Front Sheet
-
SDO
-
Has an onsite risk assessment been completed?
-
Lead Engineer
-
Team
- BC1
- BC2
- NB1
- NB2
- NB3
- NB4
- NB5
-
Location
-
Build Type
-
Has a UMJ been installed?
-
UMJ Location
-
Picture of UMJ
-
Has the box to box been completed today?
-
What has been installed today?
- Rope
- Subduct
- ULW Cable
- Blown Fibre
-
Meterage for today
-
Date
Route Information
BT Information
-
BT Portal Overview
-
NOI
-
A55's on route
-
Street Name of A55
Chamber
-
Chamber Type
- JF2
- JF4
- JF6
- JF10
- JF11
- JF12
- JRC4
- JRC11
- JRC12
- JRC14
- FW Manhole
- CW Manhole
- Lead In Duct
- Other
-
Chamber Lid Image
-
Chamber Street Name
-
Inside As Built Chamber Image
-
Close Up Picture Showing Label
-
State the Cable Type Used
- 7MM Subduct
- 7W/14MM Subduct
- 12MM Subduct
- 3W/25MM Subduct
- 9W/25MM Subduct
- 16MM Sub-Duct
- 12 Core ULW
- 24 Core ULW
- 48 Core ULW
- 96 Core ULW
Enabling Works
-
Anything extra to flag regarding installation?
-
If Yes Please State
Sign Off
Build Overview Report
-
Confirm Status
-
Total Time Spent at Job
Lead Engineer Off
-
I can confirm that all information provided is accurate to the installation works undertaken
-
Engineer Signature