Date Of Inspection
-
Substation Name
-
Location
-
Inspectors Name
General
-
General Condition
-
Substation Access - confirm Dual Locking Arrangement
-
Site Access - 24/7 access available
-
S/S Security - UKPD /DNO locks fitted?
-
S/S Ventilation - Louvers Clear and Unobstructed
-
S/S Nameplate / Property Plate - UKPD / DNO Plates fitted? (Same site Name) + 1 x inside <br>S/S<br>
-
S/S Danger of Death Notices - Notices fitted on all approachable S/S faces?
-
S/S Door Ironmongery - Correctly applied – door stays, drop bolts etc
-
-
AC Supply Connected - Lighting & Power for indoor S/S & Some GRP’s (depends upon DNO)
-
Housing Watertight - Check for water ingress? GRP housing
-
Site Responsibility Schedule Available - Plan affixed to S/S internal wall - UKPN only
HV Switchgear - (UKPD owned HV Systems only)
-
General Condition
-
SF6 Gas Pressure - Check SF6 Pressure Gauge?
-
Switchgear Locks applied - UKPD padlocks fitted?
-
Engraved Circuit Labels - Photograph required – Photograph of RH SW Label, LH Sw Label and CB Label
HV Switchgear <br>(UKPD owned HV Plant only)
-
Relay setting sheet - on site?
-
Earth connections complete
-
Paint Condition
-
Plant Details - Photograph of rating plate required
-
Earth Fault Indicator Fitted - RH or LH SW? Reset : Man / Elec Photograph Required
Transformer
-
General Condition
-
Oil Level (Sight glass)
-
Off Load Tap changer - Tap Position
-
UKPD Switchgear Gear Locks applied - Applied to Tap changer, Voltage selector (dual Voltage)?
-
Earth Connections Complete - Check for tightness.
-
HV and LV Flange Inspection - Check for Oil Leaks RMU & LV cabinet to Transformer
-
Rating Plate Details - Photograph Required
Substation Earthing
-
Earth Bars & Earth cables
-
Neutral Earth Connection
-
Substation Bonding - Metal Doors, Louvers (Flexibles), cable tray, trunking etc
LV Cabinet, LV Boards
-
General Condition
-
Engraved circuit Destinations labels fitted - LV fuse ways, LV paralleled ways, MCCB’s and ACB’s- Photograph required
-
LV Ways Numbered (L to R) - Fit yellow numbers if no way numbers identified on the engraved labels
-
MDI Ratio & Reading - i.e. 800/1600/5?
-
LV Cabinet Earthing
-
SW Gear Locks Applied - Check UKPD SW Gear locks Applied – LV cabinet door, LV Links, metering Multicore marshalling cabinet.
MCCB / ACB
-
General Condition
-
Engraved Circuit Destinations Fitted
-
Reset Locking Bar Locked - UKPD SW Gear Lock applied
-
MCCB / ACB Protection Setting Sheet - On site
HV Cables (UKPD Owned HV Systems Only)
-
General Condition
-
HV Cable Boxes - Checked secure (all fixings applied (Nuts & Bolts)
-
HV Bending Radii - checked ok
-
HV Trenches - Open?
LV Cables
-
General Condition
-
LV Bending Radii - Checked ok
-
LV Trenches - Open?
MDI Readings
-
CT Ratio
-
L1
-
L2
-
L3
-
General Comments