Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
1. SITE and DOCUMENTATION
Authority
1.1 Authority Certificates/Licences
-
b. EWP licence
-
c. Western Power authorised contractor signage displayed
-
d. First aid ticket available and in date
-
e. Construction Industry Safety card/certificate
1.2 Pre Job Planning
-
a. Has Tailgate been conducted & documented
-
b. Have all personnel who are involved in carrying out the task signed the JSA
-
c. Has JSA form been filled out correctly
-
d. Have all hazards been identified and controlled
-
e. Western Power Distribution Construction Handbook available and up to date (Reference HB1-2007)
-
f. Western Power Safety manual available
2. SAFETY EQUIPMENT AND SITE SET-UP
2.1 RTC Worksite Management
-
a. Road signs used to alert traffic of works in progress
-
b. Correct road signs/cones used
-
c. Flashing arrows used on vehicles working on road ways
-
d. Reflective vests or hi viz clothing worn by personnel working in road reserve
-
e. Traffic management personnel hold current authorisation for tasks that are being carried out
-
f. Traffic Controllers Handbook available on site
-
g. Traffic management personnel complying with Western Power PPE requirements
-
h. Worksite barriers and warning signs in place
2.2 Work Gloves
-
a. Are HV/LV gloves stored correctly when not in use. Not inside out
-
b. Correct gloves used for the task being performed
-
c. LV/HV gloves in test date
-
d. Are correct gloves worn for switching
2.3 Eye Protection
-
a. Approved safety glasses worn when working on site
2.4 Safety Helmets
-
a. Helmet has name and replacement date inside
-
b. Worn on work site
2.5 Worksite Clothing
-
a. Approved overalls/long sleeve shirt & trousers worn.
-
b. Sleeves rolled down, buttoned at cuffs and neck area when on Western Power site
-
c. Approved safety footwear worn
-
d. Fall arrest harness displaying current inspection tag.
2.6 Pole Top Rescue Kit
-
a. PTR kit used when working on or near live/de-energised LV conductors & positioned accordingly and inspected.
-
b. Observer on ground monitoring person working on live/de-energised LV
2.7 Use of Mobile Phones
-
a. Mobile phones NOT being used at the pole top
-
b. Mobile phones NOT being used when operating machinery
-
c. Mobile phones NOT being used when performing safety observer duties on live LV/HV
2.8 Use & Maintenance of Ladders
-
a. Are all ladders tied in when working on live/de-energised conductors
-
b. Are ladders mechanically stabilised or footed when ascending or descending
-
c. Are ladders in serviceable condition and have a current inspection tag attached
2.9 House Keeping
-
a. Work vehicle clean tidy and hazard free
-
b. Fuel stored correctly not near gloves and sleaves
-
c. Correct number and type of fire extinguishers on the vehicles (extinguishers within test date)
-
d. Electrical cords/equipment displaying current test tag
-
e. All chains and slings displaying SWL tag and in good condition
-
f. All live working tools and equipment within test date including earths
-
g. Are gas bottles stored correctly and hoses in good condition
-
h. Vehicle logbooks in vehicle and kept up to date
3. CIVIL CONSTRUCTION
3.1 Removal of Poles
-
a. Has hardware been removed from pole if is it logged as a risk on the JSA
-
b. Correct pulling method applied
-
c. Is the pole completely exposed if pole is to be removed by crane
3.2 Erection of Conductive poles Through Live Line
-
a. Is a Safety Observer present
-
b. Are conductors covered & stabilised if the LV/HV is live
-
c. Are the pole and crane earthed during pole installation if LV/HV is live
-
d. Pole top shroud fitted if HV is live
3.3 Handling of Treated poles
-
a. Are dusk masks worn if risk of breathing sawdust from treated poles
-
b. Are poles extracted from the ground that show signs of leeching wrapped in plastic sheeting
3.4 Excavation Work
-
a. Safety observer present if work in trench is more than 1.5m in depth
-
b. Excavation areas temporarily barricaded
-
c. Excavation shored up where required
3.5 Working Adjacent to Gas Mains
-
a. Minimum separation distance of 500mm untouched soil between any new structure and gas main
-
b. Are relevant one call plans available, in date and for the correct work area
-
c. Gas authority notified of intended work adjacent to gas mains in Albany and the Vines
-
d. If working within 15M of high pressure gas main has Alinta been notified and is there an accredited locator on site
4. WORKING AT HEIGHTS
4.1 Working From EWP
-
a. Operator/s in EWP conforming to approved procedures and tickets valid (EWP and EDD)
-
b. Approved safety harness worn correctly
-
c. EWP earthed when working in regulated area
-
d. EWP displaying current electrical test sticker or certificate
-
e. Ground observer present when working dead
-
f. SWL of the basket not exceeded
-
g. Operators inside the bucket with at least one foot on the basket floor
-
h. If operators are travelling in basket are they complying with FI 2.10.6.4
4.2 Climbing & Inspecting Poles
-
a. Has initial visual pole inspection been carried out? Including hardware, conductors and adjacent structures
-
b. Is pole to be climbed supported/reinforced.
