 1: Power on Activation of FAS results in roller shutter doors to open

  • Roller shutter - Test 2: Power off Activation of FAS results in roller shutter doors to open

  • Access Control Doors - Test 1: Power on Activation of FAS results in Access control doors to open

  • Access Control Doors - Test 2: Power off Activation of FAS results in Access control doors to open

  • EscalatorsActivation of FAS results in any escalators to stop

  • LiftsActivation of FAS results in any lifts to Ground and doors to open

  • Mechanical Ventillation, Smoke Extract Activation of FAS results in smoke extract to start

  • LPG Solenoid control valve Activation of the fire alarm results in Gas Solenoid valve to close

  • Electric Power to kitchen equipment Activation of FAS results in Power to kitchen equipment to be isolated

  • Smoke Curtains Activation of FAS results in smoke curtains to drop

  • Air Handling Supply Fans to Unit Activation of FAS results to stopping of AHU supply fans

  • General & toilet fans installed by Tenants Activation of FAS results to stop operation off this units

  • Kitchen Exhaust Fan Activation of FAS results to stop operation of KEF

  • Fire/Smoke Dampers Activation of FAS results to Fire/Smoke Dampers to Close

Fire Alarms sounders/PAVA and Strobe Light

  • Confirm audibility of PAVA or sounders

  • Confirm operation of Strobe light

Smoke detectors & Manual Call Points Landlord - 10% of devices installed by Tenants shall be witness tested, which shall include one manual call point, or 2 devices including one manual call point, whichever is greater. In the case of any failure of any device, Base build shall be requested to attend unit and undertake 100% retest.

  • Test smoke detector with smoke detector test cup or operation test key, confirm that this activate the Landlord fire alarm panel

  • Remote LED indicator is functioning

Fire Suppression System (FSS)

  • Disarm FSS with locking Bar

  • Visual inspection of the system and check CO2 cylinders

  • Remove CO2 cylinder check date and weigh cylinder to confirm it is charged

  • Check chemical tank, remove and confirm if charged

  • Activate the SystemPull manual activation point and confirm the following effects,

  • Activation mechanism operates

  • Retail unit FAS activates

  • Retail unit Gas solenoid valve closes

  • Electrical Power to kitchen is isolated

  • Activate the Systemrelease fusible link and confirm the following effects,

  • Activation mechanism operates

  • Retail unit FAS activates

  • Retail unit Gas solenoid valve closes

  • Reset the system

  • Disarm FSS with locking Bar

  • Install Chemical Tank

  • Install CO2 cylinder

Mechanical VentillationSmoke Extract Fan (SEF)

  • Test 1 Volume flow rate - Activate SEF and check volume flow rate in minimum of 2 extract grills

  • Test 2 Smoke Test - Using smoke generator fill an area with smoke

  • Test 2 Smoke Test - Activate SEF and check volume flow rate in minimum of 2 extract grills

  • Test 2 Smoke Test - Record time taken to clear the smoke. Video required - In case of volume flow rate being different in the witness test than the indicated on the commissioning data, another measurement should be done.

Emergency Lighting

  • Turn of Power of the unit, all emergency lighting should operate

  • Measure lighting levels and to be compared to commissioning data results for conformity

  • After 30 minutes , put back the normal power and confirm the emergency exit and escape lighting is maintained

Fire alarm testing - Power off

  • Turn off Power of the Retail unit and activate the FAS, confirm the following

  • Fire alarm Functions

  • PAVA, sounder and or Strobe Light function

  • Roller shutter raises

  • Access control doors open

  • Lift grounds

  • Mechanical ventillationSmoke extract system functions

  • Smoke and fire dampers operate

  • Smoke curtains function

LPG System - Press Emergency shut off switch, observe the following;

  • LPG Solenoid control valve Activation of the fire alarm results in Gas Solenoid valve to close

  • LPG System sounder will activate

  • Electrical power to Kitchen equipment to Cut off

  • FCUs will stop

  • Kitchen ventillation fans will stop

  • Fire Alarm will activate and all Flash sounders will operate

  • Fire status will be displayed on Tenants FACP. Check & Record device address and location

  • Tenant Music system will cease to operate

Initiate Gas Leak Sequence, observe the following:

  • LPG Solenoid control valve Activation of the fire alarm results in Gas Solenoid valve to close

  • LPG System sounder will activate

  • Electrical power to Kitchen equipment to Cut off

  • FCUs will stop

  • Kitchen ventillation fans will stop

  • Fire Alarm will activate and all Flash sounders will operate

  • Fire status will be displayed on Tenants FACP. Check & Record device address and location

  • Tenant Music system will cease to operate

Phase 3: Interface Tenant Fire Alarm Panel with Landlord

  • Activate Tenant Fire alarm panel, observe if signal is received in Landlord FAS and unit is identified correctly

  • Landlord sends fire alarm to tenant, observe if signal is received in Tenant's FAS

  • Tenant FAS induces fault, observe if fault signal is received at Landlords FAS panel correctly

  • Name of Contractor

  • Name of Tenant

  • Landlord

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.