Work Activity
-
Air Sampling Systems Maintenance
-
Employees on site
-
Dean Rees
-
Arrival on site
-
undefined
-
1. Park as directed by the customer, ensuring the safety of yourself, the customer, the customer's employees
-
and members of the public.
-
2. Sign in to the site or if there is no signing in/out procedure, advise the customer or the customer's
-
representative that you have arrived.
-
3. Attend the customer's induction, if required.
-
4. Obtain Permit to Work, if required.
-
5. Note access and egress routes, positions of fire extinguishers, the fire assembly point, first aid facilities and
-
welfare facilities.
-
6. Agree with the customer the working location and any measures required to prevent access by the
-
customer and other trades.
-
7. Read installation instructions, method statement, risk assessment and familiarise yourself with
-
the potential risks.
-
Personal protective equipment
-
Wear the following personal protective equipment at all times when on site:
-
1. Safety shoes conforming to EN 20345.
-
2. Hi-visibility waistcoat or coat conforming to EN 20471, with "Wagner" logo.
-
Have available and wear the following personal protective equipment as required:
-
3. Eye protection to EN 166.
-
4. Gloves BS EN 388.
-
5. Dust mask to EN 149.
-
6. Hearing protection to EN 352.
-
7. Protective overall.
-
Site Access
-
undefined
-
1. Sign required.
-
2. Carry out site induction as required.
-
Work Activity
-
undefined
-
1. Establish work area and bring through tools, materials and access equipment as required.
-
2. Service and maintenance of fire alarm system
-
3. Remove tools and any remaining equipment from site.
-
4. Sign out and leave site.
-
q
-
Experienced | Other Workers | Inexperienced | Public | Disabled
-
Yes | No
-
Yes | No
-
Contact With:
-
Yes | No
-
Yes | No
-
Yes | No
-
No
-
Yes
-
No
-
Yes
-
Yes
-
Yes
-
Yes
-
No
-
No
-
Yes
-
Yes
-
Yes
-
No
-
Yes
-
Yes
-
Yes
-
Yes
-
Yes
-
Yes
-
Method Statement
-
Risk Assessment
-
Selectable Tabs
-
Access Egress
-
Hand Tools
-
PPE
-
Site Machinery
-
Exposure to Noise
-
Lifting Equipment
-
Manual Handling
-
Portable Electric Tools
-
Work In Risers
-
Work At Height
-
MEWP
-
MEWP Pre Use
-
MEWP Rescue Plan
-
Installation of Cables
-
Slinging Loads
-
Vibratory Hand Tools
-
Reduced Oxygen Area
-
Electrical Connections
-
Lock Out Tag Out
-
Electrical Controls
-
Insurance
-
Safe Contractor
-
RAMS Acceptance
-
Emergency Procedure
-
- yes
-
- no
-
HEALTH AND SAFETY RISK ASSESSMENT RECORD
-
Risk Assessment No.: 2
-
Site: Cosmos romford
-
Activity: Use of Hand tools
-
Location: Battery testing
-
Date: 21.05.2024
-
Persons:
-
Employees
-
Other Workers
-
Public Visitors
-
Young Persons
-
Total Persons at Risk
-
Person Conducting Assessment: Shaw
-
Exposed: ALL
-
Approved by: d rees
-
RISK = Likelihood X Severity
-
Low Risk
-
Medium Risk
-
High Risk
-
Likelihood
-
Rating 1 = Very Unlikely
-
Rating 2 = Unlikely
-
Rating 3 = Likely
-
Rating 4 = Very Likely
-
Rating 5 = Almost Certain
-
Severity
-
Rating 1 = Near Hit, No First Aid Injury
-
Rating 2 = First Aid Injury or Illness
-
Rating 3 = 3 day Injury or Illness
-
Rating 4 = Major Injury or Illness
-
Rating 5 = Disabling Injury Or Fatality.
-
HAZARD
-
Factors of Harm
-
Risk
-
Likelihood
-
Severity
-
Residual Risk
-
Control Measures
-
Multiple of CONTROL MEASURES
-
Multiple of CONTROL MEASURES
-
Implemented by
-
Vibration & Noise: Hearing Protection to be worn if noise levels exceed 85Db(A). HAVS certs are in the office for all equipment that generates any form of vibration.
-
2
-
5
-
10
-
S.Lees
-
Working at Height: All platforms must be erected by PASMA trained persons, if using MEWPS, the machine must carry a valid inspection certificate, all operatives must carry a valid certificate of training, and must be competent to carry out all works associated working at height from MEWPS, safety harnesses and tool lanyards must be worn at all times.
-
3
-
5
-
15
-
D . Rees
-
Working at Height: Pop ups, all persons must be trained in the use of a Popup. All above machine, must be regularly inspected, recorded, and maintained, also must be used on level and firm ground. Ladders and Stepladders may be used at times but will be kept to a minimum. These will be inspected on a daily basis for wear and tear.
-
Poor House keeping: All walkways and work area must be cleared of debris, ensuring a high level is maintained in housekeeping policy. Barriers must not be altered in any way from a designated access route. Noise levels in the building will closely monitor and information about excessive levels will be controlled.
-
2
-
3
-
6
-
D.rees
-
Dust & Fibre Particles: Some tools and plant are fitted with dust extraction and collection devices, if these are fitted ensure they are used correctly and working. Ensure the correct type of dust mask is used properly, When drilling goggles must be worn at all times as well as dust masks.
-
2
-
2
-
4
-
D.rees
-
Failure to Wear Eye protection is to be provided and used whenever work is being carried out using cold chisels, drills, grinders or any other tool where there is a risk of flying particles or pieces of tool breaking off.
-
1
-
2
-
2
-
D.rees