Information

  • Location
  • Document No.

  • Audit Title

  • Project Name

  • Conducted on

  • Prepared by

  • Location
  • Personnel present during inspection

General Observations

    General Observations
  • Hazard Categories

  • Location

  • Applicable Contractor/Trade

  • Rectification Required

  • Close Out By

  • Signed off by -<br><br>Signature -

  • Additional Comments

  • Add Media/Photos

Site Compound & Signage

  • Site Identification signage- security, PPE and Toga branding in place? <br>

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial actions to be completed by.

  • Site fencing secure and stable?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial actions to be completed by.

  • Site office clearly marked and identified?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Controlled entry (e.g. 'Digi-pad' or swipe card/turnstile?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Overhead and public protection certified (e.g. Hoarding)?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Site entry register (Form 6) on-site and in use?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • First Aid location signposted and names of Toga First Aiders clearly displayed?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • First Aid kit clearly identified and adequately stocked?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Amenities adequate for the site and code compliant?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Drinking water - adequate fresh supply?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Are lighting levels acceptable throughout the site?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Is battery back up lighting installed on the site?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Access and Egress - clear designated pathways and signage?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Lasers- warning signage on site?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Designated smoking areas and signage indicating areas?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Housekeeping observation (1 = Poor, 10 = Outstanding)

  • Overall Site Housekeeping Score (1 = Poor, 10 = Outstanding)

Notice Board

  • Site Notice Board tidy and in good order?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Toga Policies and Site Rules displayed?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Emergency Evacuation Plan/ Emergency Contact List displayed on the notice board?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Toolbox Talks posted on the notice board?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Site Consultation Statement displayed, signed?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

Safety

  • Previous Site HSE Inspection displayed on the notice board and required actions closed-out?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Toga Safety Alerts displayed on the notice board?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

PPE

  • Site Induction stickers visible on worker hard-hats?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Sunscreen/UV protection readily available?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Hard Hats, Boots, Gloves in use?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • High Vis Vests/Shirts worn by all workers?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • PPE compliance with Toga Site Rules?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

Electrical & Fire

  • Fire Extinguishers or Hose Reel service identified and tagged as current?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Hot-work permit/ flashback arresters/ fire extinguisher/ clothing/ PPE?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Main Electrical Switchboard locked after hours?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Electrical sub-boards and equipment inspected, tagged as current and connected through an RCD?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Electrical extension leads tested and tagged?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Electrical lead stands isolated cables and maintain 2m minimum clearance? <br>

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

Materials

  • Hazardous Goods/Chemicals stored in a secure ventilated area?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Tools and Materials secure/stored neatly on site and not against walls or fencing?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Safety Data Sheet (SDS) available for stored materials?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

Plant

  • Plant/ Maintenance Logs/ WorkCover registration completed and inspected?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Plant has warning devices & registration where required?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Lifting Gear: Man-boxes, Cages, Bins, Chains, Slings... tagged and lifting gear register maintained?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Manual Handling, mechanical aids available for use?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Is Plant locked and secured after hours?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Is Plant & Equipment excessively loud?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

Excavations & Falls

  • Are Excavations-Services identified/ depth/ barricades/ shoring/ restricted access?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Excavation - Access and escape from adequate?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Slip and Trip hazards identified and controlled?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Reinforcing- Starter Bars protected with bar caps?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Penetrations- identified, covered and secured?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Are lift penetrations caged/ bundled at openings?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Are Ladders Industrial rated, and in good condition? (platform type preferred)

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Formwork- Are catch decks installed and minimum two plank platforms?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Scaffold handover and 30 day inspections available and current?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Toga Scaffold Coordinator appointed and nominated at site inductions?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Toga Scaffold Coordinator conducting "Monitoring" periodically on the scaffold?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Scaffold and deck edge protection - hand and mid rails, toe boards, bracing in place?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Scaffolding - Mobile - complete with guardrails, bracing and safe ladder access?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • If harnesses are being used on site, are the workers trained in harness use?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Are Safety Lines, Anchor Points adequate and installed by competent persons?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

Environment

  • Any DA/ client specific controls required and are they implemented?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Controls listed in EMP implemented?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Traffic Management Plan adequate and displayed?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Water use permit displayed where required?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Perimeter silt fencing in place and adequate?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Drains & Pits protected from potential contaminants and soil/ storm water run-off?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • External public roads and footpaths free from soil/ mud/ debris?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Dust- Water cart hosing in use to minimise dust on site?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Concrete trucks - no washout or dedicated wash out area with signage?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Paint - captive washout system and appropriate waste disposal in place?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Hazardous Chemicals stored to prevent spills- cabinets, cage, bundling?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Oil/ Fuel spills evident on site?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Toga Spill Kit & Fire Extinguishers located in appropriate areas and sign posted?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Flora- protected by Tree preservation Order identified? Street tree protection required?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Fauna- protection. If required, is this implemented?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Noise Disturbance- any noisy works/ monitoring/ complaints requiring follow-up?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

  • Recycling and Waste bins adequate and properly transported?

  • Please provide person responsible for remedial action.

  • Please provide remedial action, if appropriate.

  • Please provide date remedial action to be completed by.

10

People present during this inspection - list below

  • HSE Manager

  • Site Manager

  • Project Manager

  • Site Safety Officer

  • Site Safety Committee

  • Foreman

  • Subcontractor 1

  • Subcontractor 2

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.