Title Page
-
Tenant/Unit
-
Conducted on
-
Prepared by - Inspector name
-
Document number
GENERAL REQUIREMENTS
-
During the Inspection, Representatives are present from Landlord, Tenant & Contractor
-
All necessary equipment & tools such as Ladders and steps, torch, etc. should be provided by the Tenant
-
All necessary testing equipment and Trained staff to perform the testing to be provided by the Tenant
-
Tenant to provide laborers to assist the Team in the inspection process
-
Tenant to provide approved Drawing from QCDD for reference
-
All access panels shall be required to be opened
Phase 1: PreInspection Checklist
-
Visual inspection of Fire Alarm System installation
-
Visual inspection of Fire Fighting System installation
-
Visual Inspection of Emergency exit & lighting system installation
-
Visual inspection of smoke extract system installation
-
Visual inspection of Fire suppression system
-
Conduct General inspection to identify any apparent item that may represent a fire risk or hazard or inhibit the operation of the Life Safety System
Phase 2: Witness Testing
Fire Fighting System
-
Close Sprinkler isolating valve and confirm signal is received at Landlord Panel
-
Put the Sprinkler Isolating valve into its normal Open position after testing
-
Open Drain valve and confirm signal is received at Landlord Panel
-
Put the Drain valve into its normal Close position after testing
Fire Alarm System (FAS) Note - As part of the fire alarm system, the cause and effect should be verified based on a review of the tenant cause and effect.
FAS Panel
-
FAS Panel - Inspect Fire alarm panel and check if panel is clear of faults
-
FAS Panel - Turn off power supply of FAS panel and confirm if panel remains active
Smoke detectors and manual call points - 20% of smoke detector devices installed by Tenants shall be witness tested, which shall include one manual call point, or 3 devices including one manual call point, whichever is greater.
-
Smoke Detectors & Manual Call Points - Smoke detectors are properly tagged
-
Smoke Detectors & Manual Call Points - Test smoke detector with smoke detector test cup or operation test key, confirm that this activates the fire alarm panel & sounders or PAVA
-
Smoke Detectors & Manual Call Points - Record witness tested device address and location in provided log sheet
-
Smoke Detectors & Manual Call Points - Mute the FAS panel, confirm that the panel remains in fire state but fire alarm sounders and PAVA cease
-
Smoke Detectors & Manual Call Points - Test manual call point and confirm that this activates the Fire alarm panel and sounders
-
Smoke Detectors & Manual Call Points - Remove 1 smoke detector head and observe if fault will register in the FAS panel
Heat detectors -50% of heat detector devices installed by Tenants shall be witness tested or 2 devices, whichever is greater.
-
Heat Detectors - Heat detectors are properly tagged
-
Heat Detectors - Test heat detector with heat detector test cup or operation test key, confirm that this activates the fire alarm panel & sounders or PAVA
-
Heat Detectors - Record witness tested device address and location in provided log sheet
-
Heat Detectors - Mute the FAS panel, confirm that the panel remains in fire state but fire alarm sounders and PAVA cease
-
Heat Detectors - In the case of any failure the number of devices to be witness tested shall be increased 40% or 6 devices whichever is greater
Fire alarm cause and effect - As part of the fire alarm system, the cause and effect should be verified based on a review of the tenant cause and effect, this may include but not limited to the following;
-
Music Activation of FAS results in any music system ceasing to operate
-
FCUActivation of FAS results in FCU turning off
-
Roller shutter - Test 1: Power on Activation of FAS results in roller shutter doors to open
-
Roller shutter - Test 2: Power off Activation of FAS results in roller shutter doors to open
-
Access Control Doors - Test 1: Power on Activation of FAS results in Access control doors to open
-
Access Control Doors - Test 2: Power off Activation of FAS results in Access control doors to open
-
EscalatorsActivation of FAS results in any escalators to stop
-
LiftsActivation of FAS results in any lifts to Ground and doors to open
-
Mechanical Ventillation, Smoke Extract Activation of FAS results in smoke extract to start
-
LPG Solenoid control valve Activation of the fire alarm results in Gas Solenoid valve to close
-
Electric Power to kitchen equipment Activation of FAS results in Power to kitchen equipment to be isolated
-
Smoke Curtains Activation of FAS results in smoke curtains to drop
-
Air Handling Supply Fans to Unit Activation of FAS results to stopping of AHU supply fans
-
General & toilet fans installed by Tenants Activation of FAS results to stop operation off this units
-
Kitchen Exhaust Fan Activation of FAS results to stop operation of KEF
-
Fire/Smoke Dampers Activation of FAS results to Fire/Smoke Dampers to Close
Fire Alarms sounders/PAVA and Strobe Light
-
Confirm audibility of PAVA or sounders
-
Confirm operation of Strobe light
Smoke detectors & Manual Call Points Landlord - 10% of devices installed by Tenants shall be witness tested, which shall include one manual call point, or 2 devices including one manual call point, whichever is greater. In the case of any failure of any device, Base build shall be requested to attend unit and undertake 100% retest.