-
c. Have correct safety checks been made prior to climbing/lowering off conductors on steel service pole
-
d. EWP used to access 150mm x 150mm wood carry over pole
-
e. Is the pole supported 4 ways if treated and over 10 years old (if not reinforced)
-
f. Is pole supported 4 ways if untreated and over 5 years old (if not reinforced)
5. LINE WORK
5.1 Line Work On Or Close To Live/De-Energised Conductors
-
a. Line sleeve/covers used to cover conductors during pole top work
-
b. Line sleeve used to cover bare s/l wire while working on live/de-energised conductors
-
c. Are approve methods used when temporarily supporting LIVE LV conductors
-
d. Safety observer present during all live/de-energised work
5.2 Dead LV Requirements
-
a. Personnel working between shorting out leads, all phases shorted out to neutral including streetlight
-
b. Shorting out leads in good condition
-
c. Disios barriered if working on the same pole (one side live)
-
d. Are Disios out side the work area and all points of isolation fitted with danger labels
-
e. All personnel signed on/off the (EAP) Electrical Access Permit
5.3 LV Aerial Bundled Cable
-
a. Are Dynamometers used in conjunction with sag charts and thermometer to tension ABC
-
b. Is radio contact between cable drum winch and observers constant during the stringing of ABC
-
c. Has temporary out of balance stay been applied where ABC meets existing conductor to counter act different loading
-
d. Are correct procedures being used when less than 4 turns remain on the drum
5.4 Stringing and Tensioning Conductors
-
a. Mains de-energised or made dead during stringing and tensioning> 1 bay of LV below HV conductors
-
b. Mains de-energised or made dead during HV stringing and tensioning over LV conductors
-
c. Mains de-energised or made dead during re regulating >1 bay of LV or HV under or over live conductors either side of work position
5.5 HV Live Line/G&B Techniques
-
a. Live Line tools/equipment within test date
-
b. Insulating barriers within test date
-
c. Safety observer appointed and watching when crew are in the contact area
-
d. VA issued and all signed on/off
-
e. Correct voltage recorded on (VA) Vicinity Access
-
f. Correct class of gloves/covers used for voltage (e.g. class4 for 33KV and class3 up to 22KV)
-
g. HV and LV insulating barriers installed as required
-
h. Conductor loading calculated
-
i. EWP boom wiped down and bucket clean
-
j. EWP/Plant Earthed correctly and earth lead in test date
-
k. Minimum approach distances maintained at all times
-
l. Conductor controlled at all times
-
m. Communication between all team members clear and precise
-
n. Correct tools and equipment used for task
-
o. Min of 150mm maintained from LV if no HV covers applied
-
p. No one accesses the EWP whilst crew in the contact area
-
q. Work site/EWP barriered off
6. UNDERGROUND WORK
6.1 LV Cable Work (UDS)
-
a. Cable identified prior to jointing by approved methods and ends marked accordingly
-
b. Working ends of cables made off and placed in mini pillars with lids painted white and labelled correctly
-
c. Approved DANGER labels fitted to UDS cabled advising other end not to be terminated
-
d. Live bus bars in kiosk either side of work position covered during LV work
-
e. Are distribution feeder cables labelled (inc. Next interconnection point) in transformer kiosk
-
f. Cables entering UDS uni pillars correctly positioned (left side/right side)
6.2 Commissioning Procedure (UDS)
-
a. Working ends of cables made off and placed in mini pillars with lids painted white
-
b. Have new cable had an insulation resistance test before energising
-
c. Drawings checked ensuring cables feeding into another scheme cannot be energised
-
d. All cable ends terminated within the UDS scheme
7. SERVICE COMMISSIONING AND TESTING
7.1 Service Cable and Meter Testing
-
a. Service cable de-energised prior to removal or reconnection of MCB (Field reference instruction FI 5.1- FI5.2)
-
b. Three man crew for service connections
-
c. Two men carrying out meter testing and both authorised
-
d. Meter testing procedure followed as per Service Connection Testing Form
-
e. Service connection test form been completed (2 signatures)
-
f. Meters and fuses sealed on completion of testing
-
g. Independent earth used when testing
-
h. Are customers with ineffective earth notified, disconnected and issued fault notice
-
i. Authorised safety observer present when re-connecting service cable
-
j. Neutral tag fitted to LV conductor
8. SWITCHING
8.1 Switching & Permits
-
a. All personnel involved in work associated with switching programme individually signed on/off the EAP, VA or sanction to test
-
b. Are personnel working on overhead conductors boxed in by portable earths
-
c. Points of isolation danger labelled
-
d. Is equipotential mat used correctly when operating PTS
-
e. Have all possible point of supply been disconnected
-
f. Switching a Authorised level (Western Power only)
9. SPRAY WASHING AND SILICON
-
a. Bare hand stick techniques used
-
b. Safety clearances adhered to
-
c. All tools and equipment in test date
-
d. Has water been tested before washing with calibrated tester
-
e. EWP earthed
-
f. (VA) Vicinity Access issued and all signed on/off
-
g. Water pressure correct (min 5600kpa max 14000kpa)
-
h. LV covers fitted when spraying HV
-
i. Current authorisation for spraying
10. PEOPLE AND BEHAVIOURS (ACTIVE 8 OBSERVATIONS)
-
Sign off by person controlling the workplace ?
-
Are employees maintaining Eyes on Path whilst moving around the worksite ?
-
Are employees Looking Before Moving ?
-
Are employees selecting appropriate Tools and Equipment and wearing correct PPE ?
-
Are employees keeping Eyes on Hands whilst doing works which could result in injury ?
-
Are employees ensuring they are not placing themselves in Line of Fire ?
-
Are employees Communicating their intent to others ?
-
Are employees using correct manual handling techniques to maintain correct Position and Effort ?
11. POSITIVE OBSERVATIONS
-
Note Positive Observations
12. AT RISK OBSERVATIONS IF IDENTIFIED
-
Note at Risk Observations
-
Provide a sketch of the area of concern if applicable to support findings
-
Provide a sketch of the area of concern if applicable to support findings
13. SIGN OFF AT COMPLETION OF SITE VISIT
-
Sign off by person controlling the workplace