Title Page
-
Work Order
-
Technician
-
Start Time
-
Mentor
-
Location
Installation Details
1.0 - Installation Type
-
Was Customer Home?
-
Ensure Life Support Status has been checked on Work Order
-
Select Installation Type
-
Like for Like Single Meter?
-
Asbestos Job?
Installation Steps
2.0 - Installation Process
-
Relevant steps that must be completed for a Successful assessment. Any steps missed will result in an unsuccessful assessment. Comments must be entered for each failed step.
-
1. Receive and Check Work Order
-
2. Prepare for Job
-
3. Check Site Details
-
4. Undertake Doorstep Protocol
-
Ensure that Life Support question was asked if customer was home
-
5. Undertake Site Hazard and Risk Asessment
-
Select Here if Job is to be UTC at this point
-
6. Site Safety Precautions
-
Access Permit Required?
-
7. Obtained Access Permit
-
8. Safe to Approach Test
-
9. Pre Commencement checks and inspections
-
10. Determine Work to be Undertaken
-
11. Perform Pre-Install Signal Test
-
12. Pre-Isoaltion Checks and Tests
-
Select Here if Job is to be UTC at this point
-
13. De-Energising Checks and Tests
-
14. Remove Existing Metering Equipment including labeling of conductors and photos
-
15. Capture Existing Equipment Details and Meter Reads
-
16. Mount Meter using appropriate Techniques
-
17. Configure and Wire Installation
-
18. Perform Verification Checks and Tests
-
19. Verify NITP Point prior to Energisation
-
20. Perform Electrical Safety Checks including Polarity and Neutral Supply Test
-
21. Test Whole Current metering installation
-
22. Validate whole current meter
-
23. Finalise and Close work order
UTC Details
Assessment Criteria and Critical Aspects
3.0 - Critical Aspects Confirmation
-
The Prospective Installer has demonstrated the Following Critical Aspects:
-
For each item, please provide notes as to what was observed and/or demonstrated to satisfy the criteria.
-
a) Inspecting and evaluating safety and functionality compliance of the meter-board accurately
-
b) Following Esablished Procedures to:<br>- Identify non-conformance situations, and if required;<br>- Obtain approval to rectify non-compliance defects
-
c) Carrying out preparation work effectively
-
f) Making power and communications connections in accordance with Manufacturers specifications and functional and regulatory requirements
-
g) Selecting meter configuration in accordance with design and tariff(s) in accordance with technical specifications and regulatory compliacnce
-
h) Reinstating supply to installation safely
-
i) Documenting metering and rectification work and notifying appropriate person(s) in accordance with established procedures
-
j) Dealing with unplanned events by drawing on essential knowledge and skills to provide appropriate solutions incorporated with the above items
Mentor Assessment Signoff and Reccomendations
4.0 - Assessment result confirmation and recommendation for approval
-
Meter Exchange has been Completed?
-
The Prospective Installer has completed the assessment:
-
Areas for prospective installer to improve
-
Add media
-
What was the UTC Category?
-
Technician Understands the NEXUS process, where the information is and who to contact for UTC's?
-
Did the technician Identify the UTC Reason appropriately?
-
Any additional comments regarding the UTC?
-
Please take photo of the Installation/UTC
-
Any additional comments to support this Mentoring Asessment
5.0 - Technician acknowledgement of Assessment
-
I acknowledge that the mentor listed above has discussed any observations and improvements for the completed work.
-
Add signature
6.0 - Mentor acknowledgement of completed Assessment
-
I acknowledge that the information listed above is true and correct and I have discussed any observations and improvements for the completed work with the technician
-
Add signature
-
When assessment is completed, please submit to the appropriate people for review, and recommendations for approval to work.