Information
-
Conducted on
-
Location
-
GeoOp Job Reference no.
-
Client Name
-
Switchboard
-
Person Testing
-
Lic No
Equipment in test?
-
Multi meter
-
Megger
-
Polarity tester
-
RCD tester
Record primary results:
-
Continuity of main earth conductor (must be less than 1 ohm)
-
Continuity of Equipotential bonds
-
I.R, consumer / sub mains
-
Polarity test, consumer / sub mains
-
Begin by adding a new test
Test
-
Enter date if different to the initial Test Record
-
Pole number
-
Circuit
-
Visual Inspection (Ref Clause 8.2.1)
-
Continuity value (Ref Clause 8.3.5)
-
I.R. Value (Ref Clause 8.3.6)
-
Check Polarity? (Ref Clause 8.3.7)
-
Correct connections? (Ref Clause 8.3.8)
-
Check Fault loop impedance? (Ref Clause 8.3.9)
-
RCD test? (Ref Clause 8.3.10)
-
All testing has been carried out in accordance with AS/NZ 3000.
-
Now scroll back up to the top of this page and add the next test as required!