Title Page
-
Client / Site
-
Block and Town house no.
-
Prepared by
Pre-start Tiling
-
Prestart Tiling works checks completed by
-
Date of completion
Pre-start checklist Bathroom shower area
Plumbing
-
Is the Allproof flange glued 25mm below the surface of the concrete floor?
-
Is the brass rose extension in place?
Substrates
Shower walls
-
Is the Gib Aqualine straight within the tolerances?
-
Are the screws in the Gib Aqualine at a maximum of100mm spacings?
-
Are the screws and sheet joints plastered?
Bathroom floor
-
Is the shower base rebate a minimum of 1025mm x 1025mm?
-
Is the concrete floor straight and within the tolerances?
-
Is the concrete floor free from cracks?
-
Is there a UFH draw wire cable present?