Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Site Specifications
Site specification
-
Is this a LGK B/C to PFX/Icon
-
Old LGK Serial number?
-
Scraping old system on site?
-
Is this a LGK PFX to Icon
-
PFX serial number:
-
Does the Clearance Check Tool have flex tip or not?<br>If not a CCT Calibration tool must be sent to site to be used during Phase 2 of the installation.
-
Is a reload
-
Hospital Name:
-
Hospital Address:
-
Date of inspection:
-
Reason for inspection:
-
Customer Representative Signature:
-
Local Elekta Representative Signature:
-
Elekta OF Sweden Signature
Pre-Installation Administration
Pre-Installation Administration
-
Have all parties agreed on the delivery date for the unit?
-
What is the delivery date?
-
Has the rigging firm been hired and reviewed the delivery route?
-
Contact name & phone:
-
Name of rigging firm:
-
Have the owner and rigging firm discussed and agreed on the space needed for staging of equipment during deliveries?
-
Will a lockable area be available for the storage of delivered equipment and tools?
-
Has the radioactive materials license been received by the user and a copy sent to Elekta Project Manager?
-
What type of license is on hand?
-
Is the Radiation Safety Officer, or Authorized person, available to receive the radioactive material on the selected date as per the license conditions?
-
RSO Name:
-
RSO Contact #:
-
Is network information available?<br>
-
IP address for the Router :
-
Subnet mask:
-
Default gateway address:
-
Broadcast IP address:
-
Domain name:
-
DNS Server address:
-
IP addresses to all known Dicom clients that are to send images to the LGK:
-
Have the Scanner Interface Forms and Adapter Information been complete and returned to Elekta Project Manager?
FCO
-
(N/A if the site does not have any Steriotaciall Vantage systems)
-
YES if all old Vantage Fiducial Boxes AND MRI head coil adapters are replaced with latest versions, No in all other cases.
-
Is FCO 100-06-301-001 implemented?
-
-
Additional comments:
Access to Site / offloading area
Access to site / offloading area
-
Has the rigger reviewed the area designated for delivery and will that area be clean and unoccupied at delivery time?
-
Is the off loading area flat and at the same height as the entrance to the hospital building?
-
If not, who is responsible for preparing the equipment landing area for the off loading?
-
Name:
-
Contact number:
-
Date this will be done:
-
Has security been notified of the area needed, the timing and extent of the rigging operations of the equipment deliveries and pickup?
-
Has the radiation safety officer reviewed the delivery route for the cobalt, both outside and inside the building?
-
Has it been determined that the minimum dimensions of 2 meters width and 2 meter free hight (clear opening) of the delivery route have been met? No passage can be smaller then 1.9 m X 2.0 m.
-
If not, have arrangements been made to ensure that the minimum dimensions are met throughout th delivery route?
-
Have pull points been installed (Hilti HKD-SR M20×80 or equivalent) in the rigging route and treatment room?
-
Has it been determined that the delivery route can support the 18500 KG of the radiation unit, rigging equipment and personnel necessary to move the unit, (floor<br>load requirement 20 tons / m²).
-
Is there finished flooring in the delivery route and if so, has the rigger been advised and agreed on flooring protection that will be used?
-
NOTE: It is recommended that the finished flooring be in place before the delivery of he radiation unit. ( except Terrazzo or Clay Tile)
-
Has the delivery route for the reminder of the system components been determined and will it be clean and clear of obstructions on the delivery date?
-
i.e. patient couch, covers, electrical cabinets, etc
-
Is there a gradient in the delivery route?
-
Has the rigger reviewed it and made arrangements for equipment necessary to affect delivery?
-
Has security been informed and have a plan in place if parking/blocking roadways are involved?
-
NOTE: On new construction sites the entire delivery route must be clean and clear of all obstructions the day before delivery.
-
NOTE: On existing building sites, hospital personnel must be clear of the delivery route during equipment movements and any obstructions must be removed.
-
Additional comments:
Treatment Room
Treatment Room
-
Has the ECU floor box for the radiation unit been checked for correct position?
-
Has all new concrete work been complete?
-
Has the floor been checked for levelness?
-
Does the area require earth quake kit
-
If earth quake kit is to be installed, has a contractor been contacted regarding the eight 32mm diameter and 180mm deep holes needed for bolts.
-
Have the door(s) been hung and checked operational with locks to secure the radioactive material once it is on site?
-
Who will have the keys for access?
-
Contact number?
-
Are the final lighting and controls installed and operational?
-
Is HVAC system installed and operational with ducts cleaned to ensure controllable temperature = +22 to +26 °C (+15 °C to +30 °C during rigging) & humidity = less then 50% (30–75% during rigging) 24/7?
-
Elekta specify +22 to 26 °C for patient comfort & humidity less then 50% for optimum equipment operation.
-
Is the ceiling height at 2600 mm (min) to allow loading to occur inside the treatment room?
-
Are the power outlets operational in the vault?
-
Is the the site using the Nova Solutions Disconnect Panel?
