Audit date
-
Auditor
Mould prep :
-
Are the moulds at an acceptable quality standard (no chips / cracks)
-
Are the moulds included on the mould maintenance schedule?
-
CTQ - Are the GRP and Melamine mould prep processes being followed (SOP064)?
Base coat gel :
-
Is the base coat gel shelf life in date?
-
Is the catalyst set at 2% or below?
-
CTQ - Is there any contamination in the base coat gel?
-
CTQ - Are there any thin patches in the base coat gel?
-
CTQ - Blow hole sticker lifting?
-
CTQ - Edge tape lifting?
-
CTQ - Wax bead lifting?
-
Is the wet film gauge process being followed (measurements recorded on form DW094)?
SLU :
-
CTQ - Is the resin shelf life in date?
-
Is the resin pressure set between 40 psi and 45 psi
-
Is the catalyst percentage set between 1 1/4% and 2%
-
CTQ - Is the lay up sequence correct?
-
SLU quality - excessive loose fibres?
-
CTQ - SLU quality - dry glass?
-
CTQ - SLU quality - air pockets?
-
Is the skin thickness check process being followed (measurements recorded on form DW094)?
-
Has form TW196 (spray booth daily check list) been completed and up to date?
Top coat gel :
-
CTQ - Is the top coat gel shelf life in date?
-
Are there any thin patches in the top coat gel?
-
Is the catalyst set at 2% or below?
-
Excessive pinholes in the topcoat gel?
-
Are there any runs in the top coat gel?
-
Is there any contamination in the top coat gel?
Water Test :
-
Has the tank been on test for a minimum of 2 hours?
-
Has the water test section of form DW039 been completed?
Trimming :
-
CTQ - Has form DW039 been fully completed?
-
CTQ - Voids in the trimmed flange?
-
CTQ - Dry glass in the trimmed flange?
-
Has form DW039 final inspection been signed?
-
Has the final inspection QA sticker been applied to the tank?
Non-Conformance Control :
-
Are all Quarantined products identified?
-
Are all Quarantined products recorded on the Quarantine Log?