  • Location and B Number

  • Conducted on

  • Site Check by

  • IS THIS JOB READY TO BE COMPLETED?

General Requirements

  • 1. View - Will new Controller hight block/obstruct Signage or other issue?<br>Eg check if Shark Fin install will be obstructed

  • 2. Identify on plan, lanes to be taken out

  • 3. Controller Info - Pictures to be taken (Controller Build) <br>Eg - VMS / Rapid details / pictures - Special Priority Feature

  • 4. Are Low Power Boards needed for LED Upgrade? (When existing controller is used)

  • 5. Identify the Earth Stake Location and if the Main Earth Conductor size is 6mm. Provide information.

  • 6. Identify Point of Supply Information (incl Pole or Pillar No). Pictures needed.

  • 7. Is the current mains conduit Steel or PVC?

  • 8. If recabling/changing the mains cable required, do existing conduits meet 500mm depth? Provide photos.

  • - If upgrading mains cable, what cover is over the mains conduit? Explain.

  • - Is a vac truck needed to clean out pits and conduits for upgrading the mains cable?

  • 9. Advise if new bell joint required due to direct ENERGEX feed from underground joint

  • 10. Post modification - Check cable length. If moving poles is the cable long enough to reach new position?

  • - Do the finial caps need replacing? i.e are the finials old and brittle?

  • 11. Are the current Lanterns ELV or LED?

  • 12. General Condition of Controller Base eg Does it need Dyno Bolts, On Lean. Provide information.

  • 13. Is Controller Base Pre-cast?

  • 14. If on landline - is there a Landline going into the Controller?

  • 15. Does the Controller have a Top Hat? If so what equipment is installed in it?

  • 16. Provide measurements and diagram of Shark Fin orientation.

  • 17. Is the fibre team required when changing the controller. Provide photos.

  • 18. Communications Type?

  • 19. If Optus, is the cable long enough to reach the Comms box on the side of the Controller

  • 20. Other relevant Information eg VMS, City Safe Cam, MUX, extra C/B, Generator Panel.

  • 21. Identify Broken Pits and any ASBESTOS issues

  • 22. Loops Infirmation - eg Condition of Asphalt for Loop Cutting if needed

  • 23. Is RG Tower needed to reach Mains Box when upgrading the mains?

  • 24. Check Lantern layout on new and existing plans and confirm physically on site any variation that needs to be resolved with CRU

  • 25. If QTC Controller, is the earth bridge in the E block earth terminal?

  • 26. Are the loop feeders numbered?

  • - Are all the loop feeder drain wires earthed in the controller?

  • 27. For minor mods and intersection refurbs do the streetlight poles being altered have bells or isolation points? Please explain and take photos.

  • 28. Are there holes in the poles that need to be filled? I.e from push buttons being moved

  • 29. Are pedestrian stickers above all push buttons?

  • 30. Are there any finial cap restraints missing?

  • 31. Are all audio tactile units working? If not state which poles.

  • 32. Are the conduits sealed inside the controller?

  • 33. Are there any needles in pits/gardens/footpath areas?

  • 34. Can the scope of works be completed?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.