-
Test smoke detector with smoke detector test cup or operation test key, confirm that this activate the Landlord fire alarm panel
-
Remote LED indicator is functioning
Fire Suppression System (FSS)
-
Disarm FSS with locking Bar
-
Visual inspection of the system and check CO2 cylinders
-
Remove CO2 cylinder check date and weigh cylinder to confirm it is charged
-
Check chemical tank, remove and confirm if charged
-
Activate the SystemPull manual activation point and confirm the following effects,
-
Activation mechanism operates
-
Retail unit FAS activates
-
Retail unit Gas solenoid valve closes
-
Electrical Power to kitchen is isolated
-
Activate the Systemrelease fusible link and confirm the following effects,
-
Activation mechanism operates
-
Retail unit FAS activates
-
Retail unit Gas solenoid valve closes
-
Reset the system
-
Disarm FSS with locking Bar
-
Install Chemical Tank
-
Install CO2 cylinder
Mechanical VentillationSmoke Extract Fan (SEF)
-
Test 1 Volume flow rate - Activate SEF and check volume flow rate in minimum of 2 extract grills
-
Test 2 Smoke Test - Using smoke generator fill an area with smoke
-
Test 2 Smoke Test - Activate SEF and check volume flow rate in minimum of 2 extract grills
-
Test 2 Smoke Test - Record time taken to clear the smoke. Video required - In case of volume flow rate being different in the witness test than the indicated on the commissioning data, another measurement should be done.
Emergency Lighting
-
Turn of Power of the unit, all emergency lighting should operate
-
Measure lighting levels and to be compared to commissioning data results for conformity
-
After 30 minutes , put back the normal power and confirm the emergency exit and escape lighting is maintained
Fire alarm testing - Power off
-
Turn off Power of the Retail unit and activate the FAS, confirm the following
-
Fire alarm Functions
-
PAVA, sounder and or Strobe Light function
-
Roller shutter raises
-
Access control doors open
-
Lift grounds
-
Mechanical ventillationSmoke extract system functions
-
Smoke and fire dampers operate
-
Smoke curtains function
LPG System - Press Emergency shut off switch, observe the following;
-
LPG Solenoid control valve Activation of the fire alarm results in Gas Solenoid valve to close
-
LPG System sounder will activate
-
Electrical power to Kitchen equipment to Cut off
-
FCUs will stop
-
Kitchen ventillation fans will stop
-
Fire Alarm will activate and all Flash sounders will operate
-
Fire status will be displayed on Tenants FACP. Check & Record device address and location
-
Tenant Music system will cease to operate
Initiate Gas Leak Sequence, observe the following:
-
LPG Solenoid control valve Activation of the fire alarm results in Gas Solenoid valve to close
-
LPG System sounder will activate
-
Electrical power to Kitchen equipment to Cut off
-
FCUs will stop
-
Kitchen ventillation fans will stop
-
Fire Alarm will activate and all Flash sounders will operate
-
Fire status will be displayed on Tenants FACP. Check & Record device address and location
-
Tenant Music system will cease to operate
Phase 3: Interface Tenant Fire Alarm Panel with Landlord
-
Activate Tenant Fire alarm panel, observe if signal is received in Landlord FAS and unit is identified correctly
-
Landlord sends fire alarm to tenant, observe if signal is received in Tenant's FAS
-
Tenant FAS induces fault, observe if fault signal is received at Landlords FAS panel correctly
-
Name of Contractor
-
Name of Tenant
-
Landlord