Title Page
-
PPM Air Conditioning Unit
-
Site Name:
-
Select date
-
Asset ID Ref:
-
Location:
-
Make:
-
External S/N:
-
Internal S/N:
-
Gas Type
- Indoor
- Outdoor
- N/A
-
Notes
-
Gas Charge
- Indoor
- Outdoor
- N/A
-
Notes
-
Duty in KW Heating
- Indoor
- Outdoor
- N/A
-
Notes
-
Duty in KW Cooling
- Indoor
- Outdoor
- N/A
-
Notes
-
Check Filters/Cleaned
- Indoor
- Outdoor
- N/A
-
Notes
-
Check Filters/Replaced
- Indoor
- Outdoor
- N/A
-
Notes
-
Check fan motors and components
- Indoor
- Outdoor
- N/A
-
Notes
-
Check compressor for undue noise and vibration
- Indoor
- Outdoor
- N/A
-
Notes
-
Check Refrigeration charge level in receiver/sight glass
- Indoor
- Outdoor
- N/A
-
Notes
-
Check Bearings & lubricate Fans//Motors/Damper Drives
- Indoor
- Outdoor
- N/A
-
Notes
-
Check of any refrigerant gas or oil leaks
- Indoor
- Outdoor
- N/A
-
Notes
-
Check Fan guard covers and inspection plates
- Indoor
- Outdoor
- N/A
-
Notes
-
Check and clean Evaporator/colis/drains/drip tray/pump
- Indoor
- Outdoor
- N/A
-
Notes
-
Check condensate drains is clear and clean
- Indoor
- Outdoor
- N/A
-
Notes
-
Check Refrigerant pipework for vibration - rectify loose/inadequate supports/fixings
- Indoor
- Outdoor
- N/A
-
Notes
-
Check flexible electrical conduit for damage
- Indoor
- Outdoor
- N/A
-
Notes
-
Isolate control panel and inspect for signs of overheating
- Indoor
- Outdoor
- N/A
-
Notes
-
Confirm that system operation is in accordance with design parametric - adjust as necessary
- Indoor
- Outdoor
- N/A
-
Notes
-
Record Temp set point
- Indoor
- Outdoor
- N/A
-
Notes
-
Ambient Temp during test
- Indoor
- Outdoor
- N/A
-
Notes
-
Internal temp during test
- Indoor
- Outdoor
- N/A
-
Notes
-
Humidity during test
- Indoor
- Outdoor
- N/A
-
Notes
-
Maximum Cooling
- Indoor
- Outdoor
- N/A
-
Notes
-
Maximum Heating
- Indoor
- Outdoor
- N/A
-
Notes
-
Clean down all surfaces of indoor and outdoor units
- Indoor
- Outdoor
- N/A
-
Notes
-
Check remote control for correct operation/replace batteries
- Indoor
- Outdoor
- N/A
-
Notes
-
Indoor Before
-
Indoor After
-
Outdoor Before
-
Outdoor After
-
Within 7 days of completing the service, submit service sheets detailing any outstanding defects to NWR Site Manager together with estimate costs to rectify any problems found.
- Indoor
- Outdoor
- N/A
-
Notes
-
Any comments/Condition report of the asset/Recommendations
- Indoor
- Outdoor
- N/A
-
Notes
-
Engineer Name: