Information
-
Location
-
Conducted on
-
Prepared by
-
Person/s consulted during the inspection.
1 Use this checklist to carry out an inspection of a site or area. 2 All comments must define what is to be done , by when and be allocated to a person.
INDUCTION
-
All Inductions complete for onsite personnel ?
-
Sign in completed for for contractors and visitors currently on site ?
Pre-Start checks and Risk Assessments
-
Take 5s are being undertaken ?
-
Hazard identification is evident and appropriate controls are in place eg Correct PPE , Signs , Cones / Cone Bars , Barriers ?
-
Risk Register on site maintained and reviewed to ensure all tasks are captured ?
-
Equipment & Vehicle pre-inspection checklist completed ?
-
JSEA completed and Signed on by all workers demonstrating hierarchy of controls ?
-
Work place set up as per JSEA ?
-
Workers are following JSEA ?
Test and TAg
-
Electrical equipment inspected and tagged , list the date of last inspection ?
-
Are there any damaged leads or electrical equipment ? Are they quarantined ?
-
Power marked in orange
-
Are all electrical distribution boards securely locked at all time ?
-
Are all machines guarded and in safe working condition as per the relevant New Zealand standard ?
-
Emergency stop accessible and in working order ?
-
All lifting and working at heights equipment is listed on a register and is currently within the required inspection time-frame ? list the date of the last inspection List Date in Comments Section
-
Safe working load noted on plant used for lifting onsite and current certification up to date ( plant can mean any lift points, mezzanine floors, pallet racks and overhead, cranes. ) list last date of inspection in comments section.
Isolation's - Lock out
-
LOTO Process observed<br>- Permit understood, completed and signed on<br>- Personnel locking out has been trained<br>- Locks are locked<br>
Personal protective equipment
-
correct PPE provided and PPE Register maintained.
-
PPE worn correctly and in good condition.
-
Is PPE signage clearly visible upon entry to the site and work areas
House Keeping
-
Are floors, walkways and under benches clean and tidy
-
Are floor coverings in good condition
-
Are there any unattended pits & unprotected pits present in the work area
-
All Hand rails/guardrails are in good condition and comply with safety requirements
-
Storeroom in neat and tidy with all parts in correct location
-
All vehicles have been inspected in the month, List date of last inspection in the comments section
-
Tools , Vehicles, Plant and equipment are stored / parked appropriately
-
Hatches and lids are locked / secured from unauthorised entry
-
Grounds and fences are tidy
Traffic management
-
Image of the TMP Signage and setup on site.
-
The CAR NOTICE is on site.
-
CAR IS VALID FOR THE SITE
-
TMP. Is set up according to those TMP approved in the CAR.
-
STMS CONTACT details recorded on site.
-
Equipment and plant setup inside the TMP zones?
Sign off Audit
-
Contractor/Team Leaders signature
-
Site Supervisors signature.