-
Has a separate 3 phase and single phase disconnects been installed?
-
Has a R2 contactor been installed with helper relay (R1) and wiring to ECU floor box been installed?
-
Is R1 24VDC Relay?
-
Record the current at 24VDC or the resistance in the coil of R1
-
Record the single phase voltage
-
Record the 3 phase voltage:
-
(PAS) Does the Pause Wall Switch operate correctly? (N.O. mom)
-
Have all Pause, Emergency, Stop, and Door Switches installed prepared with 2.5 m tails pulled to the ECU box? <br>Door switch is not included on our delivery.
-
(ESS) Does the Emergency Stop wall switch operate correctly? (N.C. latching)
-
(DS1 / 2) Does the door switch/es operate correctly when treatment room doors close? (Doors closed = short)
-
(RON) Does the Radiation Warning Light operate when control wires are shorted together?
-
Record the Voltage and Current measured across RON control wires: (24vac, <1.0 amp)
-
(TRM) Confirm there is an empty 25 mm & 50 mm conduit w/pull strings from Treatment Room Monitor location to control room.
-
(USI) Confirm there is an empty 50 mm conduit w/ pull string from User Status Indicator location to Floor box under RU.
-
(CAM1) Confirm there is an empty 50 mm conduit w/ pull string from Camera location on isocenter to control room.
-
(RM) Confirm a conduit path and outlets at both ends for a customer supplied and customer installed Radiation Monitoring Device.
-
Are all electrical box covers mounted and all conduits labelled as to destination?
-
Are the pull strings installed in the conduits for Elekta installed cables?
-
If in-line pull boxes have been installed, there has to be personnel standing by to assist in the pulling of the Elekta supplied cables.
-
Has the personnel been advised if applicable?
-
Contractor name:
-
Contact number:
-
Is all the work completed in the treatment room, control room, and planning room to allow installation to take place without interruption?
-
This includes all flooring, ceiling work, cabinetry, conduits, contractor wiring, user supplied cameras, door switches, e-stops, in-room radiation monitor, data link cabling, and phone lines, etc.
-
Has the installation been discussed with the site physicist and is he/she available for acceptance testing as needed?
-
Have final floor finishes (except Terrazzo & Clay tile) been installed?
-
Additional comments:
Control Area
Control Area
-
Is all millwork/desks and furniture installed and cable passages drilled in counter tops with grommets installed?
-
NOTE: the cable passages can be drilled while the installers are on site to determine best location if the contractor will be on site during the installation.
-
Are the conduits and cable ducts installed?
-
NOTE: all conduits and cable ducts made of metal (conducting material) must be grounded.
-
Are the conduits and cable ducts clean and clear?
-
Do the cable duct covers fit correctly?
-
Are pull strings installed in the conduits that will be used for Elekta supplied cables?
-
Are the power outlets operational and in the control room?
-
Are the final floor finishes installed?
-
If not, when will this be done?
-
Are the ceiling grid and all ceiling tiles installed?
-
Is the control room dust free and cleared of debris?
-
Is HVAC system installed and operational with ducts cleaned to ensure controllable temperature = +22 to +26 °C (+15 °C to +30 °C during rigging) & humidity = less then 50% (30–75% during rigging) 24/7?
-
Elekta recommends +22 to + 26 deg for patient comfort and less than 50% humidity for optimum equipment operation.
-
Are the final lighting and controls installed and operational?
-
Are the hospital network drops installed and operational? (2 minimum)
-
If not, when will they be installed?
-
When will they be operational?
-
Is there a Wi-Fi or LAN network with internet access that our engineers can use during the installation in the control area?
-
What is the SSID (name of the network)? : What is the Password? :
-
Additional Comments:
Treatment Planning Area
Treatment Planning Area
-
Is this a upgrade from older LGP
-
Is there also a SPS installation on the same PC
-
LGP version now:
-
Database size:
-
Number of patients:
-
Is all millwork/desks and furniture installed and cable passages drilled in counter tops with grommets installed?
-
NOTE: the cable passages can be drilled while the installers are on site to determine best location if the contractor will be on site during the installation.
-
Are the hospital network drops installed and operational?
-
If not, when will they be installed?
-
When will they be operational?
-
Are the power outlets operational and in the control room?
-
Are the door(s) installed and lockable?
-
Who will have the keys for access?
-
Are the final floor finishes installed?
-
Are the ceiling grid and all ceiling tiles installed?
-
Is HVAC system installed and operational with ducts cleaned to ensure controllable temperature = +22 to +26 °C (+15 °C to +30 °C during rigging) & humidity = less then 50% (30–75% during rigging) 24/7?
-
Elekta recommends +22 to + 26 deg for patient comfort and less than 50% humidity for optimum equipment operation.
-
Are the final lighting and controls installed and operational?
-
Is there a Wi-Fi or LAN network with internet access that our engineers can use during the installation in the control area?
-
What is the SSID (name of the network)? : What is the Password? :
-
Additional Comments: