Information
-
Location and B Number
-
Conducted on
-
Site Check by
General Requirements
-
1. View - Will new Controller hight block/obstruct Signage or other issue?<br>Eg check if Shark Fin install will be obstructed
-
2. Identify on plan, lanes to be taken out
-
3. Controller Info - Pictures to be taken (Controller Build) <br>Eg - VMS / Rapid details / pictures - Special Priority Feature
-
4. Are Low Power Boards needed for LED Upgrade? (When existing controller is used)
-
5. Earth Stake Location and Main Earth Conductor size is 6mm
-
6. Identify Point of Supply Information (incl Pole or Pillar No)
-
7. Advise if new bell joint required due to direct ENERGEX feed from underground joint<br>
-
8. Posts Mods - Check cable length if cable moves freely in Ducts and I'd no Vac needed.<br>Eg do finial caps need replacing
-
9. If recalling / changing Mains Cable required, do existing conduits meet minImum depth AS3000
-
10. Lanterns ELV or LED
-
11. General Condition of Controller Base eg Does it need Dyno Bolts, On Lean
-
12. Is Controller Base Pre-cast or not?
-
13. If on landline - is there a Landline going into the Controller?
-
14. Does the Controller have a Top Hat? If so what equipment is installed in it?
-
15. Communication Equipment in Controller including Shark Fin (including Pictures of SF) and Diagram of Position of Shark Fin
-
16. Blue Tooth - Type of Comms and If Fibre or CCTV Crew required
-
17. Communications Type
-
18. If Optus, is the cable long enough to reach the Comms box on the side of the Controller
-
19. Other relevant Information eg VMS, City Safe Cam, MUX, extra C/B, Generator Panel.
-
20. Identify Broken Pits and any ASBESTOS issues
-
21. Loops Infirmation - eg Condition of Asphalt for Loop Cutting if needed
-
22. Is RG Tower needed to reach Mains Box?
-
23. Check Lantern layout on new and existing plans and confirm physically on site any variation that needs to be resolved with CRU
-